Triangle Construction Co., Inc. v. Fouche and Associates, Inc.

218 So. 3d 1180, 2017 WL 1905405, 2017 Miss. App. LEXIS 260
CourtCourt of Appeals of Mississippi
DecidedMay 9, 2017
DocketNO. 2015-CA-01585-COA
StatusPublished
Cited by6 cases

This text of 218 So. 3d 1180 (Triangle Construction Co., Inc. v. Fouche and Associates, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Triangle Construction Co., Inc. v. Fouche and Associates, Inc., 218 So. 3d 1180, 2017 WL 1905405, 2017 Miss. App. LEXIS 260 (Mich. Ct. App. 2017).

Opinion

IRVING, P.J.,

FOR THE COURT:

¶ 1. Triangle Construction Company (Triangle) filed suit in the Circuit Court of Rankin County against East Madison Water Association (EMWA) and Fouche 1 and Associates (Fouche). In the suit, Triangle alleged that it had entered into a contract with EMWA that had been breached by both EMWA and Fouche, the designated engineer in the contract. It further alleged, based upon several theories, that it was *1183 entitled to recover damages from Fouche. Both Fouche and EMWA filed separate motions for summary judgment. The record does not inform us as to the status of EMWA’s motion. However, the circuit court granted Fouche’s motion and entered judgment accordingly pursuant to Rule 54(b) of the Mississippi Rules of Civil Procedure. Triangle now appeals, arguing that there existed genuine issues of material fact regarding: .

(1) whether Fouche, as the designing engineer of the water-installation project at issue in this lawsuit, breached the tort-based duties that it owed to Triangle, the contractor; to design and manage the project in a reasonable and prudent manner; (2) whether Fouche had entered into the terms of the Specifications for Water Distribution System Addition 2009 contract either as a signatory or through its conduct, as an implied[-]in-fact contract; (3) whether Fouche was the responsible party for obtaining easements for this project, on behalf of [EMWA]; and (4) whether an accord-and-satisfaction agreement had been reached between Triangle and Fouche related to the claims pleaded by Triangle against Fouche.

Finding no genuine issue of material fact, we affirm.

FACTS

¶2. Triangle won a bid offered by EMWA for a construction project to build a water system in Madison and Leake Counties. On February 9, 2010, Triangle and EMWA entered into the “Specifications for Water Distribution System Addition 2009” agreement, which incorporates many contractual documents as part of the “Contract” between Triangle and'EMWA that is now at the center .of -this dispute. 2 Triangle argues on appeal.that Fouche, the project’s engineer, was. also a party to the Contract; however, Fouche disagrees.

¶ 3. Triangle asserts that while' it performed its obligations "satisfactorily under the Contract’s terms, EMWA and Fouche did not. Specifically, Triangle argues" that EMWA and Fouche 'did not obtain' ' easements iñ a timely mamier, as they 'had agreed to do in the Contract. Triangle further argues that EMWA and' Foueh'e prematurely and negligently issued a notice instructing Triangle to .proceed ■ with its work (“Notice to Proceed”) far before the easements necessary to continue that work had been acquired. Triangle maintains 'that these failures resulted in delays, as “Triangle could not perform its contractually obligated work” in “significant areas of the [pjroject.” Furthermore,. Triangle asserts that, even after the appropriate easements had finally, been attained, neither EMWA nor Fouche gave Triangle notice that it could continue its work, resulting in more unnecessary delays.

¶4. Triangle also argues that Fouche elected to expand the size and scope of the project “long after-the [p]roject had been designed, sealed by [Fouche], and long after the Notice to Proceed ... had been issued to Triangle.” Triahgle asserts that, as a result, EMWA and -Fouche “made repeated oral promises to Triangle that [they] would execute a ‘Summary Change Order’ that would fairly compensate Triangle for the greatly-expanded scope of work that it was commanded to .perform”;' however, Triangle maintains that it never received such an order. :

*1184 ¶5. Triangle contends that, upon ultimate completion of the project, EMWA sent Triangle a check marked “Final Payment,” but the check did not compensate Triangle for its increased construction costs as a result of the delays or for the extracontractual project expansion. Triangle concedes that it cashed the check, but argues that it repeatedly asserted to EMWA—-including in a letter sent to Fouche—that it did not consider EMWA’s “final payment” to be final and that it would continue seeking the remainder of what it was owed.

116. Triangle’s lawsuit against both EMWA and Fouche, as codefendants, alleged breach of contract, unjust enrichment or quantum meruit, breach of the covenant of good faith and fair dealing, and negligence. As stated, the circuit court granted Fouche’s motion for summary judgment, leading to this appeal.

¶7. Additional facts, as necessary, will be discussed throughout the opinion.

DISCUSSION

¶ 8. Rule 56(c) of the Mississippi Rules of Civil Procedure provides that a motion for summary judgment shall be granted if “the pleadings, depositions, answers to interrogatories and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” M.R.C.P. 56(c). “We review the grant or denial of a motion for summary judgment de novo, viewing the evidence ‘in the light most favorable to the party against whom the motion has been made.’ ” Karpinsky v. Am. Nat’l Ins., 109 So.3d 84, 88 (¶9) (Miss. 2013) (quoting Pratt v. Gulfport-Biloxi Reg’l Airport Auth., 97 So.3d 68, 71 (¶5) (Miss. 2012)). “However, to survive summary judgment, the party opposing the motion may not rest upon the mere allegations or denials of his pleadings, but his response ... must set forth specific facts showing there is a genuine issue for trial.” Huynh v. Phillips, 95 So.3d 1259, 1262 (¶ 6) (Miss. 2012) (citation and internal quotation marks omitted). “Summary judgment is appropriate where a non-moving party who will bear the burden of proof at trial does not establish the existence of an essential element to his case.” Gorman-Rupp Co. v. Hall, 908 So.2d 749, 757 (¶25) (Miss. 2005) (citation omitted).

¶9. For clarity, we will first address whether Triangle’s negotiation of EMWA’s check marked “final payment” operated as an accord and satisfaction of its claims against EMWA and Fouche; next, we will address Triangle’s contract claims, including both Fouche’s status as a party to the Contract and whether Fouche was contractually obligated to acquire the easements; finally, we will address Triangle’s claims with respect to whether Fouche breached any duties in tort that it may have owed to Triangle.

1. Accord and Satisfaction

¶ 10. Triangle maintains that there are genuine issues of material fact regarding whether it reached an accord-and-satisfaction agreement with EMWA and Fouche, such that summary judgment should not have been granted.

¶ 11. Mississippi law requires satisfaction of four elements for an accord and satisfaction to exist:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
218 So. 3d 1180, 2017 WL 1905405, 2017 Miss. App. LEXIS 260, Counsel Stack Legal Research, https://law.counselstack.com/opinion/triangle-construction-co-inc-v-fouche-and-associates-inc-missctapp-2017.