Trustees of Columbia University v. Siegel & Associates Architects

167 A.D.2d 6, 574 N.Y.S.2d 668, 1991 N.Y. App. Div. LEXIS 7274
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMay 21, 1991
StatusPublished
Cited by5 cases

This text of 167 A.D.2d 6 (Trustees of Columbia University v. Siegel & Associates Architects) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trustees of Columbia University v. Siegel & Associates Architects, 167 A.D.2d 6, 574 N.Y.S.2d 668, 1991 N.Y. App. Div. LEXIS 7274 (N.Y. Ct. App. 1991).

Opinion

OPINION OF THE COURT

Milonas, J. P.

Plaintiff Columbia University and defendant-respondent Morse/Diesel, Inc. entered into a construction agreement on June 15, 1978 pursuant to which the latter was to serve as construction manager for certain proposed East Campus housing, consisting primarily of a dormitory complex with additional office and conference areas. In that regard, defendant was charged with responsibility for the entire project from the preparation of the first drawing through the completion of construction, as well as the procurement of all necessary permits. The actual building commenced in 1979, and, by 1981, Columbia, confronting an acute housing shortage, began transferring people into parts of the East Campus in January and February of that year. A temporary certificate of occupancy was thereafter obtained. According to plaintiff, the new housing was only minimally habitable, and it was accepted, even by Morse/Diesel, that more work would be required after the students had moved in. Other sections of East Campus, Columbia states, remained vacant until much later since the need for the space was not immediate. Yet, one of the codefendants in this case, Charles Gwathmey of Gwathmey Siegel & Associates, Architects, wrote in a letter of December 21, 1983, that "[i]n context, Morse/Diesel used the ’move in’ of students when the project was unfinished to deny responsibility for punch list items.” In any event, such a punch list of uncompleted or faulty matters was prepared, with new items continuing to be appended as their existence became apparent.

It is the contention of Morse/Diesel that it tendered the project to Columbia on October 12, 1981 as substantially complete pursuant to section 7.5 of Part B of the subject contract, which mandated plaintiff either to accept the work as is or provide a deficiency list. Defendant asserts that "substantial completion” means, in construction industry usage, the point at which the owner can occupy or utilize the premises for their intended purposes, and this, it insists, had long before been attained. Moreover, Morse/Diesel urges, [8]*8Columbia did not basically dispute that the project was substantially complete although it admits that there were still some open items on the punch list as of March 28, 1982. However, defendant claims that most of these matters involved repair or corrective work to previously installed aspects of the construction. Morse/Diesel does concede that there were a number of details, particularly the replacement of bathroom tiles in the dormitory bathrooms, that remained unfinished until 1983 and ultimately required more work than had been initially anticipated. Plaintiff, in contrast, argues that five major aspects of the project, whose magnitude was not fully revealed on Morse/Diesel’s punch list, along with other miscellaneous items, were still not completed by March 28, 1982. These matters consisted primarily of (1) arcade deck leaks, (2) arcade ceiling leaks, (3) facade leaks, (4) ponding in the plaza of the School of International and Public Affairs (S.I.A.), and (5) replacement of the bathroom tiles.

Notwithstanding defendant’s allegation that Columbia accepted its formal notice that the contract work was substantially complete, plaintiff’s project manager responded on October 30, 1981 that "[t]he Morse Diesel letter of 10/12/81 advising of 'substantial completion’ is somewhat premature. I have reviewed our punch list of 7/28/81 and the followup letter of 10/5/81 and find a sizable portion of those lists open and/or incomplete.” On November 9, 1981, defendant replied that of the 210 items deemed unfinished by Columbia, "only approximately 100 remain open. Many of these open items are in progress. * * * Please rest assured that every possible effort is being made to complete the remaining items. However, it is quite apparent that with only these few items remaining open on a project of this magnitude, the overall contract work and corrective work indicated on the Punch List dated July 28, 1981 can be considered substantially complete.” Columbia rejected Morse/Diesel’s position in a letter dated December 29, 1981 in which its project manager reminded defendant that it had previously complained of many unsatisfied deficiencies, some of them being "very significant” and including "leaks through the arcade into the undeveloped space below, ponding of water on the S.I.A. Plaza and trailer removal. As the cost for completing these and other items will be quite large, I suggest that we discuss whether the project can be considered substantially complete at our next meeting.”

In its next communication, dated January 8, 1982, Morse/ [9]*9Diesel lectured Columbia as to the meaning of substantial completion. It then observed that the "completion of punch list items has been an ongoing procedure as portions of the building were made available for occupancy.” The various lists, defendant claimed, "were compiled with the understanding and cooperation of your representative, with the items listed thereon completed as they appeared. On July 28, 1981, we received the 'final punch list’ from your office which incorporated not only those items remaining from previous lists, but included new items discovered during the rise and occupancy of the building.” Defendant, moreover, accused Columbia of hindering its efforts by refusing to make timely progress payments as necessitated by their contract. Nonetheless, it concluded, "not only has substantial completion been achieved, but final completion is immanent [sic]. ” Thereafter, Morse/Diesel advised Columbia, in a letter dated January 25, 1982, that it had prepared a final punch list containing 108 items and inviting plaintiff to offer any additions. Columbia’s project manager wrote back on March 8, 1982 that "[w]e forward herewith your 'boiled’ down list annotated as requested. Two additional sheets are included showing five (5) new items and 23 other items not included on your list. This second listing reminds us of problems encountered during the course of the project, but which remain incomplete or uncorrected.” Two days later, defendant’s project manager noted in an internal memorandum that work valued at $39,120, as indicated on five attached sheets, had not yet been done. Another internal memorandum ensued on April 13, 1982, again referring to a revised punch list, on this occasion stating that the "dollar value of this work is difficult to determine. This is due to the approval of some scope changes not being paid for, etc. We should carry a safe amount of $50,000 to $75,000 to complete.”

Significantly, the leakage problems evidently plaguing the project, which plaintiff attributes to defective work, persisted well into 1982 and was still mentioned on the punch list in April of that year. Indeed, Morse/Diesel itself acknowledged the seriousness of the situation with respect to the arcade deck to its subcontractor, defendant Port Morris Tile & Terrazzo Corp. At one point, the company admitted that "the trenching done by us [was] not sufficient”, and 2,000 cubic feet of the arcade deck were eventually replaced. Columbia asserts that this task was not finished until September of 1982. Simultaneous with the difficulties concerning the arcade deck, [10]*10plaintiff was also experiencing trouble with leaks in the arcade ceilings. During the winter of 1980-1981, pipes in these ceilings repeatedly froze and burst as a result of improper insulation, and Morse/Diesel’s work here was not completed until May of 1982. Correcting the various arcade deficiencies, Columbia asserts, created such severe disruption that on occasion it was almost impossible for students to enter East Campus.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New York Univ. v. Turner Constr. Co.
2018 NY Slip Op 4960 (Appellate Division of the Supreme Court of New York, 2018)
Town of Poughkeepsie v. Espie
41 A.D.3d 701 (Appellate Division of the Supreme Court of New York, 2007)
United States Fidelity & Guaranty Co. v. Delmar Development Partners, LLC
22 A.D.3d 1017 (Appellate Division of the Supreme Court of New York, 2005)
Rotterdam Square v. Sear-Brown Associates
246 A.D.2d 871 (Appellate Division of the Supreme Court of New York, 1998)
Trustees of Columbia University v. Siegel
192 A.D.2d 151 (Appellate Division of the Supreme Court of New York, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
167 A.D.2d 6, 574 N.Y.S.2d 668, 1991 N.Y. App. Div. LEXIS 7274, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trustees-of-columbia-university-v-siegel-associates-architects-nyappdiv-1991.