Tug Hill Construction, Inc.

CourtArmed Services Board of Contract Appeals
DecidedOctober 16, 2014
DocketASBCA No. 57825
StatusPublished

This text of Tug Hill Construction, Inc. (Tug Hill Construction, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tug Hill Construction, Inc., (asbca 2014).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Tug Hill Construction, Inc. ) ASBCA No. 57825 ) Under Contract No. W9126G-09-D-0006 )

APPEARANCE FOR THE APPELLANT: Brian R. Dugdale, Esq. Varela, Lee, Metz & Guarino McLean, VA

APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq. Engineer Chief Trial Attorney Charles L. Webster III, Esq. Cindy E. Shimokusa, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Fort Worth

OPINION BY ADMINISTRATIVE JUDGE MCILMAIL

The government entered into a firm, fixed-price contract with appellant for construction work at Fort Bliss, Texas. Appellant seeks additional compensation for utility system work in excess of its original price. The Board conducted an eight-day hearing, on the issue of entitlement only. The Board finds that appellant is not entitled to additional compensation, and denies the appeal.

FINDINGS OF FACT

1. On 9 April 2010, a Request for Proposals (RFP) was issued by the U.S. Army Corps of Engineers (government or USACE) for Phases 3 and 4 of the Fort Bliss Combat Aviation Brigade Additional Infrastructure Project (CAB 3 & 4) to the five contractors in the government's Fort Bliss infrastructure multiple award task order contract (MATOC) (R4, tab 3). The proposed task order was to be awarded on a firm fixed-price basis to the lowest priced acceptable offeror (R4, tab 4 ).

2. The scope of work for the project included the demolition of certain sections of existing utility systems and the construction of new primary electric, water, sanitary sewer, communications, and natural gas utilities systems. The new utilities would subsequently be connected back to the existing main utility systems. (R4, tab 3 at 55-57, 99) Further, the delivery order provides: SPECIAL NOTICE: The existing Fort Bliss Main Post Utility Systems are privately owned. This scope of work includes coordinating project utility requirements with the owners of the privatized utility systems. Typically Utility owners will remove existing utilities, install new primary utility systems and make final connections between the new systems and existing. However, contractors shall be responsible for negotiating and finalizing utility system work with the utility providers. The Contractor will include its cost for such work in its cost proposal.

(R4, tab 4 at 40) We find that the language of the Special Notice is unambiguous, and put offerors on notice that they were to make arrangements, or at least conduct discussions with, the utility providers, and account for whatever resulted from those arrangements or discussions in their cost proposals.

3. Three offerors submitted proposals for the delivery order: appellant, J.D. Abrams, and Sundt Construction (Sundt) (R4, tab 29; tr. 7/148, 8/118).

4. The Fort Bliss water utility provider was Fort Bliss Water Services Company (FBWS), the electric utility provider was Rio Grande Electric Cooperative, Inc. (RGEC), and the gas utility provider was Texas Gas (tr. 7/130). FBWS and RGEC became the owners of the Fort Bliss utility systems through a privatization effort that resulted in the utility providers entering into 50-year contracts with the Army. Thus, the Army gave these two utility owners service contracts that obligate them to operate and maintain their respective systems and to provide utility services to Fort Bliss. (R4, tabs 15, 16). We find that these contracts allow the utility owners to act as autonomous entities with respect to their respective utilities on Fort Bliss.

5. Appellant was aware of the Special Notice as early as 11 May 2010, prior to submitting its proposal (supp. R4, tab 137; tr. 1171, 171-73). On that date, in addition to extending the proposal submission deadline to 24 May 2010 at 2:00 pm, the government amended the RFP to add the Special Notice to the Scope of Work (supp. R4, tabs 38-41).

6. On 19 May 20 I 0, appellant received word from a company named CF Jordan that, with respect to CAB 3 & 4, "[FBWS] is going to be doing the water/sewer" (supp. R4, tab 148 at 827).

2 7. On 19 May 2010, Sundt posted the following (Inquiry No. 3276130) on the government's "ProjNet" 1 system, with respect to CAB 3 & 4:

Please clarify the Special Notice regarding coordination and negotiations with the owners of privatized utilities. Based upon the language provided, bidders should include in their cost proposal: Costs of work typically performed by the utility owners. Fees charged by the utility owner, such as design review, connection, and inspections. Costs for all other work required to conform with the contract documents. Are these assumptions correct? Finally, should the contractor assume, depending on the utility owner, the contractor may be required to sub-contract directly with the utility owner in order to complete the work?

(Supp. R4, tab 45 at 77)

8. Prior to submitting their cost proposals, Sundt and J.D. Abrams contacted FBWS and RGEC. RGEC would not provide a price quote for the delivery order electrical utility system work, but, on 20 May 2010, FBWS provided a quote of $11,071,000 to Sundt and J.D. Abrams for the water utility system work. (Supp. R4, tabs 146, 151; tr. 7/144-48, 8/117-20).

9. Also on 20 May 2010, a company named Helix Electric, Inc. (Helix), passed along to appellant a message that Helix had received from RGEC regarding CAB 3 & 4, in which RGEC stated:

We are the owners of the Ft. Bliss power distribution system. Please ask your general contracting POC or your USACE POC to contact us about the work required for CAB phases 3 & 4.

(Supp. R4, tab 144 at 819) On the same day appellant contacted RGEC, and asked, with respect to CAB 3 & 4, "[ c]an you explain the work to be completed on this project by the ... contractor and what role [RGEC] will play in the project please" (supp. R4, tab 150 at 832). The purpose of appellant's question was to seek clarification "as

1 The ProjNet inquiry system is a public electronic bulletin board where offerors may ask the USACE for clarification on a solicitation (see tr. 1/126). It allows offerors to view all previously-submitted inquiries, and responses, and to add new inquiries (R4, tab 3 at 75).

3 to what [appellant's] role was going to be and what [RGEC's] role was going to be" (tr. 11121). On 21May2010, RGEC replied:

RGEC's typical role involves anything with the electrical utility system. We are responsible for all of the demolition of existing and installation of new distribution utilities .... We have yet to receive clear plans so I am unable to fully comment on the work to be completed on the project. If this doesn't answer your question, please let me know and I can try to provide you with better information.

(Supp. R4, tab 150 at 831)

10. On 21 May 2010, Sundt posted the following (Inquiry No. 3283285) on ProjNet, with respect to CAB 3 & 4:

[RGEC] has informed the General Contractors that they will not be providing pricing for at least (3) three weeks. In addition, [RGEC] is not going to approve the existing design. [FBWS] has only provided conceptual budgetary numbers that are not contractually binding. [FBWS] says that firm pricing will be available in the next month. [FBWS], Texas Gas, and [RGEC] are not going to allow the ... contractors to self-perform the work.... Given that we are not going to receive pricing, we are requesting a suitable time extension for the privatized utility contractors to provide firm price quotations.

(Supp. R4, tab 45 at 77-78)

11. The government did not respond to Inquiry Nos. 3276130 and 3283285 (supp. R4, tab 45 at 77-78).

12. On the morning of 22 May 2010, Steve Haskins, appellant's estimating manager and purchasing manager (tr. 1/58), emailed Jeffrey Kellogg, appellant's president and sole owner (tr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CONNER BROS. CONST. CO., INC. v. Geren
550 F.3d 1368 (Federal Circuit, 2008)
Ace Constructors, Inc. v. United States
499 F.3d 1357 (Federal Circuit, 2007)
Grumman Aerospace Corporation v. Wynne
497 F.3d 1350 (Federal Circuit, 2007)
Scott Timber Co. v. United States
692 F.3d 1365 (Federal Circuit, 2012)
bell/heery v. United States
739 F.3d 1324 (Federal Circuit, 2014)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Tug Hill Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/tug-hill-construction-inc-asbca-2014.