Tri-Ad Constructors v. United States

36 Cont. Cas. Fed. 75,965, 21 Cl. Ct. 789, 1990 U.S. Claims LEXIS 428, 1990 WL 174945
CourtUnited States Court of Claims
DecidedNovember 9, 1990
DocketNo. 90-217C
StatusPublished
Cited by6 cases

This text of 36 Cont. Cas. Fed. 75,965 (Tri-Ad Constructors v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tri-Ad Constructors v. United States, 36 Cont. Cas. Fed. 75,965, 21 Cl. Ct. 789, 1990 U.S. Claims LEXIS 428, 1990 WL 174945 (cc 1990).

Opinion

OPINION

ANDEWELT, Judge.

In this government contract action filed pursuant to the Contract Disputes Act (CDA), 41 U.S.C. § 601 et seq., plaintiff, Tri-Ad Constructors (Tri-Ad), seeks damages relating to its contract (N62474-86-C1002) with the Department of the Navy (the Navy) for construction work at San Nicolas Island Naval Air Station, California. This action is presently before the court on defendant’s motion to dismiss the complaint pursuant to RUSCC 12(b)(1). Defendant contends this court lacks subject matter jurisdiction because plaintiff never submitted a proper claim to the contracting officer and, in any event, the contracting officer never issued a final decision on the claim.

I.

The CDA sets forth the pertinent jurisdictional requirements. Section 605(a) provides: “All claims by a contractor ... relating to a contract shall be in writing and shall be submitted to the contracting officer for a decision.” The contractor may secure review of a contracting officer’s decision denying such a claim through either an appeal to the appropriate agency board of contract appeals (Section 607) or a direct action in the United States Claims Court (Section 609). While a final decision by the contracting officer is a jurisdictional prerequisite to seeking such review, Section 605(c)(5) provides: “Any failure by the contracting officer to issue a decision on a contract claim within the period required will be deemed to be a decision by the contracting officer denying the claim and will authorize the commencement of the appeal or suit on the claim____” For claims over $50,000, Section 605(c) establishes the time period requirement, which commences upon the contracting officer’s receipt of a submitted certified claim. Section 605(c) provides, in pertinent part:

(2) A contracting officer shall, within 60 days of receipt of a submitted certified claim over $50,000—
(A) issue a decision; or
(B) notify the contractor of the time within which a decision will be issued.
(3) The decision of a contracting officer on submitted claims shall be issued within a reasonable time, in accordance with regulations promulgated by the agency, taking into account such factors as the size and complexity of the claim and the adequacy of the information in support of the claim provided by the contractor.

Here, plaintiff submitted to the Navy a letter dated April 14,1988, which purported to be a written claim under the contract and specifically requested, in two places, a final decision by the contracting officer.1 [791]*791The letter, which was addressed to the “Officer in Charge of Construction” (OICC), detailed instances of allegedly improper delay by the government and sought payments totalling in excess of $118,000. The letter was 12 pages long and described in detail the factual and legal basis of plaintiff’s request. By letter dated June 6,1988, the Resident Office in Charge of Construction (ROICC) forwarded plaintiff’s April 14 letter to the contracting officer.

The contracting officer never sent plaintiff a response characterized as a final decision on the claim. However, plaintiff did receive a response from the Assistant Resident Office in Charge of Construction (AROICC), dated June 28, 1989, which specifically addressed each item raised in plaintiff’s April 14, 1988, claim letter. The AROICC found some items meritorious and rejected all others. The response included a proposed contract modification that would compensate plaintiff for the claim items found meritorious. The response noted that if plaintiff failed to sign the proposed contract modification, the Navy would issue it unilaterally. On August 1, 1989, the contracting officer issued a unilateral modification, which states, in pertinent part: “As a unilateral modification to the subject contract, the contractor is compensated for claim items presented in [the] letter of 14 April 1988, for which Government review has concluded that merit exists.”

On September 25, 1989, plaintiff filed its original complaint in this action seeking payments plaintiff had sought unsuccessfully through its April 14, 1988, letter. That complaint was dismissed on unrelated grounds and plaintiff refiled the instant complaint on March 12, 1990.

II.

Plaintiff contends that the pertinent jurisdictional requirements for a direct action suit in this court are present. Plaintiff contends that the April 14, 1988, letter constitutes a proper written claim under Section 605(a). As to the requirement of a contracting officer decision on the claim, plaintiff contends that pursuant to Section 605(c)(5), a contracting officer decision denying the claim should be “deemed” to exist because the contracting officer received the claim on or about June 6, 1988, and failed thereafter to issue a final decision on the claim within the Section 605(c) time period.

In response, defendant disputes that the April 14, 1988, letter qualifies as a claim under Section 605(a). Defendant does not dispute that the letter provided adequate notice as to the basis and amount of the claim (Contract Cleaning Maintenance, Inc. v. United States, 811 F.2d 586, 592 (Fed.Cir.1987)) or that the letter unequivocably requested a final decision by the contracting officer. Indeed, defendant finds no fault with the body of the letter. Rather, defendant’s sole criticism of the form of the letter relates to plaintiff’s addressing the letter to the OICC and not to the contracting officer. Section 605(a) provides that the claim “shall be submitted to the contracting officer for a decision.” Defendant alleges that because plaintiff addressed its claim letter requesting a final decision from the contracting officer to the OICC, the letter was not “submitted” to the contracting officer. Defendant notes that under paragraph 66 of the contract, the OICC is the authorized representative of the contracting officer with respect to supervising the contract work but not with respect to the handling of disputes.2

[792]*792In American Pacific Roofing Co. v. United States, 21 Cl.Ct. 265 (1990), the court recently addressed the issue of the proper interpretation of “submitted” in Section 605(a). Therein, the contractor also addressed its claim to the OICC. The court concluded that the requirements of Section 605 were satisfied and explained:

The term “submit” means “to commit to another (as for decision or judgment).” WEBSTER’S NEW COLLEGIATE DICTIONARY, 1975, p. 1160. “Submit” is not entirely synonymous with the words “address” or “directly send.” A contractor may submit a claim without necessarily sending the papers directly to the [contracting officer]. The contractor, however, must clearly commit the claim to the [contracting officer] for a final decision.

Id. at 267. The court analyzed the legislative history of the CDA and found it supportive of this interpretation of Section 605.

This court agrees with the approach taken in American Pacific and relies upon the analysis therein.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Council for Tribal Employment Rights v. United States
112 Fed. Cl. 231 (Federal Claims, 2013)
L.A. Ruiz Associates, Inc. v. United States
94 Fed. Cl. 768 (Federal Claims, 2010)
M. Maropakis Carpentry, Inc. v. United States
84 Fed. Cl. 182 (Federal Claims, 2008)
Horse v. United States
49 Fed. Cl. 419 (Federal Claims, 2001)
J & E Salvage Co. v. United States
41 Cont. Cas. Fed. 77,079 (Federal Claims, 1997)
Robin Industries, Inc. v. United States
36 Cont. Cas. Fed. 76,006 (Court of Claims, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
36 Cont. Cas. Fed. 75,965, 21 Cl. Ct. 789, 1990 U.S. Claims LEXIS 428, 1990 WL 174945, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tri-ad-constructors-v-united-states-cc-1990.