Yeshiva University v. Fidelity & Deposit Co.

116 A.D.2d 49, 500 N.Y.S.2d 241, 1986 N.Y. App. Div. LEXIS 50231
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMarch 25, 1986
StatusPublished
Cited by9 cases

This text of 116 A.D.2d 49 (Yeshiva University v. Fidelity & Deposit Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Yeshiva University v. Fidelity & Deposit Co., 116 A.D.2d 49, 500 N.Y.S.2d 241, 1986 N.Y. App. Div. LEXIS 50231 (N.Y. Ct. App. 1986).

Opinion

OPINION OF THE COURT

Wallach, J.

Defendant Fidelity and Deposit Company of Maryland (Fidelity) appeals from an order denying its motion to dismiss this action as time barred. The action was brought to recover on a performance bond. The bond, a widely utilized, standard form published by the American Institute of Architects, contained a provision limiting the time for commencing an action thereon as follows: "Any suit under this bond must be instituted before the expiration of two (2) years from the date on which final payment under the Contract falls due.”

Since the interpretation placed upon this language by Special Term is not in accord with its plain meaning and the manifest intention of the parties, we reverse.

On August 23, 1976, plaintiff Yeshiva University (Yeshiva) and defendant Tishman Construction Corporation of New York (Tishman) entered into a written contract which, though not part of the record, is described in the complaint as having involved a promise by Tishman, as construction manager, to construct a certain building to house a cancer research institute, referred to as "the project”, on a site owned by Yeshiva (the main contract). On December 15, 1976, Tishman entered into a contract with Labequipco, Division of Frigitemp Corp. (Labequipco) for the portion of the main contract calling for metal casework and laboratory furniture (the subcontract). Pursuant to the subcontract, on January 3, 1977, Labequipco, as principal, procured from Fidelity, as surety, the bond in issue guaranteeing both Tishman and Yeshiva, as obligees, [51]*51that the subcontract would be completed in accordance with its terms and conditions.

Labequipco commenced work, but, in March 1978, filed for bankruptcy, an event of default under the subcontract. Fidelity thereupon hired another contractor, Laboratory Furniture, Inc. (Laboratory), to finish the job. In connection with this new hiring, Fidelity wanted Tishman and Yeshiva to make all further payments under the subcontract to it, and not to the new contractor, a demand to which both agreed in a writing dated May 31, 1978. On June 21, 1979, Tishman sent Fidelity a check which was described in a covering letter as the "final payment” of the subcontract. Copies of this letter were sent to Yeshiva, Yeshiva’s architect and Yeshiva’s attorney, none of whom responded. In November 1983, Yeshiva, having hired a consultant, learned that the reason why the metal casework and furniture in its laboratories was rusting and otherwise becoming useless was because a certain phosphate treatment specified in the main contract necessary to preserve metal surfaces had not been applied by Laboratory. On January 31, 1984, Yeshiva demanded of Tishman that it repair or replace the deteriorating casework and furniture and notify Fidelity of the situation, but Fidelity has refused to make good the defective work. Final payment having been made on June 21, 1979 when Tishman forwarded a check described as such to Fidelity, and the action not having been commenced against Fidelity until March 1984, almost five years later, the cause of action against it, Fidelity argues, is time barred. This court agrees.

Reasoning that the existence of a defect meant that the work had not been completed and that final payment, therefore, never fell due, Special Term concluded that the two-year contractual limitation period had never commenced to run notwithstanding the check sent by Tishman to Fidelity in June 1979 ostensibly as the final payment due under the subcontract. Such a construction leads to a somewhat startling paradox: not only was a provision in the bond purporting to modify the otherwise applicable statutory period of limitations read out of the bond, but, by postponing accrual until such time as a defect became manifest, the statutory period was rendered inoperative as well, leaving Fidelity liable on the bond, at least theoretically, for all time. If indeed that were the intention of the parties to the bond, their agreement would not be enforceable. An agreement to waive or even extend the Statute of Limitations, adopted at the inception of [52]*52the contract and not after the cause of action has accrued, is against public policy and void (Kassner & Co. v City of New York, 46 NY2d 544, 550-552). Thus, if this widely used, standard clause is to be given effect, it must be construed not as a waiver or extension but as a shortening of the Statute of Limitations. So viewed, it "does not conflict with public policy but, in fact, 'more effectively secures the end sought to be attained by the statute of limitations’ ” (Kassner & Co. v City of New York, supra, at p 551, quoting Ripley v Aetna Ins. Co., 30 NY 136, 163; CPLR 201).

In holding that final payment never fell due, Special Term relied upon two provisions of the subcontract. The first, insofar as invoked, provided that the "balance owing”, dubbed "final payment” in large, printed, block letters set off in the margin, was to become due and payable within 60 days after the completion of all work called for in the subcontract and its acceptance by Tishman, Yeshiva and Yeshiva’s architect. The second provided that Tishman could hold the contractor responsible for "unsound work or materials” permitted to remain on the site during construction for up to one year after completion of the entire project, and that any payments made by Tishman to the contractor during this period were not to be construed as evidence of an acceptance of the contractor’s work.

Reliance by the court below on this latter provision was error. As a rule, acceptance of performance under a construction contract is a waiver of the right to recover for defects that were known or discernible with reasonable inspection, i.e., patent, as opposed to latent, defects (Town of Tonawanda v Stapell, Mumm & Beals Corp., 240 App Div 472, affd 265 NY 630). The intent of the clause in question was to vary this rule so as to permit the prime contractor to make full payment to the subcontractor without waiving the subcontractor’s liability for patent defects. It relates to the duration of the subcontractor’s liability for patent defects and, though its enforceability would be problematic were it to result in a lengthening of the statutory period, it has nothing to do with the question of when a cause of action for such, or any other liability of the subcontractor, accrues.

Nor does the other provision of the subcontract cited by the court below—that final payment was not due until the work was completed and accepted by Tishman, Yeshiva and the architect—support the view that final payment never fell due. It should first be noted that, to the extent it conditions final [53]*53payment on acceptance as well as completion of the work, the clause is of doubtful validity. In an action upon a construction contract, the cause of action generally accrues upon completion of construction, meaning completion of the actual physical work (State of New York v Lundin, 60 NY2d 987, 989). Application of this principle could not be avoided by Tishman and Yeshiva indefinitely withholding their acceptance of the work. " 'The public policy represented by the statute of limitations becomes pertinent where the contract not to plead the statute is in form or effect a contract to extend the period as provided by statute or to postpone the time from which the period of limitation is to be computed. ’ ” (Kassner & Co. v City of New York, supra,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rite Aid of New York, Inc. v. R.A. Real Estate, Inc.
40 A.D.3d 474 (Appellate Division of the Supreme Court of New York, 2007)
Alvarez v. Attack Asbestos, Inc.
287 A.D.2d 349 (Appellate Division of the Supreme Court of New York, 2001)
Trustees of Columbia University v. Siegel & Associates Architects
167 A.D.2d 6 (Appellate Division of the Supreme Court of New York, 1991)
Brintec Corp. v. Akzo N. V.
171 A.D.2d 440 (Appellate Division of the Supreme Court of New York, 1991)
Mastropieri v. Solmar Construction Co.
159 A.D.2d 698 (Appellate Division of the Supreme Court of New York, 1990)
Menorah Nursing Home, Inc. v. Zukov
153 A.D.2d 13 (Appellate Division of the Supreme Court of New York, 1989)
County of Nassau v. H. Sand & Co.
144 A.D.2d 619 (Appellate Division of the Supreme Court of New York, 1988)
Town of Esopus v. Brinnier & Larios, P. C.
135 A.D.2d 935 (Appellate Division of the Supreme Court of New York, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
116 A.D.2d 49, 500 N.Y.S.2d 241, 1986 N.Y. App. Div. LEXIS 50231, Counsel Stack Legal Research, https://law.counselstack.com/opinion/yeshiva-university-v-fidelity-deposit-co-nyappdiv-1986.