United States Fidelity & Guaranty Co. v. American Blower Co.

84 N.E. 555, 41 Ind. App. 620, 1908 Ind. App. LEXIS 205
CourtIndiana Court of Appeals
DecidedApril 30, 1908
DocketNo. 6,445
StatusPublished
Cited by22 cases

This text of 84 N.E. 555 (United States Fidelity & Guaranty Co. v. American Blower Co.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Fidelity & Guaranty Co. v. American Blower Co., 84 N.E. 555, 41 Ind. App. 620, 1908 Ind. App. LEXIS 205 (Ind. Ct. App. 1908).

Opinion

Watson, J.

Appellee, plaintiff below, alleged, in substance, in its complaint, that on June 20, 1903, the Decatur Pulmbing and Heating Company entered into a written contract with the school city of South Bend, Indiana, to erect a steam heating and ventilating plant in the grammar school building then being constructed, and to furnish all material and things requisite to execute said work, said school city agreeing to pay therefor the sum of $8,669; that on the same date said heating company and the appellant herein executed a joint and several bond, made part of the complaint by exhibit, binding themselves in the sum of $4.300 [622]*622that said heating company “would, among other things, pay for all material employed, used or furnished in said work, in carrying out said contract, in erecting, constructing and installing said heating and ventilating plant and apparatus, and all attorney’s fees;” that by a written contract, executed on or about December 22, 1904, appellee agreed to furnish said heating company “f. o. b. ears at South Bend, Indiana, certain housed steel plate fans and furnishings, and certain sections, ’ ’ said heating company to pay therefor $1,036; that appellee performed all conditions of said contract by it to be performed, and furnished said fans, furnishings and heater sections; that said heating company has failed and refuses to pay appellee said $1,036; that said fans, furnishings and heater sections were used by said heating company in the construction of said heating and ventilating plant in said grammar school building; that a reasonable attorneys’ fee was $200. There was a prayer for judgment in the sum of $1,036, with interest and attorneys’ fee.

Appellant answered in three paragraphs, substantially as follows: (1) General denial. (2) Admitting the bond and contract alleged in the complaint, but setting up as a defense that subsequently thereto, “in consideration of the separate promise of the school city to pay it an additional sum of $1,300, the plumbing and heating company agreed to extend the work to be done by it, as specified in said original contract, so as to connect the old school building situate across the alley and immediately south of said grammar school building with said heating and ventilating system; that said alteration and change of said contract was made without this defendant’s knowledge or consent, and the same greatly increased the burdens of said plumbing and heating company, and was not and is not a change in the work provided for and contemplated in and by the provisions of said original contract.” And furthermore, that [623]*623said school city, by said contract, was bound to retain possession and control of twenty per cent of the contract price until the completion and acceptance of said work, and then pay the same over to said heating company, provided the terms of said contract had been performed, but that the amount retained was less than $300, which was a material alteration of the contract. (3) Relying upon the failure' of said school city to retain twenty per cent of the contract price until the completion of the work.

The errors assigned and considered in the briefs are: (1) Sustaining the demurrer to each of the second and third paragraphs of the answer; (2) overruling the motion for a new trial.

1. Appellant contends that the facts set out in the second paragraph of the answer show such an alteration of the contract, for the due performance of which it became surety, that it is thereby released from its liability. The averments are that for an additional sum of $1,300 said heating company agreed to connect this heating plant with a certain other building across the alley from said grammar school building. There are no allegations whatever to show that such extension would in any way interfere with, delay or in any manner alter or change the performance of the contract for which appellant became surety. In fact the natural deductions to be drawn from the averments of this paragraph are that this second contract is entirely separate from and independent of the agreement for which appellant became liable. The cases cited by appellant establish the rule that, in order to release the surety, there must be a change or alteration in the subject-matter of the contract. But this rule does not extend to independent contracts entered into between the same parties pertaining to additional subject-matter. Barclay v. Deckerhoof (1892), 151 Pa. St. 374, 24 Atl. 1067; Fitzpatrick v. McAndrews & Collins (1888), 12 Pa. Co. Ct. 353.

[624]*6242. Appellant further insists that it was released from liability on its bond by reason of the fact that said school city violated its contract by failing to retain in its possession and control twenty per cent of the agreed price until the completion of the work.

The bond executed by appellant was as follows:

“Now, if said principal will keep and perform said contract, and erect, construct and install said heating and ventilating plant and apparatus in and to said school building, according to the terms of said contract, and the plans and specifications made a part thereof, and fit for use and occupancy and for the purpose for which said plant and apparatus is intended, and will pay all subconti-aetors thereon and all labor and material employed, used or furnished in said work, in carrying out said contract and in erecting, constructing and installing said heating and ventilating plant and apparatus, whether the same is used or employed by or furnished to said principal or any of his subcontractors thereon, and pay for all licenses or permits for patented articles, appliances or processes used or employed thereon, then this obligation is to be null and void, else in full force and effect. All payments herein contracted to be made are to be made without relief from valuation or appraisement laws and with all attorney’s fees. ’ ’

3. It will be observed that this bond provided not only for the due performance of the contract, but it also expressly secured the payment of materialmen. In the case of School District, ex rel., v. Livers (1899), 147 Mo. 580, 49 S. W. 507, the court, speaking of a bond similar'to the one in this case, said: “The bond is dual in its nature, being for the benefit and protection of the school district against loss or damage for the nonfulfillment of their contract by the contractors, and the payment by them of laborers for work done-, and of materialmen for material furnished, rights which when once fixed could not be de[625]*625stroyed or taken away by any act of the school district.” Where such a bond has been required by statute the courts have recognized and given effect to its dual nature, and the right of a materialman to recover against the surety on a building contract is separate and independent of any right of action vesting in the obligee of such contract. Therefore alterations in the contract which of themselves might release the surety as to the obligee will not affect the right of the materialman to proceed upon the bond. Statutes requiring such bonds are for the purpose of providing security-for laborers and materialmen, and to give them protection upon which they may rely. Dewey v. State, ex rel. (1883), 91 Ind. 173, 185; Conn v. State, ex rel. (1891), 125 Ind. 514; United States, ex rel., v. National Surety Co. (1899), 92 Fed. 549, 34 C. C. A. 526; United States, etc., Guaranty Co. v. Omaha Bldg., etc., Co.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Evansville v. Verplank Concrete & Supply, Inc.
400 N.E.2d 812 (Indiana Court of Appeals, 1980)
Southwestern Sash & Door Co. v. American Employers' Ins.
20 P.2d 928 (New Mexico Supreme Court, 1933)
Cherry v. Charles Benson, Inc.
264 Ill. App. 199 (Appellate Court of Illinois, 1931)
Concrete Steel Co. v. Metropolitan Casualty Insurance
173 N.E. 651 (Indiana Court of Appeals, 1930)
Hartford Accident & Indemnity Co. v. State Ex Rel. Martin
159 N.E. 21 (Indiana Court of Appeals, 1927)
Maryland Casualty Co. v. Johnson
15 F.2d 253 (W.D. Michigan, 1926)
Park v. Brunswick-Balke-Collender Co.
209 N.W. 188 (Michigan Supreme Court, 1926)
U. S. Fidelity & Guaranty Co. v. Henderson County
276 S.W. 203 (Texas Commission of Appeals, 1925)
Webb v. Freng
194 N.W. 155 (Wisconsin Supreme Court, 1923)
State ex rel. Interstate Public Service Co. v. Lund
139 N.E. 466 (Indiana Court of Appeals, 1923)
Collins v. Tarrant County
242 S.W. 1105 (Court of Appeals of Texas, 1922)
Bankers Surety Co. v. German Investment & Securities Co.
126 N.E. 6 (Indiana Supreme Court, 1920)
Forburger Stone Co. v. Lion Bonding & Surety Co.
170 N.W. 897 (Nebraska Supreme Court, 1919)
Wilson v. Vander Molen
1918 OK 177 (Supreme Court of Oklahoma, 1918)
Standard Asphalt & Rubber Co. v. Texas Building Co.
99 Kan. 567 (Supreme Court of Kansas, 1917)
Fry v. P. Bannon Sewer Pipe Co.
101 N.E. 10 (Indiana Supreme Court, 1913)
Aetna Indemnity Co. v. Indianapolis Mortar & Fuel Co.
98 N.E. 706 (Indiana Supreme Court, 1912)
Snider v. Greer-Wilkinson Lumber Co.
96 N.E. 960 (Indiana Court of Appeals, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
84 N.E. 555, 41 Ind. App. 620, 1908 Ind. App. LEXIS 205, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-fidelity-guaranty-co-v-american-blower-co-indctapp-1908.