Bilt-Rite Contractors, Inc. v. Architectural Studio

866 A.2d 270, 581 Pa. 454, 61 A.L.R. 6th 739, 2005 Pa. LEXIS 99
CourtSupreme Court of Pennsylvania
DecidedJanuary 19, 2005
Docket74 MAP 2002
StatusPublished
Cited by249 cases

This text of 866 A.2d 270 (Bilt-Rite Contractors, Inc. v. Architectural Studio) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bilt-Rite Contractors, Inc. v. Architectural Studio, 866 A.2d 270, 581 Pa. 454, 61 A.L.R. 6th 739, 2005 Pa. LEXIS 99 (Pa. 2005).

Opinions

OPINION

Justice CASTILLE.

This appeal raises the first impression question of whether a building contractor may maintain a negligent misrepresentation claim against an architect for alleged misrepresentations in the architect’s plans for a public construction contract, where there was no privity of contract between the architect [457]*457and the contractor, but the contractor reasonably relied upon the misrepresentations in submitting its winning bid and consequently suffered purely economic damages as a result of that reliance. The Superior Court found as a matter of law that, absent privity of contract, the contractor could not maintain such a tort action against the architect. For the reasons that follow, we reverse the order, of the Superior Court and remand to the trial court for further proceedings.

Because this Court sits in review of the trial court’s grant of appellee’s preliminary objections in the nature of a demurrer, the salient facts are derived solely from the allegations in appellant’s complaint. In such an instance, all material facts as set forth in the complaint, as well as all inferences reasonably deducible therefrom, must be accepted as true. Estate of Witthoeft v. Kiskaddon, 557 Pa. 340, 733 A.2d 623, 624 n. 1 (1999). The facts are as follows: East Penn School District entered into a contract with appellee, The Architectural Studio (“TAS”), pursuant to which TAS provided architectural services for the design and construction of a new school in Lower Macungie Township, Lehigh County. The services included the preparation of plans, drawings and specifications to be submitted to contractors for the purpose of preparing bids for the construction of the new school. In February of 1997, the school district solicited bids from contractors for all aspects of the project and included TAS’s plans, drawings and specifications in the bid documents supplied to the contractors. Appellant, Bilb-Rite Contractors, Inc. (“Bilt-Rite”), submitted its bid for general construction work on the project and on May 6, 1997, the school district awarded the general construction contract to Bilb-Rite, who was the lowest responsible bidder. On June 6, 1997, the school district and Bilt-Rite entered into a contract for the project in the base amount of $16,238,900. The contract specifically referred to, and incorporated by reference, TAS’s plans, drawings and specifications.

TAS’s plans provided for the installation of an aluminum curtain wall system, sloped glazing system and metal support systems, all of which TAS expressly represented could be [458]*458installed and constructed through the use of normal and reasonable construction means and methods, using standard construction design tables. Once construction commenced, however, Bilt-Rite discovered that the work including the aluminum curtain wall, sloped glazing and metal support systems could not be constructed using normal and reasonable construction methods, and instead required Bilt-Rite to employ special construction means, methods and design tables, resulting in substantially increased construction costs.

On November 19, 1999, Bilt-Rite sued TAS on a theory of negligent misrepresentation under Section 552 of the Restatement (Second) of Torts, claiming that TAS’s specifications were false and/or misleading, and seeking damages for its increased construction costs.1 On December 9, 1999, TAS filed [459]*459preliminary objections in the nature of a demurrer, arguing that: (1) Bilt-Rite’s action was barred by the “economic loss doctrine,” which holds that a tort plaintiff cannot recover for purely economic losses; and (2) TAS owed no duty to Bilt— Rite, with whom it had no contractual relationship. On June 22, 2000, the trial court sustained TAS’s preliminary objections and dismissed Bilt-Rite’s complaint.

The trial court deemed itself bound by the Superior Court’s decision in Linde Enterprises, Inc. v. Hazelton City Authority, 412 Pa.Super. 67, 602 A.2d 897 (1992), appeal denied, 533 Pa. 601, 617 A.2d 1275 (1992), which, the court noted, held that a contractor cannot prevail against an architect for economic damages suffered as a result of negligence in drafting specifications, absent privity of contract between the contractor and the architect. Slip op. at 2 n. 1. The trial court found further support for its decision in Palco Linings, Inc. v. Pavex, Inc., 755 F.Supp. 1269 (M.D.Pa.1990). In Palco, the district court, which was applying Pennsylvania law in a diversity action, addressed the operation of the economic loss rule in actions involving negligent misrepresentation. Palco noted that the economic loss rule reflects the concern that tort law (unlike contract law) is not generally intended to compensate parties for losses suffered as a result of a breach of duties which are assumed only by agreement; to recover in tort, there must be a breach of a duty of care imposed by law and a resulting injury. 755 F.Supp. at 1271. Looking to Illinois cases for persuasive authority, the Palco court suggested two viable exceptions to the economic loss rule in negligent misrepresentation cases: (1) where the defendant intentionally makes a false misrepresentation; and (2) where the defendant is in the business of supplying information for the guidance of others and makes negligent misrepresentations. The Palco court found that neither exception should apply to architects sued in their capacity as design professionals. Id. at 1274.

Following its discussion of Linde and Palco, the trial court noted that, although Pennsylvania courts have cited Section [460]*460552 of the Restatement (Second) with approval, no court had held that it permitted such a cause of action against a design professional. The trial court found that Bilt-Rite’s action did not fall into either of the exceptions outlined in Palco, and therefore, Bilt-Rite had failed to set forth a viable Section 552 cause of action against TAS.

On Bilt-Rite’s appeal, the Superior Court affirmed in an unpublished decision. The panel noted that the absence of privity is not an absolute bar to recovery for economic damages in tort; however, the question of which business relationships should be deemed exempt from the privity requirement (and thus exempt from the economic loss rule) must be decided on a case-by case basis. The panel further noted that the architect-contractor relationship had never been expressly included or excluded from the reach of Section 552. Therefore, the panel reasoned, its “review is guided by the principle that the tort of negligent misrepresentation, like the [sic] any action in negligence, requires the existence of a duty owed by one party to another.” Slip op. at 9, citing, inter alia, Bortz v. Noon, 556 Pa. 489, 729 A.2d 555, 561 (1999) and Gibbs v. Ernst, 538 Pa. 193, 647 A.2d 882, 889 (1994). The question then became whether, as a matter of law, an architect such as TAS who prepares and develops design drawings and specifications, owes a duty to the contractors who apply those specifications in the situation where no contractual relationship exists. The panel recognized that question was controlled by Linde;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

K.J. Bard v. PA DOC
Commonwealth Court of Pennsylvania, 2025
B. Jones v. K. Varner
Commonwealth Court of Pennsylvania, 2025
Castelli, A. v. Natural Lands Trust
Superior Court of Pennsylvania, 2024
T. Prozan v. Millcreek Twp. S.D.
Commonwealth Court of Pennsylvania, 2024
Williams, G. v. Nancy J. Shattuck Real Estate
Superior Court of Pennsylvania, 2024
Spiritrust Lutheran v. Wagman Construction, Inc.
2024 Pa. Super. 80 (Superior Court of Pennsylvania, 2024)
D.R. Malloy & E.C. Malloy v. N.A. Feigenbaum
Commonwealth Court of Pennsylvania, 2024
D.R. Hargy Malloy & E.C. Malloy v. Hon. G.M. Green
Commonwealth Court of Pennsylvania, 2024
D.R. Hargy Malloy & E.C. Malloy v. Hon. B.C. Dozor
Commonwealth Court of Pennsylvania, 2024
B. Key v. PA DOC
Commonwealth Court of Pennsylvania, 2024
Salsberg, C., Aplt. v. Mann, D.
Supreme Court of Pennsylvania, 2024
J. Brown v. PBPP
Commonwealth Court of Pennsylvania, 2024
J.M.G. v. PSP
Commonwealth Court of Pennsylvania, 2023
J. Sokorelis v. PA DOC
Commonwealth Court of Pennsylvania, 2023
J. Taylor v. DOC
Commonwealth Court of Pennsylvania, 2023
C. Talbert v. G. Little
Commonwealth Court of Pennsylvania, 2023

Cite This Page — Counsel Stack

Bluebook (online)
866 A.2d 270, 581 Pa. 454, 61 A.L.R. 6th 739, 2005 Pa. LEXIS 99, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bilt-rite-contractors-inc-v-architectural-studio-pa-2005.