United Power Ass'n v. Moxness

267 N.W.2d 814
North Dakota Supreme Court·Decided July 12, 1978·No. Civ. 9449·Published·Cited by 10 cases

Opinions

PEDERSON, Justice.

The appeal and cross-appeal from part of an order in an eminent domain proceeding (a consolidation of separate suits from Sargent and Richland Counties) involve awards of costs, fees (including attorney fees), and expenses to landowners (§§ 32-15-32 and 32-15-35, NDCC). Sums awarded as appraisal fees are not challenged. We reverse and remand for further proceedings.

The events which bear upon the principal dispute here are as follows:

(1)Before January 1975

United Power Association and Cooperative Power Association (hereinafter UPA-CPA), Minnesota cooperative corporations engaged in generating and transmitting electrical power for distribution in Minnesota and Wisconsin through distributing cooperatives, made plans to construct a major electric generating plant at Coal Creek in McLean County, North Dakota. Also planned was a high voltage, direct current transmission line to deliver the electric power generated at Coal Creek to a distribution terminal at Dickinson Substation in Wright County, Minnesota. A major part of the generating plant was constructed before January 1975, but right-of-way for the transmission line across Sargent and Richland Counties had not been acquired.

(2) April 1975

The North Dakota Legislature enacted as an emergency measure (effective April 9, 1975) the North Dakota Energy Conversion and Transmission Facility Siting Act (Chapter 436, S.L.1975 — now Chapter 49-22, NDCC), which provides in part that:

“No utility shall begin construction of an energy conversion facility or transmission facility in the state, or exercise the right of eminent domain in connection with such construction, without first having obtained a certificate of site compatibility issued with respect to such facility by the [Public Service] commission . . . .” Section 49-22-07, NDCC.

Some provisions of the Act did not become effective until implementing rules and regulations were adopted.

(3) November 1975

UPA-CPA instituted eminent domain proceedings (without first having obtained a certificate of site compatibility) to acquire right-of-way from the landowners involved in this appeal.

(4) March 1976

The Public Service Commission (hereinafter PSC) determined, after holding extensive hearings (in which the landowners involved in this appeal participated), that it had jurisdiction over the UPA-CPA transmission line pursuant to Chapter 49-22, NDCC. The PSC ordered that UPA-CPA not commence construction of the transmission line without first obtaining PSC authority. That order was not appealed.

(5) December 1976

UPA-CPA applied for a route permit and construction authorization from the PSC and, after extensive hearings (in which the landowners involved in this appeal again participated), the authority was granted. The route finally authorized by the PSC [816]*816contained numerous variations from that initially proposed by UPA-CPA. Authority was granted to construct the line on lands owned by persons who we will call the “Wetherbee group.” Authority was not granted to construct the line on lands owned by persons who we will call the “Moxness group.”

(6) July 1977

UPA-CPA applied to the district court for a dismissal of the eminent domain proceedings against the Moxness group of landowners, acknowledging in its application “. . . that the dismissal . shall be subject to a determination by this court as to court costs, expenses and fees, including reasonable attorney’s fees to said defendants by reason of the dismissal of this action against them.” The Moxness group of landowners moved that the court award them costs, fees and expenses pursuant to the provisions of § 32-15-35, NDCC.

(7) August 1977

UPA-CPA and the Wetherbee group of landowners reached agreement concerning the amount of compensation to be awarded for the right-of-way taken, but left unresolved the amount of costs to be recovered by the landowners under § 32-15-32, NDCC.

(8) September 1977

The trial court ordered UPA-CPA to pay to both groups of landowners, costs, fees and expenses based in part upon their participation in the jurisdictional hearings (referred to in item (4) above), and in the site location hearings (referred to in item (5) above). Attorney fees awarded to the Wetherbee group of landowners were based upon contingent fee contracts. Attorney fees awarded to the Moxness group of landowners were not based upon an hourly rate.

UPA-CPA, in this appeal, contend that:

(1)Section 32-15-35, NDCC, does not permit landowners to recover attorney fees incurred by them in connection with PSC proceedings under Chapter 49-22, NDCC.

(2) Section 32-15-35, NDCC, does not permit landowners to recover personal expenses and loss of time incurred by them in connection with PSC proceedings under Chapter 49-22, NDCC.

(3) Section 32-15-35, NDCC, does not permit landowners to recover attorney fees based upon other than an hourly rate.

(4) Section 32-15-32, NDCC, does not permit landowners to recover attorney fees based upon contingent fee contracts.

Jelinek, in cross-appealing, argues that the trial court arbitrarily reduced the costs awarded without a basis therefor in the record.

Reasonableness of the amounts awarded for costs and attorney fees is an issue of fact and we do need to know the basis of the trial court’s determinations, whether we apply the standard of “clearly erroneous” from Rule 52(a), NDRCivP, or the standard of “abuse of discretion.” See the discussion on this subject in City of Bismarck v. Thom, 261 N.W.2d 640, 647 (N.D.1977). From the trial court’s memorandum opinion and the affidavits on file, we are made aware of the basis for the awards made in this case. It is obvious that attorney fees and other costs and expenses were, in part, based upon participation in jurisdictional and site location hearings conducted by the PSC. In addition, we learn that the basis of some of the costs and expenses was “loss of time” rather than actual “out-of-pocket payments.”

I.

The Moxness group of landowners, as well as the Wetherbee group, and Jelinek (on his cross-appeal), all argue that they were compelled to participate in PSC proceedings under Chapter 49-22, NDCC, in order to protect their interests. Their contention appears to be that PSC hearings on jurisdiction and site compatibility have really become a part of, or have replaced, judicial determination of use and necessity under Chapter 32-15, NDCC.

Section 49-22-16(1), NDCC, provides, in part:

[817]*817“The issuance of ... a transmission facility permit and subsequent . . . use of such . . . route locations for transmission facilities shall, subject to subsections 2 and 3, be the sole site approval required to be obtained by the utility.” [Emphasis supplied.]

If PSC hearings to determine “sole site approval” are a part of, or substitution for, the judicial determinations of use and necessity under § 32-15-05, NDCC, it would logically follow that those costs recoverable under either § 32-15-32 or § 32-15-35, NDCC, should include the costs incurred by landowners who participate in those PSC hearings.

Free access — add to your briefcase to read the full text and ask questions with AI

United Power Ass'n v. Moxness, 267 N.W.2d 814 (N.D. 1978).

267 N.W.2d 814 (United Power Ass'n v. Moxness) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

MDU v. Behm
2020 ND 234 (North Dakota Supreme Court, 2020)
Klinger v. Adams County School District No. 50
130 P.3d 1027 (Supreme Court of Colorado, 2006)
Cassady v. Souris River Telephone Cooperative
520 N.W.2d 803 (North Dakota Supreme Court, 1994)
Gissel v. Kenmare Township
512 N.W.2d 470 (North Dakota Supreme Court, 1994)
Welsh v. Alumni Ass'n of the North Dakota State School of Science
381 N.W.2d 199 (North Dakota Supreme Court, 1986)
In Re Condemnation Proceeding for the Wilmarth Line of the CU Project
380 N.W.2d 127 (Court of Appeals of Minnesota, 1986)
Arneson v. City of Fargo
331 N.W.2d 30 (North Dakota Supreme Court, 1983)
United Power Ass'n v. Moxness
267 N.W.2d 814 (North Dakota Supreme Court, 1978)