Trinity Contracting, Inc. v. Municipal Sewage Authority of the Twp. of Sewickley and Gibson-Thomas Engineering Co., Inc.

CourtCommonwealth Court of Pennsylvania
DecidedDecember 15, 2015
Docket523 and 524 C.D. 2015
StatusUnpublished

This text of Trinity Contracting, Inc. v. Municipal Sewage Authority of the Twp. of Sewickley and Gibson-Thomas Engineering Co., Inc. (Trinity Contracting, Inc. v. Municipal Sewage Authority of the Twp. of Sewickley and Gibson-Thomas Engineering Co., Inc.) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trinity Contracting, Inc. v. Municipal Sewage Authority of the Twp. of Sewickley and Gibson-Thomas Engineering Co., Inc., (Pa. Ct. App. 2015).

Opinion

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

Trinity Contracting, Inc. : : No. 523 C.D. 2015 v. : Argued: November 16, 2015 : Municipal Sewage Authority of : the Township of Sewickley and : Gibson-Thomas Engineering Co., Inc., : : Appellants :

Trinity Contracting, Inc., : : No. 524 C.D. 2015 Appellant : Argued: November 16, 2015 : v. : : Municipal Sewage Authority of : the Township of Sewickley and : Gibson-Thomas Engineering Co., Inc. :

BEFORE: HONORABLE BERNARD L. McGINLEY, Judge HONORABLE RENÉE COHN JUBELIRER, Judge HONORABLE ROCHELLE S. FRIEDMAN, Senior Judge

OPINION NOT REPORTED

MEMORANDUM OPINION BY SENIOR JUDGE FRIEDMAN FILED: December 15, 2015

The Municipal Sewage Authority of the Township of Sewickley (Authority) and Gibson-Thomas Engineering Company, Inc. (Gibson) (together, Appellants) appeal from the December 22, 2014, order of the Court of Common Pleas of Westmoreland County (trial court) denying their post-trial motions. Trinity Contracting, Inc. (Trinity) has also cross-appealed from the trial court’s December 22, 2014, order denying its post-trial motion.1 We affirm.

In 2012, Trinity filed a complaint against Appellants, alleging, inter alia, claims for breach of contract and negligent misrepresentation relating to the construction of a sewage treatment plant (Project) in Sewickley Township, Pennsylvania. Sewickley Township commissioned the Authority to finance, plan, and construct a public sanitary sewer system. The Authority entered into a contract with Gibson to design the Project, perform the engineering work, and oversee the Project.

Gibson hired Dr. James Hamel as its geotechnical consultant for the Project. On March 28, 2007, Dr. Hamel wrote a letter to Gibson identifying five geotechnical problems with the Project site: (1) surface subsidence from abandoned mining operations; (2) total and differential soil settlement from surface mining; (3) landslides in excavated slopes on the east side of the site; (4) mine drainage from surface and underground mining operations; and (5) dewatering.

Thereafter, Gibson hired Professional Service Industries, Inc. to perform boring work and prepare a geotechnical engineering services report (Geotechnical Report) for the Project. Gibson completed its site design and Project layout in August 2007. After receiving the Geotechnical Report in January 2008, Gibson did not change the Project design or layout.

1 The appeals have been consolidated for disposition in this court.

2 The Authority put the Project out for bid on March 6, 2009. The Project was solicited as a “plan-and-spec” project, meaning that Gibson completely designed the Project, and interested bidders were instructed that if they followed Gibson’s plans and specifications, they could successfully complete the Project. Gibson did not supply a copy of the Geotechnical Report to prospective bidders.

In August 2009, Gibson awarded Trinity the construction contract (Contract) in the amount of $4,872,648.40. The scope of Trinity’s work included performing the general and mechanical construction necessary for a complete sewage treatment plant. Planned activities included subsurface mine grouting, pressure grouting, extension of the water lines, and construction of the sanitary sewer force main. Under the Contract, Trinity agreed to substantially complete the work by November 10, 2010.

After construction began, Trinity and its subcontractors encountered unforeseen, subsurface conditions and geotechnical difficulties at the site, which required Gibson to modify the Project design and layout. Throughout the course of the Project, the Authority and Trinity entered into five Change Orders, which resulted in several site redesigns and eventually increased the Contract amount to $5,362,627.79. The Change Orders also moved the substantial completion date to February 25, 2011.

By letter dated January 5, 2012, Gibson notified Trinity that its work was deemed substantially complete on November 8, 2011, and, as a result, Gibson

3 was assessing liquidated damages against Trinity in the amount of $210,050. Trinity filed the instant suit against Appellants on January 27, 2012.

In March 2014, the trial court held a seven-day, non-jury trial, after which the parties submitted proposed findings of fact and conclusions of law. On September 30, 2014, the trial court entered judgment in favor of Trinity and against Appellants in the amount of $1,049,011.632 plus $18,140.39 in interest, with interest accruing at a rate of $17.70 per day until the underlying award is satisfied. The trial court also found in the Authority’s favor with respect to Trinity’s counterclaim for bad faith. Appellants and Trinity filed post-trial motions, which the trial court denied on December 22, 2014. These appeals followed.3

Appellants’ Appeal

Appellants first assert that the trial court erred in concluding that the Authority breached its contract with Trinity by failing to give Trinity additional time and money that was not contemplated by the Change Orders. Appellants claim that because the Contract documents, including the Change Orders, addressed all of the issues that arose during the course of the Project, the Authority properly denied Trinity’s requests for additional time and money. We disagree.

2 This amount included the contract balance of $325,288.83; schedule-related damages of $359,785.54; and additional work-scope damages of $363,937.26. (Trial Ct. Order, 9/30/14, at 1.)

3 Our review of an order denying post-trial motions is limited to determining whether the trial court abused its discretion or committed an error of law. Wright v. Denny, 33 A.3d 687, 688 n.2 (Pa. Cmwlth. 2011).

4 We conclude that the trial court correctly determined that the language contained in the Contract and Change Orders, when read together, constituted a reservation of rights to additional compensation. The Contract stated that the Contract times and/or price “will be equitably adjusted” if the existence of differing subsurface or physical conditions at the site cause an increase or decrease in Trinity’s costs or the time required to perform the work. (Trial Ct. Op. at 9 (citing Section 4.03.C of the Contract).) In addition, the Change Orders expressly “exclude[d] any and all work not specifically listed above.” (Id. at 10.) The trial court concluded that by this language, Trinity reserved its right to request equitable adjustments to the Contract price and times at a later date due to unforeseen, differing site conditions.4 We find no error.

Moreover, the evidence showed that Trinity incurred a significant amount of additional work and costs as a result of Gibson’s Project redesigns, which fell outside the scope of work described in the Change Orders. Thus, the trial court

4 The trial court explained:

To the extent that language of the contract or change orders was vague, it was so necessarily, as the parties were encountering unknown issues and could not insert values for items such as the additional number of days it would take to complete certain tasks, or the additional costs, duties and obligations to be undertaken in the event that unforeseen conditions arose. In other words, the language of the contract was not vague, but rather drafted with the foresight that unanticipated problems often arise during construction, and in such events, it is sometimes wise for the parties to evidence their desire to complete the project nonetheless. This is in fact what was contemplated by the contract here at issue. Further, this was drafted with an eye toward providing fairness to both parties: fair compensation to Trinity in exchange for the promise of fair completion of the project in spite of unanticipated difficulties.

(Trial Ct. Op. at 11.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

James Corp. v. North Allegheny School District
938 A.2d 474 (Commonwealth Court of Pennsylvania, 2007)
Bilt-Rite Contractors, Inc. v. Architectural Studio
866 A.2d 270 (Supreme Court of Pennsylvania, 2005)
Department of General Services v. Pittsburgh Building Co.
920 A.2d 973 (Commonwealth Court of Pennsylvania, 2007)
A. G. Cullen Construction, Inc. v. State System of Higher Education
898 A.2d 1145 (Commonwealth Court of Pennsylvania, 2006)
Wright v. Denny
33 A.3d 687 (Commonwealth Court of Pennsylvania, 2011)
Commonwealth v. Cumberland Construction Co.
494 A.2d 520 (Commonwealth Court of Pennsylvania, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
Trinity Contracting, Inc. v. Municipal Sewage Authority of the Twp. of Sewickley and Gibson-Thomas Engineering Co., Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/trinity-contracting-inc-v-municipal-sewage-authority-of-the-twp-of-pacommwct-2015.