Traudt v. Potomac Electric Power Co.

692 A.2d 1326, 1997 D.C. App. LEXIS 4, 1997 WL 13307
CourtDistrict of Columbia Court of Appeals
DecidedJanuary 16, 1997
Docket94-CV-781
StatusPublished
Cited by21 cases

This text of 692 A.2d 1326 (Traudt v. Potomac Electric Power Co.) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Traudt v. Potomac Electric Power Co., 692 A.2d 1326, 1997 D.C. App. LEXIS 4, 1997 WL 13307 (D.C. 1997).

Opinions

FARRELL, Associate Judge:

This appeal from summary judgment granted to defendant Potomac Electric Pow-

er Company (PEPCO) requires us to decide what duties, if any, PEPCO owed to plaintiff Traudt, an employee of an independent contractor, Waco, which PEPCO retained to remove asbestos from energized electrical cables in PEPCO’s underground manhole system. Traudt suffered severe burns when a screwdriver he was using pierced the lead insulation covering a live wire and ignited an explosion. After receiving workers’ compensation from Waco, Traudt sued PEPCO in Superior Court, alleging primarily that PEPCO breached three duties it owed him despite the intermediation of Waco: first, its statutory duty, under federal and local worksite safety laws, to provide Traudt with a safe place of employment; second, its duty to take special precautions, or to provide in the contract with Waco for the taking of such precautions, against the peculiar risk of harm that removal of a covering from energized, high voltage power lines was likely to create; and third, the duty arising from its (non-negligent) employment of Waco, which itself had been negligent in performing work PEPCO knew or had reason to know was inherently dangerous — this being a form of vicarious liability. The trial court rejected each theory of liability proffered, concluding that PEPCO had absolved itself of any duty it owed the employee of its independent contractor by informing Waco beforehand — a fact not in dispute— that the electric lines would remain energized during the asbestos removal.

We reverse and hold as a matter of law1 that PEPCO owed Traudt duties under the common law “peculiar risk” doctrine and under its local statutory duty to provide employees — whether its own or those of an independent contractor — with a safe place of employment. As to each of these theories, PEPCO does not dispute that if it owed a duty, there are genuine issues of material fact as to whether it breached the duty so as to cause Traudt’s injuries. (We reject PEP-CO’s argument as to the common law duty that Traudt was contributorily negligent as a matter of law.) We reject Traudt’s remain[1330]*1330ing theories of liability, and, in particular, join the vast majority of state courts which have held that an employer such as PEPCO is not vicariously liable to the employee of an independent contractor for the latter’s negligence.

I. The Facts

A. The Contract

PEPCO contracted with Waco, an asbestos abatement company, for the removal of asbestos from PEPCO’s electrical cables throughout its manhole system. The contract stated that Waco was an independent contractor “and not an agent of PEPCO.” It made Waco “solely responsible for the means, methods, techniques, sequences, and procedures of construction,” upon the contractor’s “represent[ation] prior to submitting his proposal [that] he [had] familiarized himself with ... the nature and extent” of the project, the job sites, and electric power. Waco was responsible for “initiating, maintaining and supervising all safety precautions and programs in connection with the Work,” and was obligated to “comply with all applicable laws, ordinances, rules, regulations, and orders of any public body” concerning job-site safety. PEPCO was under “[n]o obligation ... to review [Waco’s] compliance with safety requirements or measures.”

On the other hand, PEPCO reserved “the right at all reasonable times to inspect and test the Work,” and the right “to perform itself, or contract for and perform other or additional work on or near the Work covered by this Contract.” Waco was enjoined against doing its work in a way that “hinder[ed] the progress or completion” of such other work “being performed by PEPCO ... whether on the Project or not.” And PEP-CO could direct Waco to “cease work at any point” temporarily to “facilitate the erection of any other work” by PEPCO. Regarding safety, PEPCO required Waco to comply as well with PEPCO’s own rules concerning safety and security, and reserved the right to direct removal of any Waco employee from the work. PEPCO could provide additional workers or equipment any time Waco “refuse[d] to or neglect[ed] to supply a sufficient number of properly skilled workmen [or] sufficient equipment and/or materials,” and PEPCO could stop the work if it was defective or otherwise “fail[ed] to satisfy the requirements of the Contract.”

B. The Accident

Traudt was hired by Waco in 1989. He had not completed high school and had not taken any course dealing with electricity. Before Waco’s bid was submitted, PEPCO explained to Waco officials that the work would be performed on insulated cables that would remain “hot” or energized.2 On the other hand, Traudt alleged, PEPCO did not furnish Waco with any written information, rules, or guidelines concerning the handling of PEPCO’s power lines. Waco held a four-day asbestos removal training program for its employees which Traudt attended; the employees were to receive additional training on the job. In keeping with the contract (“The contractor shall keep a competent resident Superintendent on the Work at all times”), a Waco employee supervised the work, and PEPCO employees maintained no safety-related presence at the site except to conduct an atmospheric test for gases and visual inspection of the manhole each morning before work began.

Waco gave Traudt a hammer and metal screwdriver as tools and assigned him to work with foreman Ray Fenwick. According to Traudt, Fenwick told him to “take the tip of the screwdriver, stick it underneath one part of the [asbestos] wrap and pry it up.” After the PEPCO inspector had tested the worksite for gases and pointed out which cables were to be cleaned, he left the site and Traudt entered the manhole. He removed the asbestos from one cable and began work on a second. When he used the screwdriver to pry up the wrapping, the tip of the screwdriver pierced the lead insulation of the wiring, causing contact with a live wire. An [1331]*1331explosion ensued, the precise cause of which is disputed, but which resulted in bums to Traudt over most of his body.

In suing PEPCO, Traudt alleged inter alia that PEPCO provided him with an intrinsically unsafe place of work by leaving the power lines energized, failed to warn Waco’s workers of the dangers associated with electricity or to train them in how to remove materials from live power lines, and failed to provide him or insure that he was provided with safe tools and equipment for working around high voltage electricity.

II. Discussion

A. The Industrial Safety Act

Traudt contends that PEPCO was obligated to provide him with a safe place of employment and insure the use of safe work practices and procedures under the D.C. Industrial Safety Act, D.C.Code § 36-228(a) (1993).3 That section provides:

(a) Every employer shall furnish a place of employment which shall be reasonably safe for employees, shall furnish and use safety devices and safeguards, and shall adopt and use practices, means, methods, operations, and processes which are reasonably safe and adequate to render such employment and place of employment reasonably safe.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zagami v. Hp Enterprise Services, LLC
212 F. Supp. 3d 185 (District of Columbia, 2016)
Ridgell v. Hp Enterprise Services, LLC
District of Columbia, 2016
Delorenzo v. HP Enterprise Services, LLC
207 F. Supp. 3d 26 (District of Columbia, 2016)
Halmon-Daniels v. Experts, Inc.
212 F. Supp. 3d 55 (District of Columbia, 2016)
Frasier v. Hp Enterprise Services, LLC
212 F. Supp. 3d 1 (District of Columbia, 2016)
Jacobs v. Experts, Inc.
District of Columbia, 2016
STEPHANIE C. ARTIS v. DISTRICT OF COLUMBIA
135 A.3d 334 (District of Columbia Court of Appeals, 2016)
Merit Energy Company, LLC v. Blake Horr
2016 WY 3 (Wyoming Supreme Court, 2016)
Stephen M. Sullivan v. AboveNet Communications, Inc.
112 A.3d 347 (District of Columbia Court of Appeals, 2015)
Presley v. Commercial Moving & Rigging, Inc.
25 A.3d 873 (District of Columbia Court of Appeals, 2011)
ConocoPhillips Co. v. Henry
520 F. Supp. 2d 1282 (N.D. Oklahoma, 2007)
Halmon v. Jones Lang Wootton USA
355 F. Supp. 2d 239 (District of Columbia, 2005)
Dukes v. Sirius Construction, Inc.
2003 MT 152 (Montana Supreme Court, 2003)
Youssef v. 3636 CORP.
777 A.2d 787 (District of Columbia Court of Appeals, 2001)
Velasquez v. Essex Condominium Ass'n
759 A.2d 676 (District of Columbia Court of Appeals, 2000)
Herbert v. District of Columbia
716 A.2d 196 (District of Columbia Court of Appeals, 1998)
Traudt v. Potomac Electric Power Co.
692 A.2d 1326 (District of Columbia Court of Appeals, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
692 A.2d 1326, 1997 D.C. App. LEXIS 4, 1997 WL 13307, Counsel Stack Legal Research, https://law.counselstack.com/opinion/traudt-v-potomac-electric-power-co-dc-1997.