United States Ex Rel. J. Bobby Currin & Sons v. J & W Builders, Inc.

17 F. Supp. 2d 462, 1996 U.S. Dist. LEXIS 19851, 1996 WL 1044570
CourtDistrict Court, M.D. North Carolina
DecidedDecember 13, 1996
DocketCiv. 2:95CV533
StatusPublished
Cited by3 cases

This text of 17 F. Supp. 2d 462 (United States Ex Rel. J. Bobby Currin & Sons v. J & W Builders, Inc.) is published on Counsel Stack Legal Research, covering District Court, M.D. North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. J. Bobby Currin & Sons v. J & W Builders, Inc., 17 F. Supp. 2d 462, 1996 U.S. Dist. LEXIS 19851, 1996 WL 1044570 (M.D.N.C. 1996).

Opinion

MEMORANDUM OPINION

BULLOCK, Chief Judge.

Before the court is the motion for summary judgment of Defendant, 1 Hartford Accident and Indemnity Company (“Hartford”). Plaintiff, J. Bobby Currin & Sons (“Currin”), brought this action under the Miller Act, 40 U.S.C.A. §§ 270a, 270b (1986 & Supp.1996), seeking to recover $310,834.00 on Hartford’s payment bond for subcontract work performed on federal property known as the Seaforth Recreational Facility at Jordan Lake, North Carolina (“the Project”). In March 1987, J & W Builders, Inc. (“J & W”) was engaged by the Department of the Army Corps of Engineers to serve as general contractor on the Project at Jordan Lake. Hart-, ford, as surety for J & W, issued a payment bond in accordance with 40 U.S.C.A. § 270a(a) for the protection of all subcontractors and suppliers on the project. Currin completed work on the Project in March of 1988. Currin is seeking payment for additional work done beyond that required by the terms of the subcontract as a result of later discovered discrepancies in the topographical survey provided to J & W. Hartford has moved for summary judgment arguing that Currin’s claim is barred by the one-year statute of limitations under the Miller Act. Currin argues that the doctrine of equitable estoppel precludes Hartford from raising the limitations defense. For the reasons set forth hereafter, the court will grant Defendant’s motion for summary judgment and dismiss Plaintiffs complaint with prejudice as untimely filed.

FACTS

There are no material facts in dispute in this matter. Currin seeks to recover $310,-834.00 for clearing, grubbing, and grading work done as part of a subcontract entered into on June 15,1987, by and between J & W and Currin. Within two weeks of beginning work on the project, it became apparent that there were material errors in the topographical survey which ultimately required correction by the Corps of Engineers. Thereafter, and before the Corps of Engineers issued a contract modification, J & W directed Currin to continue work in accordance with the original plans and specifications.

In October 1987, the Corps of Engineers issued a modification to the original contract which the parties have referred to as “Mod-k.” Currin alleges that it has not been paid for extra work performed as a result of the errors in the original plans and specifications. Currin last performed work on the project on March 8, 1988. 2 In April 1988, J & W experienced financial difficulties and voluntarily defaulted on the project. Thereafter, Hartford arranged for a completion contractor, George W. Kane, Inc. (“Kane”), to complete the project. Both parties agree that, under the Miller Act, Currin was re *464 quired to bring an action for payment under the bond prior to March 8, 1989. Currin filed its complaint on July 11, 1995. Plainly, this filing was well outside the statute of limitations for an action on a payment bond on a federal project.

In considering Currin’s counter-defense of equitable estoppel, the court need address only those facts which arose before March 8, 1989, and which could possibly have induced Currin to miss its filing deadline. See United States ex rel. Bagnal Builders Supply Co. v. United States Fidelity and Guaranty Co., 411 F.Supp. 1333, 1336 n. 3 (D.S.C.1976). The facts reveal that Currin began submitting progress payment claims for the extra work done on the project as early as August 1987; by November 1987, due to the financial difficulties of J & W, Currin negotiated a direct payment from Hartford. By letter dated February 8, 1988, an agent from the bond claim department of Hartford wrote Currin and stated that Currin was “going to be paid for the work ... accomplished under [Currin’s] subcontract,” and that Currin would “receive fair treatment.”

After the April 1988 voluntary default of J & W, Hartford, as the surety and assignee of all of J & W’s rights, claims, and demands related to the Project, became responsible for the contract up until the time that the completion contractor, Kane, was selected on May 5,1988.

In May of 1988, Currin retained the legal services of E. Cader Howard, Esquire, and William M. Black, Esquire, of Howard, From, Stallings & Hutson, P.A. Thereafter, Currin began negotiations with Hartford for payment of claims against the original subcontract balance and for the extra work it allegedly performed. On September 3,1988, Hartford issued a check for $40,000.00 to Currin whereupon the cheek stub described the nature of payment as “on account — pending resolution of modification K Seaforth contract.” Although it is not entirely clear from the facts, taking the allegations of Currin as true, the $40,000.00 disbursement was for extra work completed by Currin under Mod-K.

It appeal’s from various correspondences (appearing as exhibits to both parties’ briefs) that there was a great deal of confusion surrounding the Seaforth project regarding which entity was ultimately responsible for payment of the subcontractors. It appears from deposition testimony that Currin regarded the government as primarily liable for the extra work accomplished because the government had admitted errors on the original plans and formalized the contract modification in the fall of 1987. The deposition testimony indicates that Currin considered the aforementioned errors in the original plan as a “design bust” which, Currin apparently believed, entitled it to payment under Mod-K directly from the government pursuant to claims for equitable adjustment.

In January 1989, Hartford sent a release to Currin for review regarding a settlement under the original contract between J & W and Currin. Nothing in the record indicates, however, that Currin was aware of the one-year statute of limitations or that Currin had spoken with Hartford about forbearance on a suit under the Miller Act in exchange for continued negotiations towards a settlement with Hartford on the alleged extra work. The statute of limitations expired on March 8, 1989. Thereafter, on April 14, 1989, Hartford settled and paid to Currin the balance on the original subcontract.

Before the running of limitations, and over the course of six years thereafter, Currin sought compensation from the government for the extra work completed under Mod-K through various claims submitted through the general contractor, Kane, in accordance with government contract regulations. In October 1992, the government filed a civil false claims action against Kane, Currin, and other subcontractors on the Seaforth project. Ultimately, the matter was settled and the government paid Currin, through Kane, $30,-000.00 in March 1995. On July 21, 1995, Currin filed the present action.

DISCUSSION

Section 270b of the Miller Act provides as follows:

Every person who has furnished labor ... in respect of which a payment bond is furnished under sections 270(a) to 270(b) of *465 this title and who has not been paid in Ml therefor before the expiration of a period of ninety days after the day on which the last of the labor was done or performed by him ... shall have the right to sue on such payment bond ....

40 U.S.C.A. § 270b(a).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zell v. Donley
757 F. Supp. 2d 540 (D. Maryland, 2010)
Datastaff Technology Group, Inc. v. Centex Construction Co.
528 F. Supp. 2d 587 (E.D. Virginia, 2007)
Millgard Corp. v. White Oak Corp.
224 F. Supp. 2d 425 (D. Connecticut, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
17 F. Supp. 2d 462, 1996 U.S. Dist. LEXIS 19851, 1996 WL 1044570, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-j-bobby-currin-sons-v-j-w-builders-inc-ncmd-1996.