Transource Pennsylvania LLC v. Gladys Brown Dutrieuille

Court of Appeals for the Third Circuit·Decided June 22, 2022·No. 21-2567·Unpublished

Opinion

NOT PRECEDENTIAL

UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT

No. 21-2567

TRANSOURCE PENNSYLVANIA, LLC v.

GLADYS BROWN DUTRIEUILLE, Chairman, Pennsylvania Public Utility Commission; DAVID W. SWEET, Vice Chairman, Pennsylvania Public Utility Commission; JOHN F. COLEMAN, Commissioner, Pennsylvania Public Utility Commission, in his official capacity; RALPH V. YANORA, Commissioner, Pennsylvania Public Utility Commission, in his official capacity;

PENNSYLVANIA PUBLIC UTILITY COMMISSION

The County of Franklin*,

Appellant

* Added pursuant to F.R.A.P. 12(a)

On Appeal from the United States District Court for the Middle District of Pennsylvania (D.C. No. 1-21-cv-01101)

District Judge: Honorable Jennifer P. Wilson

Submitted Under Third Circuit L.A.R. 34.1(a):

May 6, 2022

Before: CHAGARES, Chief Judge GREENAWAY, JR. and PORTER, Circuit Judges.

(Filed: June 22, 2022)

OPINION

PORTER, Circuit Judge.

Intervention protects nonparties from the adverse effects of litigation and fosters judicial economy by preventing a multiplicity of suits. But a nonparty’s indirect and remote interests do not allow it to commandeer an existing action. Franklin County moved to intervene in this action under Federal Rule of Civil Procedure 24, asserting that the outcome of the suit would cause detrimental economic and environmental harm to Franklin County by authorizing Transource Pennsylvania, LLC (“Transource”) to condemn Franklin County’s agricultural security areas and conservation easements. The District Court denied intervention. The District Court did not abuse its discretion, so we will affirm.

I

The Commonwealth of Pennsylvania participates in an interstate regional electric grid connecting thirteen states and the District of Columbia. PJM Interconnection, LLC (“PJM”), a federally regulated regional transmission organization, operates and plans that interstate grid. See 16 U.S.C. § 791a, et seq. Because PJM determined that the existing electric transmission framework was “congested,” PJM solicited proposals to alleviate

 This disposition is not an opinion of the full Court and, under I.O.P. 5.7, is not binding precedent.

the congestion.1 Transource, through its parent company, submitted a proposal to construct the Independence Energy Connection Project (“IEC Project), consisting of two new transmission lines spanning the Pennsylvania-Maryland border. Transource entered a “Designated Entity Agreement” with PJM to construct the IEC Project in Pennsylvania.

Although federal law vests authority over interstate electrical grid planning in the federal government, states retain authority over siting and construction. See S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 76 (D.C. Cir. 2014) (“States retain control over the siting and approval of transmission facilities.”). In Pennsylvania, a public utility must obtain a certificate of public convenience from the Pennsylvania Public Utility Commission (“PAPUC”) before offering service. 66 Pa. Cons. Stat. § 1101. Transource obtained a provisional certificate of public convenience, which would allow it to conduct studies, surveys, and appraisals relating to siting and other pre-condemnation actions. But in order to make “extensions” or “improvements” to transmission facilities, a public utility must establish that the improvements are “necessary or proper for the accommodation, convenience, and safety of its patrons, employees, and the public.” 66 Pa. Cons. Stat. § 1501. Specifically, the public utility must establish:

(1) That there is a need for [the transmission line].

(2) That it will not create an unreasonable risk of danger to the health and safety of the public.

1 See U.S. Dep’t of Energy, Office of Electricity, National Electric Transmission Congestion Study 5 (Sept. 2020), https://www.energy.gov/sites/default/files/2020/10/f79/2020%20Congestion%20Study% 20FINAL%2022Sept2020.pdf (“Transmission congestion refers to the economic impacts on the users of electricity that result from operation of the system within” the “physical limits on the amount of electricity flow the system is allowed to carry.”).

(3) That it is in compliance with applicable statutes and regulations providing for the protection of the natural resources of this Commonwealth.

(4) That it will have minimum adverse environmental impact, considering the electric power needs of the public, the state of available technology and the available alternatives.

52 Pa. Code § 57.76(a). Only after the PAPUC makes all four findings can a public utility receive siting approval. On December 22, 2020, an administrative law judge recommended “that the Commission deny Transource’s Siting Applications . . . because Transource has failed to show need for the project within the meaning of [PAPUC] Regulations and the Pennsylvania Public Utility Code.” App. 94–95. The PAPUC agreed that Transource had failed to establish a “need” for the IEC Project and rescinded Transource’s certificate of public convenience. Transource filed a complaint in the District Court, alleging that the PAPUC’s decision violated the dormant Commerce Clause and was preempted by PJM’s earlier determination of need.

Franklin County moved to intervene as of right under Rule 24(a) and permissively under Rule 24(b). Franklin County expressed concern that the outcome of this suit could reverse the PAPUC’s “need” determination, which would result in Transource being “much closer to having condemnation powers.” Appellant Br. 20. The District Court denied intervention.

II2

We review the District Court’s denial of intervention as of right for abuse of discretion. Harris v. Pernsley, 820 F.2d 592, 597 (3d Cir. 1987). Federal Rule of Civil Procedure 24(a)(2) requires a district court to grant intervention as of right if “(1) the application for intervention is timely; (2) the applicant has a sufficient interest in the litigation; (3) the interest may be affected or impaired, as a practical matter by the disposition of the action; and (4) the interest is not adequately represented by an existing party in the litigation.” United States v. Territory of Virgin Islands, 748 F.3d 514, 519 (3d Cir. 2014) (quoting Harris, 820 F.2d at 596). Although Franklin County’s motion was timely, the District Court determined that Franklin County failed to establish a sufficient interest in the litigation and did not address the remaining elements. See Mountain Top Condo. Ass’n v. Dave Stabbert Master Builder, Inc., 72 F.3d 361, 366 (3d Cir. 1995) (requiring each element to be met for intervention). We find no error, much less an abuse of discretion, in the District Court’s sound reasoning.

A “sufficient interest in the litigation” is one “that is specific to [the intervenor], is capable of definition, and will be directly affected in a substantially concrete fashion by the relief sought.” Kleissler v. United States Forest Serv., 157 F.3d 964, 972 (3d Cir. 1998). “[T]he polestar for evaluating a claim for intervention is always whether the proposed intervenor’s interest is direct or remote.” Id. Franklin County’s conservation

2 The District Court had jurisdiction under 28 U.S.C. § 1331. Franklin County timely appealed, and we have jurisdiction under 28 U.S.C. § 1291. See United States v. Alcan Aluminum, Inc., 25 F.3d 1174, 1179 (3d Cir. 1993).

Free access — add to your briefcase to read the full text and ask questions with AI

Transource Pennsylvania LLC v. Gladys Brown Dutrieuille, (3d Cir. 2022).

Transource Pennsylvania LLC v. Gladys Brown Dutrieuille (Transource Pennsylvania LLC v. Gladys Brown Dutrieuille) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Brody v. Spang
957 F.2d 1108 (Third Circuit, 1992)
Catanzano v. Wing
103 F.3d 223 (Second Circuit, 1996)
Liberty Mutual Insurance Company v. Treesdale, Inc.
419 F.3d 216 (Third Circuit, 2005)
Liberty Mutual Insurance v. Pacific Indemnity Co.
76 F.R.D. 656 (W.D. Pennsylvania, 1977)
Harris v. Pernsley
820 F.2d 592 (Third Circuit, 1987)