United States Ex Rel. B & M Roofing of Colorado, Inc. v. AKM Associates, Inc.

961 F. Supp. 1441, 41 Cont. Cas. Fed. 77,102, 1997 U.S. Dist. LEXIS 5418, 1997 WL 193897
CourtDistrict Court, D. Colorado
DecidedMarch 17, 1997
Docket1:96-cv-00100
StatusPublished
Cited by4 cases

This text of 961 F. Supp. 1441 (United States Ex Rel. B & M Roofing of Colorado, Inc. v. AKM Associates, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. B & M Roofing of Colorado, Inc. v. AKM Associates, Inc., 961 F. Supp. 1441, 41 Cont. Cas. Fed. 77,102, 1997 U.S. Dist. LEXIS 5418, 1997 WL 193897 (D. Colo. 1997).

Opinion

ORDER ON MOTIONS FOR SUMMARY JUDGMENT

BRIMMER, District Judge.

Both interpleaded defendant Mile High Roofing Materials Inc. (“Mile High”) and defendant Amwest Surety Insurance Company (“Amwest”) filed motions for summary judgment asking the Court to determine the limits of Amwest’s liability. Use plaintiff B & M Roofing of Colorado (“B & M”) opposes Amwest’s motion. Amwest opposes Mile High’s motion.

Background

Amwest contracted with Defendant AKM Associates, Inc. (“AKM”) to provide bid, pay *1443 ment, and performance bonds for United States Government indefinite delivery, indefinite quantity (“IDIQ”) Contract No. F0561194D0003, (the “Contract”) for roofing repairs at the United States Air Force Academy (the “Academy”).

The Contract was for a one year period from March 1994, subject to options for additional years and guaranteed work between a minimum of $200,000 and a maximum of $9,000,000. A varying contract price is inherent in IDIQ contracts; as delivery orders are placed, the value of the contract rises.

At the outset, AKM, as principal, and Am-west, as surety, provided a Miller Act performance bond with a penal sum of $200,000 and a Miller Act payment bond with a penal sum of $100,000. Amwest billed and received $5,000 for these bonds.

During the first year of the Contract several delivery orders were placed and the value of the Contract exceeded $1,000,000 (the exact value is disputed). On March 2, 1995, the Academy exercised the first year option. The Academy sent a Consent of Surety form along with notice of the exercise of the first year option to Amwest. Additional delivery orders were placed during the first option year, but the Consent of Surety form was never returned.

In early June 1995, Amwest requested and received a status report from the Academy. Pursuant to this status report, Amwest billed AKM additional premiums of $17,675. In a letter to AKM, Amwest agent Doug Taylor stated that the additional premiums were “associated with the contract price of $1,081,-237.00.” Use Plf.’s Resp. Br. Ex. 9.

During this same time, the Academy began experiencing problems with AKM. AKM had fallen behind schedule and a cure notice was issued. As a result, the Academy granted an extension to AKM, giving it until October 31, 1995, to complete certain delivery orders. AKM also fell behind in its payments to subcontractors and materialmen. Eventually, these problems resulted in the Academy terminating the Contract with AKM. Consequently, the unpaid subcontractors and mate-rialmen filed this action.

Standard of Review

The specific standards for summary judgment are well recognized, and need only be briefly restated. Summary judgment is appropriate “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that the moving party is entitled to summary judgment as a matter of law.” Fed.R.Civ.P. 56(e); see also Martin v. Nannie and the Newborns, Inc., 3 F.3d 1410, 1414 (10th Cir. 1993).

Analysis

Amwest contends its liability is limited to $100,000, the stated penal sum of the Miller Act payment bond. B & M and Mile High argue that AKM and Amwest are liable for all unpaid materials and labor supplied. 1 B & M and Mile High advance two arguments: Amwest is liable under the terms of the Contract, and Amwest is hable under the equitable doctrine of quantum meruit. The Court will address each of these arguments in turn.

I. The Miller Act

It is universally accepted that the Miller Act protects subcontractors and suppliers. United States ex rel. C.J.C., Inc., v. W. States Mechanical Contractors, 834 F.2d 1533, 1537 (10th Cir.1987). The Miller Act provides an alternative remedy to the mechanics’ hen ordinarily available on private construction projects. Because a hen cannot attach to federal property, supphers of materials or labor are protected by a payment bond. J.W. Bateson Co. Inc., v. United States ex rel Bd. of Trustees of the Nat’l Automatic Sprinkler Indus. Pension Fund, 434 U.S. 586, 589, 98 S.Ct. 873, 875, 55 L.Ed.2d 50 (1978).

*1444 A. The Contract and the Bonds

In analyzing the extent of Amwest’s liability, the Court must divine the meaning of the Contract and the payment bond. 2 In re Sinking of M/V Ukola, 806 F.2d 1, 4-5 (1st Cir.1986). Amwest’s liability must be determined by reading the Contract, payment bond, Miller Act, and any applicable regulations. St. Paul Fire and Marine Ins. Co. v. Commodity Credit Corp., 474 F.2d 192, 199-200 (5th Cir.1973). Interpreting the language of the Contract and payment bond is important because the parties disagree both as to payment bond’s penal sum and the duration of its coverage.

1. The Penal Sum

From the outset, both AKM and Amwest were put on notice that the Contract was “an Indefinite Delivery, Indefinite Quantity (IDIQ) contract----” Contract at 3. Under the section entitled “BONDS,” the Contract states that AKM and Amwest “should consider the cumulative effects of Delivery Orders (DO) placed against this contract ... in determining total bonding liability and costs.” Contract at 4. 3

After notifying AKM and Amwest that the Contract is an IDIQ contract, the Contract clearly obligates AKM and Amwest to determine their own total bonding liability. The Contract also unambiguously instructs AKM and Amwest that total bonding liability (for both the performance and payment bonds) is calculated by adding the total value of the delivery orders that have been placed.

This provision that automatically increases the bonding liability when additional materials or labor is supplied is uniquely suited to IDIQ contracts for three reasons. First, requiring automatic increases in bonding protection each time the Contract price increases is efficient. It obviates the need for the Academy to require additional bonding protection each time supplies are provided. Second, this provision forces the parties that are best able to monitor increases in the Contract’s value to ensure that the bonds protect materialmen by placing the ultimate responsibility on the prime contractor and surety. Asking the Academy to protect suppliers would have been illogical, as the federal government cannot be held liable for failing to require adequate bonding protection. See Arvanis v. Noslo Engineering Consultants, Inc.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

US Ex Rel. King Mountain v. Rb Constructors, LLC.
556 F. Supp. 2d 1250 (D. Colorado, 2008)
United States v. Coleman
200 F. Supp. 2d 561 (E.D. North Carolina, 2002)
US EX REL. VIRG. BEACH MECH. v. SAMCO Const. Co.
39 F. Supp. 2d 661 (E.D. Virginia, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
961 F. Supp. 1441, 41 Cont. Cas. Fed. 77,102, 1997 U.S. Dist. LEXIS 5418, 1997 WL 193897, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-b-m-roofing-of-colorado-inc-v-akm-associates-cod-1997.