Contractors Equipment Maintenance Co. v. Bechtel Hanford, Inc.

514 F.3d 899, 2008 U.S. App. LEXIS 1332, 2008 WL 191663
CourtCourt of Appeals for the Ninth Circuit
DecidedJanuary 24, 2008
Docket06-35310
StatusPublished
Cited by3 cases

This text of 514 F.3d 899 (Contractors Equipment Maintenance Co. v. Bechtel Hanford, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Contractors Equipment Maintenance Co. v. Bechtel Hanford, Inc., 514 F.3d 899, 2008 U.S. App. LEXIS 1332, 2008 WL 191663 (9th Cir. 2008).

Opinion

CUDAHY, Circuit Judge:

United Coastal Insurance Company (UCIC) appeals the district court’s order granting Bechtel Hanford, Inc.’s (Bechtel’s) motion for judgment on a supersede-as bond. Bechtel was awarded a judgment in 2004 against Acstar Insurance Co. (Acs-tar) and P.W. Stephens Contractors, Inc. (PWS). Acstar obtained a supersedeas bond from UCIC and appealed the judgment against it. After we affirmed in part and reversed in part, Bechtel moved to collect the entire 2004 judgment from UCIC. The district court concluded that the supersedeas bond covered the judgment against both Acstar and PWS and granted Bechtel’s motion, ordering UCIC to pay the entire underlying judgment. On appeal, UCIC claims that the bond secured only Bechtel’s judgment against Acstar. We have jurisdiction under 28 U.S.C. § 1291. We agree with UCIC that the bond secures only Acstar’s obligations on the underlying judgment and therefore reverse. Because Acstar’s liability has *902 been satisfied, we direct entry of judgment in favor of UCIC.

FACTUAL AND PROCEDURAL BACKGROUND

This case is the product of a breach of contract dispute in an environmental remediation project. Bechtel contracted with the United States Department of Energy (DOE) to perform environmental clean-up work at the Hanford Nuclear Reservation in Washington. 1 PWS entered a subcontract with Bechtel to work under Bechtel’s prime contract with DOE and obtained a performance bond from Acstar. When PWS defaulted on the subcontract, Contractors Equipment Maintenance Company, Inc., a second-tier subcontractor, sued Bechtel, PWS and Acstar. Bechtel subsequently filed cross-claims against PWS and Acstar. On March 23, 2004, the district court awarded Bechtel $282,611 against PWS for its breach of contract and the same amount against Acs-tar on its performance bond. The district court also found Acstar and PWS jointly and severally liable for $296,554 in attorney’s fees, $35,844.09 in costs and expenses and $95,989.35 in prejudgment interest, and awarded Bechtel post-judgment interest as provided by law.

On April 22, 2004, Acstar and PWS filed a Notice of Appeal, which stated that:

Defendants Acstar Insurance Company and P.W. Stephens Contractors, Inc. appeal to the United States Court of Appeals for the Ninth Circuit the judgment entered by the United States District Court, Eastern District of Washington, on March 23, 2004

Pursuant to Fed.R.Civ.P. 62(d), Acstar obtained a supersedeas bond from UCIC to stay the judgment. 2 Whether that bond secures the judgment against Acstar alone or against both Acstar and PWS is the issue presented here. A Notice of Filing Undertaking to Stay Enforcement of Money Judgment Pending Appeal was filed on June 9, 2004 and the supersedeas bond was attached as Exhibit 1 to the filing. The notice provided:

[A]n undertaking is being filed on behalf of Defendant Acstar Insurance Co., the original of which is attached hereto as Exhibit 1, to stay the money Judgment for Bechtel Hanford, Inc. against P.W. Stephens Contractors, Acstar Insurance Co. and Contractor’s [sic] Equipment Maintenance Co. entered by the Court on May 23, 2004.

On appeal, Acstar challenged the district court’s award of damages as well as attorney’s fees, costs and prejudgment interest. We affirmed the judgment against Acstar on its performance bond but vacated the award of attorney’s fees, costs and interest. We also determined that as the prevailing party, Bechtel was entitled to costs under Fed.R.Civ.P. 54(d). Contractors Equip. Maint. Co. v. Bechtel Hanford, Inc., 150 Fed.Appx. 585 (9th Cir.2005). PWS did not challenge the judgment against it and remained liable for its *903 breach of contract damages as well as fees, costs and prejudgment interest.

After our decision, Bechtel moved to recover the 2004 judgment from UCIC pursuant to the supersedeas bond. The district court granted Bechtel’s motion and entered judgment in favor of Bechtel. After the court’s decision, Acstar paid Bechtel its portion of the 2004 judgment and Bechtel acknowledged that the payment satisfied Acstar’s own obligation under the judgment. On appeal from the district court’s judgment, UCIC contends that the supersedeas bond covered only Acstar’s liability and that UCIC is not liable for the outstanding obligations of PWS, which is the only portion of the 2004 judgment that remains unsatisfied.

STANDARD OF REVIEW

We review a decision to execute a bond de novo. Nintendo of Am., Inc. v. Lewis Galoob Toys, Inc., 16 F.3d 1032, 1036 (9th Cir.1994). A supersedeas bond is a contract. Nat’l Bank of Wash. v. Equity Investors, 86 Wash.2d 545, 546 P.2d 440, 444 (1976) (en banc). Hence, we apply contract review principles and review de novo the district court’s interpretation of the bond. Confederated Tribes of Siletz Indians v. Oregon, 143 F.3d 481, 484 (9th Cir.1998).

DISCUSSION

State law governs the interpretation of surety bonds. See Mai Steel Serv., Inc. v. Blake Constr. Co., 981 F.2d 414, 420 (9th Cir.1992). In Washington, surety contracts are subject to the rules governing simple contracts, Nat’l Bank of Wash., 546 P.2d at 444, and “the touchstone of the interpretation of contracts is the intent of the parties.” Scott Galvanizing, Inc. v. Nw. EnviroServices, Inc., 120 Wash.2d 573, 844 P.2d 428, 432 (1993) (en banc). Washington follows the objective manifestation theory of contracts under which a court focuses on the “objective manifestations of the agreement, rather than on the unexpressed subjective intent of the parties” to ascertain intent. Hearst Commc’ns, Inc. v. Seattle Times Co., 154 Wash.2d 493, 115 P.3d 262, 267 (2005) (en banc). See also Allstate Ins. Co. v. Peasley, 131 Wash.2d 420, 932 P.2d 1244, 1246 (1997) (en banc) (noting that if “the language in an insurance policy is clear and unambiguous, the court must enforce it as written and cannot modify the contract or create ambiguity where none exists”). In interpreting surety contracts, like other contracts, courts focus on the language of the agreement. See King Equip. Co. v. R.N. & L. Corp., 1 Wash.App. 487, 462 P.2d 973, 975 (Ct.App.1969) (“[T]he liability of a surety is measured by the terms of his agreement.”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Munoz v. Ojogho CA2/3
California Court of Appeal, 2023
Beres v. United States
Federal Claims, 2019
Curtis Oswalt v. Resolute Industries Inc
500 F. App'x 605 (Ninth Circuit, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
514 F.3d 899, 2008 U.S. App. LEXIS 1332, 2008 WL 191663, Counsel Stack Legal Research, https://law.counselstack.com/opinion/contractors-equipment-maintenance-co-v-bechtel-hanford-inc-ca9-2008.