Hartford Accident & Indemnity Co. v. State Ex Rel. Martin

159 N.E. 21, 94 Ind. App. 531, 1927 Ind. App. LEXIS 317
CourtIndiana Court of Appeals
DecidedDecember 8, 1927
DocketNo. 12,461.
StatusPublished
Cited by3 cases

This text of 159 N.E. 21 (Hartford Accident & Indemnity Co. v. State Ex Rel. Martin) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hartford Accident & Indemnity Co. v. State Ex Rel. Martin, 159 N.E. 21, 94 Ind. App. 531, 1927 Ind. App. LEXIS 317 (Ind. Ct. App. 1927).

Opinion

Nichols, J.

This is an action by appellee, on the relation of C. M. Martin, as commissioner of drainage in charge of the construction of a public drain established by the judgment of the Newton Circuit Court, against Walter Hygema, an alleged defaulting contractor under a contract for the construction of such ditch, and appellant as the surety upon his bond in the sum of $20,000. The bond that is the basis of the action was conditioned that, “if the said Hygema should well and truly do and perform all of the acts necessary in the construction of said drain, and construct the same by furnishing all the labor and materials, and work necessary in the construction of the same and should pay all cost of labor and materials and board for laborers and complete the same within the time specified in the contract then the obligation should be void, else to remain and be in full force and effect.”

In the contract involved Hygema agreed and bound himself to pay for all materials and to pay for the board of all- laborers furnished in and about the construction of said drain. It also contained a specification that the work should remain at the risk of the contractor until its final completion and until each and every clause of the specifications should have been complied with and the work finally inspected and accepted. The’ amended complaint was answered by a general denial under which it was stipulated that all defenses of every kind and nature might be proved by defendants. There was a trial by jury which returned a verdict in favor of appellee for damages in the sum of $11,400. After appel *535 lant’s separate motion for a new trial was overruled there was judgment against the defendant Hygema and appellant for the amount of the verdict from which appellant prosecutes its separate appeal. We may say that the defendant Hygema filed his separate motion for a new trial, which was overruled, but as he does not prosecute an appeal we give it no further Attention. Appellant has assigned as error the action of the court in overruling its separate objection to appellee’s verified motion for leave to amend its complaint; in sustaining appellee’s said verified motion for leave to amend the complaint;'in overruling appellant’s motion for a new trial; and in overruling appellant’s motion to set aside the submission and discharge the jury because of improper conduct of appellee’s counsel in the presence of the jury. Under its motion for a new trial appellant has assigned 162 reasons therefor. The record in this case contains 1,140 pages, the briefs of appellant alone contain 744 pages. From such voluminous record and briefs it is difficult to make a satisfactory statement of the facts involved within proper limits, but as we understand them from the record and briefs, they are substantially and briefly as follows: One of the petitioners was the Real Estate Securities Company, from which the ditch derived its name. The work was established by the Newton Circuit Court as a new ditch under §6166 et seq. Burns 1926, but over and along a certain ditch theretofore constructed, known as the Lawlor ditch which, it sought to change, repair and clean out. The main ditch was 10 miles in length with a number of laterals thereto; it was an open ditch and the yardage to be excavated was 159,434 cubic yards; the fall of the ditch as appeared by the specifications was only one foot in every 4,000 feet over much of its course, this fall being obtáined by making the ditch deeper and deeper down stream; in times of high water, a large vol *536 ume flowed through the channel which washed the sand in from the sides and tended to fill up the ditch. The contract for the construction was first let to one Charles Hahn for $19,043; this contract was entered into in May, 1917, said Hahn giving his bond in the sum of $10,000 with the London and Lancashire Indemnity Company as surety; he did little, if any, work under his contract which required completion by December 1, 1918. On January 8, 1919, the commissioner then in charge canceled Hahn’s contract and reported such action to the court, which approved the annulment and directed the commissioner to re-let the contract, which was done on March 31, 1919, said Hygema being the successful bidder. Shortly prior to the date of re-letting the contract, at a conference between the construction commissioner then in charge, said defaulting contractor, Hahn, and a representative of the surety on the defaulting contractor’s bond, and said Hygema, it was arranged, as appellant claims, that Hygema should make his bid in his own name but for the benefit of Hahn, that his bid should be in the amortnt originally bid by Hahn, that if Hygema should be the successful bidder Hahn’s security company would pay the premium on Hygema’s bond and advance certain moneys to further the work, and that Hahn working for Hygema and under his contract should do the construction work. The contract between the commissioner then in charge and Hygema was entered into May 8, 1919, on which date Hygema as principal and appellant as surety executed the bond in suit to secure the faithful performance by Hygema of the work to be done under his contract, the conditions of which bond are more specifically set out above. The premium on such bond was paid by that surety company which as surety had executed the Hahn bond. It is claimed by appellant that it had no knowledge of what it terms the collusive and unlawful *537 triangular contract made with the knowledge and assent of the construction commissioner between its principal, the former defaulting contractor Hahn, and his surety, London and Lancashire Indemnity Company.

Work under the Hygema contract .began in the spring of 1919, and continued with many interruptions until in December, 1921, at which time Hygema removed his dredge boat and dredges and left the work uncompleted. He had at this time excavated 112,268 cubic yards, or more than two-thirds of the engineer’s total estimate. From time to time the engineer in charge made estimates of the yardage excavated on a basis of 12 cents per cubic yard instead of 10 cents, which was the estimated cost which became the basis of the contract involved, and, after these estimates were approved by the court, warrants were drawn in Hygema’s favor for 80 per cent thereof, excepting two or three instances in which the court did not allow the contractor the full 80 per cent of the estimate. The work done by Hygema was not in one continuous section, but on different parts of the ditch, while portions lying between were not excavated at all, and it is claimed that these unexcavated sections acted as a dam and held back the flow of water, thereby greatly increasing the natural fill. The contractor was very much behind with his work and did no excavating on more than two and one-half miles of it. On March 21, 1921, appellee as commissioner in charge filed with the court a report stating that, because of the substitution of materials, delay and other causes, he had annulled the Hygema contract, and the court made an order approving such annulment and directing the commissioner to re-let the contract. Thereafter on May 16, 1921, appellee as such commissioner filed a further report that Hygema had not completed the work under his contract, had removed only about one-third of the required yardage, had substituted for vitrified sewer *538

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chrysler Corporation v. The Hanover Insurance Company
350 F.2d 652 (Seventh Circuit, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
159 N.E. 21, 94 Ind. App. 531, 1927 Ind. App. LEXIS 317, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hartford-accident-indemnity-co-v-state-ex-rel-martin-indctapp-1927.