In Re Condemnation Proceeding for the Wilmarth Line of the CU Project

380 N.W.2d 127, 1986 Minn. App. LEXIS 3891
CourtCourt of Appeals of Minnesota
DecidedJanuary 14, 1986
DocketCO-85-874
StatusPublished
Cited by1 cases

This text of 380 N.W.2d 127 (In Re Condemnation Proceeding for the Wilmarth Line of the CU Project) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Condemnation Proceeding for the Wilmarth Line of the CU Project, 380 N.W.2d 127, 1986 Minn. App. LEXIS 3891 (Mich. Ct. App. 1986).

Opinion

OPINION

FOLEY, Judge.

Appellants, Cooperative Power Association and United Power Association, appeal from that part of a judgment granting respondents attorney’s fees and costs of $340,450.84, following appellants’ dismissal of condemnation proceedings. Appellants argue that the trial court misconstrued Minn.Stat. § 117.195, subd. 2 (1982) by awarding fees to counsel who represented a nonprofit corporation, Southern Landowners’ Alliance of Minnesota, Inc. (SLAM), rather than individual landowners, by awarding fees in excess of respondents’ contractual obligation with their attorney and by awarding fees for administrative proceedings not part of the condemnation proceedings. We affirm.

FACTS

The condemnation proceedings for construction of the Wilmarth Line in southern Minnesota commenced in May 1979 with appellants’ filing of a petition for eminent domain. Appellants sought right-of-way easements for a 76-mile, 1000 megawatt transmission line known as the Wilmarth Line. The Southern Landowners’ Alliance of Minnesota, Inc. was organized as a nonprofit corporation in May 1979. SLAM, consisting of various affected landowners, hired St. Paul lawyer Kenneth E. Tilsen to challenge the condemnation petitions. Til-sen obtained authorization forms from about 170 landowners before commencing representation of thése landowners. Tilsen represented the interests of the affected property owners at various proceedings over the course of five years. He only formally represented SLAM as an inter-venor at administrative proceedings before the Minnesota Energy Agency. Tilsen’s work included preparation and participation at the following:

1. Proceedings before the district courts in Blue Earth, LeSueur, Sibley and Scott Counties where condemnation petitions had been filed against landowners.

2. Proceedings before the Minnesota Supreme Court in Cooperative Power Association v. Eaton, 284 N.W.2d 395 (Minn.1979).

3. Proceedings before a special three-judge panel appointed by the Minnesota Supreme Court in Eaton, to handle litigation relative to the Wilmarth Line.

4. Proceedings before the Minnesota Supreme Court in In Re Wilmarth Line of CU Project, 299 N.W.2d 731 (Minn.1980) (Wilmarth I).

5. Reconvened proceedings (contested case hearings) before the Minnesota Energy Agency (MEA), as directed by the Minnesota Supreme Court in Wilmarth I and as ordered by the three-judge panel to determine the need for a high transmission line.

After the MEA found that no need existed for 1000 megawatts of power in appel *129 lants’ system, appellants filed notices of discontinuance and dismissal, dismissing the condemnation actions against all respondents-landowners, on or about December 2, 1983. In January 1984, respondents-landowners moved the court overseeing these condemnation proceedings for attorney’s fees and costs as allowed in Minn. Stat. § 117.195, subd. 2 (1982). Filed with the motion for fees and expenses were six notices of discontinuance and dismissal received by attorney Tilsen for respondents in Blue Earth, Carver, LeSueur, Scott and Sibley Counties.

At the hearing on this motion, attorneys for each party and their expert witnesses testified as to a reasonable fee, an appropriate hourly rate, and the hours expended in the condemnation proceedings. Respondents submitted the briefs Tilsen had prepared for the two Minnesota Supreme Court proceedings, a summary of proceedings regarding the Wilmarth Line, a reconstructed time record, a statement of amounts received, his own affidavit and deposition regarding these matters, the decisions of the courts and the Minnesota Energy Agency, and other materials. Appellants submitted SLAM’S articles of incorporation, affidavits of attorneys regarding a reasonable fee and other materials. In addition, both parties briefed the issues.

The trial court found that attorney Tilsen represented 170 landowners and SLAM (which it found was composed of landowners affected by the condemnation proceedings) in district court, supreme court and agency proceedings relative to the proposed Wilmarth Line; that counsel agreed to represent SLAM as a community service with fees to be based on a minimum amount to cover expenses; that he received $25,349.16 from SLAM for fees and expenses — the total sum raised by that organization; that compensable time was 2960 hours (2904 for legal services and 56 hours for travel); and that a reasonable fee for his legal services was $125.00 an hour and $50.00 an hour for his travel time.

The trial court concluded that Tilsen represented “owners” within the meaning of Minn.Stat. § 117.195, subd. 2; that his reasonable compensation was not limited to the fee arrangement he had with respondents; that the reconvened MEA proceedings were an inherent part of the condemnation proceedings in this matter; and that Tilsen was entitled to reasonable attorney’s fees and costs in the amount of $340,-450.84.

ISSUES

1. Did the trial court err in concluding that counsel represented “owners” within the meaning of Minn.Stat. § 117.195, subd. 2?

2. Did the trial court err in its award of fees and expenses to counsel?

3. Were the reconvened proceedings before the MEA a part of the condemnation proceedings?

ANALYSIS

1. “Owners” Represented:

The statute at issue here is Minn.Stat. § 117.195, subd. 2 (1982) which states in part:

When the proceeding is dismissed for nonpayment or discontinued by the petitioner, the owner may recover from the petitioner reasonable costs and expenses including attorneys’ fees.

Minn.Stat. § 117.025 (1982) defines owner as follows:

“Owner” includes all persons interested in such property as proprietors, tenants, life estate holders, encumbrancers, or otherwise.

Appellants, the utility cooperatives who sought condemnation of certain land to construct a high voltage power line, discontinued and dismissed the petitions filed against respondents-landowners. The respondents, landowners whose land was directly affected by the condemnation proceedings, sought “reasonable costs and expenses, including attorneys’ fees” under Minn.Stat. § 117.195, subd. 2.

On appeal, appellants claim that respondents may not recover fees for work per *130 formed by attorney Tilsen since he did not represent individual landowners, but rather he represented SLAM, a nonprofit corporation that owns no land. Appellants note that Tilsen had a fee arrangement with SLAM, but not with landowners. They further assert that Tilsen admitted that he had no expectation of payment from individual landowners.

The trial court found:

Kenneth E. Tilsen, Attorney at Law, represents approximately 170 landowners and the Southern Landowners’ Alliance of Minnesota, Inc. (S.L.A.M.). S.L.A.M.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
380 N.W.2d 127, 1986 Minn. App. LEXIS 3891, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-condemnation-proceeding-for-the-wilmarth-line-of-the-cu-project-minnctapp-1986.