Tuthill Ranch, Inc. v. United States

381 F.3d 1132, 2004 WL 1872725
CourtCourt of Appeals for the Federal Circuit
DecidedAugust 23, 2004
Docket03-5085
StatusPublished
Cited by23 cases

This text of 381 F.3d 1132 (Tuthill Ranch, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tuthill Ranch, Inc. v. United States, 381 F.3d 1132, 2004 WL 1872725 (Fed. Cir. 2004).

Opinions

GAJARSA, Circuit Judge.

Tuthill Ranch, Inc. (“Tuthill”) appeals the summary judgment granted by the United States Court of Federal Claims (“Court of Federal Claims”) in favor of the United States (“government”). Tuthill claimed that the government had physically occupied Tuthill’s property, thereby effecting a compensable physical taking. The Court of Federal Claims found that, based upon undisputed facts, the government had not physically occupied Tuthill’s property, and was therefore not liable for a physical taking. Based upon this finding, the Court of Federal Claims denied Tuthill’s motion for summary judgment and granted the government’s motion for summary judgment. Tuthill v. United States, No. 00-635L, (Fed.Cl. Mar. 17, 2003). Because the Court of Federal Claims correctly determined that no disputed material facts could establish a physical taking, we affirm.

BACKGROUND

The Bonneville Power Administration (“BPA”), an agency of the federal government, transmits electrical power along approximately 15,000 miles of power lines in Oregon, Washington, Idaho, and Montana. One of these power lines crosses Tuthill’s property in Washington. In 1953, Tuthill’s predecessor-in-interest sold the BPA “a perpetual easement and right to enter and erect, operate, maintain, repair, rebuild, and patrol one or more electrical power transmission lines and appurtenant signal lines, poles, towers, wires, cables, and appliances necessary in connection therewith.”

The BPA then built both power lines and accompanying communication, or signal lines in accordance with the terms of its easement. Beginning in the 1950s, the BPA upgraded its signal line technology on a number of occasions. In the most recent of these technological upgrades, the BPA decided to convert all of its signal lines to fiber optic cables.

The upgrade to fiber optics began in 1995. According to the government, BPA devised its upgrade plan based “upon planned load growth and wholesale transmission transactions between now and 2025.” In most places, the BPA standardized its cables to either the 36- or the 72-fiber size to accommodate a claimed projected need of sixteen fibers by 2008, sixty-four by 2018, and seventy-six by 2025. It is therefore undisputed that the BPA installed more capacity than it requires for its current needs but that the BPA may need this capacity to meet its projected future needs. It is also undisputed that the BPA now leases some of this excess capacity to unrelated third parties. The BPA currently needs only a fraction of the [1134]*1134thirty-six fibers crossing Tuthill’s property to maintain the power lines. It leases the remainder to a telecommunications company.

Tuthill alleges that the “creation of a fiber optic communication system many times greater than is needed by the agency to serve its energy control needs, coupled with [the government’s] leasing and other contractual agreements with for-profit communications companies, is use outside of the scope of the easement [that the government] relies on to burden [Tut-hill’s] real property.” Given this alleged breach of the easement’s explicit terms, Tuthill further asserts that the government’s “misuse of these easements, and or [the government’s] allowing of others to misuse these easements, amounts to a physical occupation of [Tuthill’s] real property which is a per se taking without just compensation prohibited by the Fifth Amendment to the Constitution.” Finally, Tuthill claims that the government owes it just compensation for the permanent physical taking of its property — or in the alternative, if the government chooses to cease the occupation, just compensation for the temporary physical taking of its property. Tuthill has not brought any other causes of action or theories upon which the government allegedly caused compensable damage to Tuthill’s property. Tuthill’s entire case therefore rests upon whether or not the government’s actions constituted a per se physical taking.

The government contends that the BPA designed this natural upgrade to its infrastructure to accommodate growth projected through 2025. Those projections determined the number of fibers, and thus the size of the cables, laid as necessary “signal lines” per the easement’s terms. Once the BPA laid those cables, leasing unused fibers to third parties did not constitute a physical invasion, and did not increase the burden on the servient estate in any way. Therefore, according to the government, “[Tuthill’s] property has not been burdened in any way for which it has not been compensated already,” that is in 1953.

Tuthill and the government filed cross motions for summary judgment. Based upon undisputed facts, the Court of Federal Claims explained that

[t]he scope of the easement is not relevant in this court because it cannot give rise to a physical taking. Moreover, [Tuthill] has not identified a property interest that could have been taken. Tuthill may have avenues of relief in federal court, but not on a takings theory. For example, misuse of an easement may be a trespass to real property.
The government overbuilt the communication network to accommodate future growth. What is excess capacity today may or may not be excess in the future. The easement allows “appurtenant signal lines ... necessary and in connection therewith.... ” Physical presence of the fiber optic cable over the easement is not a taking. No additional physical intrusion to [Tuthill’s] land has resulted from the lease to the third parties.

Tuthill, slip op. at 6. The Court of Federal Claims therefore denied Tuthill’s motion and granted summary judgment in favor of the government. Tuthill timely appealed.

DISCUSSION

We have jurisdiction to hear this appeal under 28 U.S.C. § 1295(a)(3). We review the Court of Federal Claims’ grant of summary judgment without deference. Christopher Vill., L.P. v. United States, 360 F.3d 1319, 1326 (Fed.Cir.2004); Agwiak v. United States, 347 F.3d 1375, 1377 (Fed.Cir.2003); Scott Timber Co. v. United States, 333 F.3d 1358, 1365 (Fed.Cir.2003). Summary judgment is appropriate when there are no disputed issues of material [1135]*1135fact and the moving party is entitled to judgment as a matter of law. Fed. R.Civ.P. 56; Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247-48, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986).

This case involves Fifth Amendment takings jurisprudence. “The Fifth Amendment does not proscribe the taking of property; it proscribes taking without just compensation.” Brown v. Legal Found, of Wash., 538 U.S. 216, 235, 123 S.Ct. 1406, 155 L.Ed.2d 376 (2003). Tut-hill asserts that the federal government, acting through the BPA, physically occupied its property without just compensation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Estate of Hage v. United States
685 F. App'x 927 (Federal Circuit, 2017)
Love Terminal Partners, L.P. v. United States
126 Fed. Cl. 389 (Federal Claims, 2016)
Chittenden v. United States
126 Fed. Cl. 251 (Federal Claims, 2016)
Cebe Farms, Inc. v. United States
116 Fed. Cl. 179 (Federal Claims, 2014)
Warren Trust v. United States
107 Fed. Cl. 533 (Federal Claims, 2012)
Smith v. JERSEY CENT. POWER
24 A.3d 300 (New Jersey Superior Court App Division, 2011)
Ladd v. United States
646 F.3d 910 (Federal Circuit, 2011)
Love Terminal Partners v. United States
97 Fed. Cl. 355 (Federal Claims, 2011)
Grygiel v. Monches Fish & Game Club, Inc.
2010 WI 93 (Wisconsin Supreme Court, 2010)
Ladd v. United States
90 Fed. Cl. 221 (Federal Claims, 2009)
Bullock v. Klein
341 F. App'x 812 (Third Circuit, 2009)
International Industrial Park, Inc. v. United States
80 Fed. Cl. 522 (Federal Claims, 2008)
Cienega Gardens v. United States
503 F.3d 1266 (Federal Circuit, 2007)
Butler v. Michigan State Disbursement Unit
738 N.W.2d 269 (Michigan Court of Appeals, 2007)
Souders v. South Carolina Public Service Authority
497 F.3d 1303 (Federal Circuit, 2007)
Brace v. United States
72 Fed. Cl. 337 (Federal Claims, 2006)
Canal Electric Co. v. United States
65 Fed. Cl. 650 (Federal Claims, 2005)
The Stearns Company, Ltd. v. United States
396 F.3d 1354 (Federal Circuit, 2005)
Tuthill Ranch, Inc. v. United States
381 F.3d 1132 (Federal Circuit, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
381 F.3d 1132, 2004 WL 1872725, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tuthill-ranch-inc-v-united-states-cafc-2004.