United States Ex Rel. AWL Industries, Inc. v. Site Remediation Services Corp.

92 F. Supp. 2d 132, 2000 U.S. Dist. LEXIS 4811, 2000 WL 381594
CourtDistrict Court, E.D. New York
DecidedApril 10, 2000
DocketCV 98-7082
StatusPublished
Cited by5 cases

This text of 92 F. Supp. 2d 132 (United States Ex Rel. AWL Industries, Inc. v. Site Remediation Services Corp.) is published on Counsel Stack Legal Research, covering District Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. AWL Industries, Inc. v. Site Remediation Services Corp., 92 F. Supp. 2d 132, 2000 U.S. Dist. LEXIS 4811, 2000 WL 381594 (E.D.N.Y. 2000).

Opinion

OPINION

WEXLER, District Judge.

This is a case brought pursuant to the Miller Act, 40 U.S.C. § 270b, to collect on a payment bond issued in connection with a construction project that took place at the Brookhaven National Laboratory (“BNL”). The use plaintiff, hereinafter referred to as the plaintiff, is AWL, Industries, Inc. (“AWL”). 1 AWL seeks to recover payments allegedly due pursuant to its subcontract with Site Remediation Services, Inc. (“SRS”), the general contractor on the BNL construction project.

AWL commenced this action against SRS and its payment bond surety, United Pacific Insurance Company, to collect in excess of $200,000 AWL claims due for work, labor and services. After being sued by AWL, SRS asserted counterclaims against AWL’s surety, General Accident Insurance Company of America (“General Accident”). In response to the counterclaim, AWL and General Accident (hereinafter referred to collectively as AWL) asserted several affirmative defenses.

Presently before the court are cross-motions for summary judgment. SRS moves for summary judgment dismissing AWL’s second affirmative defense. AWL opposes the motion and cross-moves to dismiss SRS’s counterclaim for common law delay damages. For the reasons that follow, both motions for summary judgment are denied.

BACKGROUND

I. The Parties, the Prime Contract and the Subcontract

As noted above, AWL seeks payment for work, labor and services performed in connection with a construction project at BNL (the “Project”). SRS, as the general contractor on the Project, entered into a contract with the United States, acting through the General Services Administration (“GSA”), to perform the Project (the “Prime Contract”). The Prime Contract originally required completion of the Project by June 80, 1998. The contract was subsequently modified by agreement of the parties thereto to establish a completion date of July 31, 1998. Failure to complete the Project by that date was to result in assessment of liquidated damages against SRS, on a daily basis, beginning on August 3, 1998.

After SRS entered into the Prime Contract, it entered into a subcontract with AWL to perform certain heating, ventilation and air-conditioning work at the Project (the “Subcontract”). The total amount that was to be paid to AWL under the Subcontract was $569,239. AWL alleges, and SRS does not dispute, that to date AWL has been paid only $284,195.

II. The Liquidated Damages Clauses

The Subcontract contains two clauses that refer to liquidated damages. It is these clauses that are the subject of disagreement between the parties. One clause appears in paragraph 4.6 of the Subcontract; the other appears in Attach *134 ment A to the Subcontract. Before turning to the precise language of each clause, the court observes that the Subcontract is a form that is suitable for use with all subcontractors performing work for SRS. Attachment A is the rider attached to all such forms which differentiates each form subcontract from the others. Thus, the Subcontract contains general language applicable to all subcontracts entered into between SRS and its various subcontractors. Attachment A specifies the work to be done by each individual subcontractor— in this case, it specifies the precise work to be done by AWL.

The liquidated damages clause appearing in paragraph 4.6 of the Subcontract (“Paragraph 4.6”) appears as part of Article 4 of the Subcontract, entitled “Changes and Delays.” Paragraph 4.4 of the Subcontract (“Paragraph 4.4”) establishes that time is of the essence and that the subcontractor’s work must be performed “on or before the time period specified in Attachment A.” Paragraph 4.6, entitled “Liquidated Damages,” states that if the subcontractor fails to complete the subcontracted work:

within the time agreed to in the Contract Documents 2 or within such extended time granted as provided in the Contract Documents, SRS shall withhold ... payment as liquidated damages in accordance with the following schedule:

Paragraph 4.6 does not contain a schedule of liquidated damages payments. Instead, the Subcontract refers the reader to Attachment A for the schedule of liquidated damages.

Attachment A of the Subcontract, to which Paragraphs 4.4 and 4.6 refer, contains the following language (in paragraph 11) concerning liquidated damages:

If the time of completion extends beyond March 15, 1998 liquidated damages will be incurred at the rate of $2000/day.

Thus, paragraph 11 of Attachment A supplies the information needed to “fill in the blanks” created by Paragraphs 4.4 and 4.6 of the Subcontract. The parties added handwritten material above Paragraph 4.6.

That handwritten material states:

Liquidated damages shall only be assessed against AWL if the owner makes claim for liquidated damages against SRS and if the delays are directly attributable to AWL.

III. The Parties’Motions

A. SRS’s Motion For Summary Judgment Dismissing AWL’s Second Affirmative Defense

In its affirmative defenses to SRS’s counterclaims AWL asserts, as its second affirmative defense, that any recovery of liquidated damages is limited to liquidated damages assessed against SRS by the owner of the project. SRS moves for summary judgment dismissing this affirmative defense.

In support of its claim that the second affirmative defense is viable, AWL relies upon the handwritten rider to Paragraph 4.6, referred to above, which expressly limits the ability of SRS to collect liquidated damages from AWL to those cases where the owner assesses such damages from SRS. AWL argues that this handwritten material applies to any and all claims for liquidated damages that may be assessed against AWL by SRS.

SRS interprets the liquidated damages language differently. SRS argues that AWL bound itself to two separate liquidated damages clause. First, the clause in Paragraph 4.6, referring to cases where liquidated damages are assessed by the owner against SRS and SRS seeks to pass on such assessment to AWL. Second, AWL is argued to be bound to a separate liquidated damages clause appearing in paragraph 11 of Attachment A, which obligated AWL to finish its part of the Project by March 15, 1998 or be assessed liqui *135 dated damages at the rate of $2,000 per day.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
92 F. Supp. 2d 132, 2000 U.S. Dist. LEXIS 4811, 2000 WL 381594, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-awl-industries-inc-v-site-remediation-services-nyed-2000.