Union Pacific Railroad Company v. Chicago, Milwaukee, St. Paul And Pacific Railroad Company

549 F.2d 114, 1976 U.S. App. LEXIS 5670
CourtCourt of Appeals for the Ninth Circuit
DecidedDecember 29, 1976
Docket75-1441
StatusPublished
Cited by9 cases

This text of 549 F.2d 114 (Union Pacific Railroad Company v. Chicago, Milwaukee, St. Paul And Pacific Railroad Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Union Pacific Railroad Company v. Chicago, Milwaukee, St. Paul And Pacific Railroad Company, 549 F.2d 114, 1976 U.S. App. LEXIS 5670 (9th Cir. 1976).

Opinion

549 F.2d 114

UNION PACIFIC RAILROAD COMPANY, a corporation, and
Oregon-Washington Railroad & Navigation Company, a
corporation, Appellants,
v.
CHICAGO, MILWAUKEE, ST. PAUL AND PACIFIC RAILROAD COMPANY, a
corporation, Appellee.

No. 75-1441.

United States Court of Appeals,
Ninth Circuit.

Dec. 29, 1976.

Randall B. Kester (argued), Portland, Ore., for appellants.

J. Laurence Cable (argued), Portland, Ore., for appellee.

Before TRASK and GOODWIN, Circuit Judges, and JAMESON,* District judge.

GOODWIN, Circuit Judge.

The Union Pacific Railroad Company appeals a judgment of the district court, following a decision that a contract between the Union Pacific and the Chicago, Milwaukee, St. Paul and Pacific Railroad Company (the Milwaukee) terminated when the connecting tracks were removed. We affirm.

In 1910, the predecessor to the Union Pacific (the Oregon-Washington Railroad & Navigation Company) entered into three trackage agreements with the predecessor to the Milwaukee (the Chicago, Milwaukee & Puget Sound Railway Company).1 These contracts provided for the construction and operation of a continuous railroad system running from Morengo, Washington, through a depot in Spokane, Washington, to a point called Northern Pacific Crossing which is located in the eastern part of Spokane. A fourth contract executed in 1913 provided for the joint use and operation of terminal facilities in downtown Spokane.

The tracks were divided into three sections, each to be covered by a separate contract.

The Spokane-Morengo joint contract provided for the construction and maintenance of the western section of the line. Pursuant to this agreement, the Union Pacific constructed some 60 miles of track which ran from Morengo to Monroe Street in Spokane. The Union Pacific also had a continuing duty to maintain these tracks. The Milwaukee obtained an irrevocable right to use this section of track in exchange for making two payments. The payment here in issue is the so-called "rental payment", which was based upon a percentage of the capital expenditures made by the Union Pacific in constructing the tracks. This payment was to continue for 999 years whether or not the Milwaukee actually used the tracks. A second payment, not here in issue, was based upon actual usage of the tracks.

The Center Street-Northern Pacific Crossing joint contract provided for the construction and maintenance of the eastern section of the line. Under this contract, the Milwaukee was to construct a line connecting Center Street in downtown Spokane with the Northern Pacific Crossing. The Union Pacific was given an irrevocable right to use this line in exchange for the rental and usage payments. Except for the change in the positions of the parties and the obvious differences necessitated by geography, the terms of this contract are identical to those contained in the Spokane-Morengo Agreement.

The third contract, called the Union Terminal contract, provided for the construction and use of the center portion of this line. These central-city tracks connected with the Spokane-Morengo Line on the West and with the Center Street-Northern Pacific Crossing Line on the East. This agreement, which was of indefinite duration, provided for the joint ownership and construction of this section of the track and for the terminal facilities.

Three years later, after all the tracks had been constructed, the parties consummated the Union Depot contract which governed use of the terminal facilities. This agreement was also of indefinite duration and was terminable by either party upon a notice of one year.

In the late 1950's public pressure forced the two railroads to consider abandoning their jointly owned central-city tracks and terminal facilities in order to make the land available for a civic river-beautification project.

The plans for Expo '74 in Spokane intensified the public pressure for the city to acquire this land, and negotiations between Spokane and the railroads were accelerated. As time passed, city condemnation of the tracks appeared imminent. In the end, the railroads abandoned the tracks and related facilities between Monroe Street and the Northern Pacific Crossing, and the land was conveyed2 to the City of Spokane for adequate consideration. The City then removed the tracks, supporting structures, and other facilities. The City also condemned the eastern 300 feet of the Spokane-Morengo Line because the removal of the other tracks had left an unsightly dead-end bridge 80 feet in the air over Monroe Street.

The Union Pacific continues to use the western part of the Spokane-Morengo Line. At Fish Lake, which is located some 47 miles east of Morengo, the Union Pacific has constructed a spur line which connects with the tracks of the Burlington Northern. The Burlington Northern line provides an alternate route to the Northern Pacific Crossing and the Union Pacific now routes its traffic over this alternate route. The section of the Spokane-Morengo line between Fish Lake and a point some 300 feet west of Monroe Street is not currently in use, but these tracks are still maintained by the Union Pacific. The Union Pacific has an option to lease this land to the City after the issues in the present lawsuit are resolved.

The Milwaukee discontinued its use of any part of the Spokane-Morengo Line as early as 1961. Until 1972, however, it continued to pay the contract rental of $167,000 a year. Then, in December of 1971, the Milwaukee notified the Union Pacific that it was terminating the Spokane-Morengo Contract because of material changes in circumstances since the consummation of the agreement.

The Union Pacific brought this action to seek a declaration of its rights under the Spokane-Morengo Agreement. At trial, the Union Pacific contended that because all but 300 feet of the Spokane-Morengo Line was still in place and serviceable, the Milwaukee should continue to make full rental payments. The Union Pacific characterizes the rental payment as an interest payment which was to reimburse the Union Pacific for its construction costs. As its investment in the line is fully executed, the Union Pacific argues that the duty of the Milwaukee to make these interest payments is absolute. Alternatively, the Union Pacific argues that any termination of the contract should operate pro tanto. That is, the Milwaukee should at least be required to pay rent upon the tracks running from Morengo to Fish Lake (with connections via the Burlington Northern to Northern Pacific Crossing).

The trial court held that since the parties contemplated the existence of a continuous railroad system when they entered into these agreements the continued existence of that system was an implied condition of the Milwaukee's duty to make rental payments. The court ruled that when the connecting tracks were conveyed to the City of Spokane (and subsequently removed) the parties' rights and obligations under the Spokane-Morengo Contract terminated.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
549 F.2d 114, 1976 U.S. App. LEXIS 5670, Counsel Stack Legal Research, https://law.counselstack.com/opinion/union-pacific-railroad-company-v-chicago-milwaukee-st-paul-and-pacific-ca9-1976.