Transcontinental Gas Pipe Line Corp. v. Federal Energy Regulatory Commission

866 F.2d 477, 275 U.S. App. D.C. 276, 1989 U.S. App. LEXIS 654
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 27, 1989
DocketNo. 88-1000
StatusPublished
Cited by1 cases

This text of 866 F.2d 477 (Transcontinental Gas Pipe Line Corp. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Transcontinental Gas Pipe Line Corp. v. Federal Energy Regulatory Commission, 866 F.2d 477, 275 U.S. App. D.C. 276, 1989 U.S. App. LEXIS 654 (D.C. Cir. 1989).

Opinion

Opinion for the Court filed by' Circuit Judge STARR.

STARR, Circuit Judge:

Transcontinental Gas Pipeline Corporation (“Transco”) seeks review of two orders of the Federal Energy Regulatory Commission approving a contested settlement of rate increases filed by Consolidated Natural Gas Transmission Corporation. Consolidated Gas Transmission Corp., 38 FERC ¶ 61,150 (1987) (“Order Approving Offer of Settlement Subject to Conditions’’); Consolidated Natural Gas Transmission Corp., 41 FERC ¶ 61,130 (1987) (“Order Granting Rehearing and Clarifications in Part”). For the reasons set forth [278]*278below, we deny Transco’s petition on the ground that, under our decision in Papago Tribal Util. Auth. v. FERC, 628 F.2d 235 (D.C.Cir.1980), the issues presented are not currently fit for judicial review.

I

This case arises out of Consolidated’s filing, on July 1, 1985, of a proposed rate increase. FERC accepted for filing and immediately suspended the proposed increase, thereby making the rates effective January 1, 1986, but subject to refund if the Commission ultimately determined that the filed rate is unreasonable. Consolidated Gas Transmission Corp., 32 FERC ¶ 61,203, 61,471 (1985); see 15 U.S.C. § 717c(e) (1985) (FERC’s authority, under section 4 of the Natural Gas Act, to accept and suspend effectiveness of filed rates).

Consolidated’s filed rate is based largely on two factors: the filed cost of service to Consolidated’s customers and a method for allocating that cost of service among those customers. Consolidated’s filing was based on a new (and higher) cost of service, but did not alter the existing cost allocation methodology (the so-called “100-A” method), which had previously been approved by the Commission for a five-year period ending March 31, 1986. Consolidated Gas Transmission Corp., 14 FERC ¶ 61,291 (1981). In its July 31, 1985 suspension order, FERC questioned the continued appropriateness of the 100-A methodology and thus invited the parties to address that issue in the forthcoming hearing on Consolidated’s proposed rate increase. 32 FERC at ¶ 61,471.

As luck would have it, the proposed hearing was obviated, in principal part, by a settlement entered into in early February 1986. 35 FERC ¶ 63,006 (1986) (“Certification of a Contested Partial Settlement”). As to the primary bone of contention, the settlement fixed Consolidated’s cost of service (the “settlement cost of service”) at a level below that contained in Consolidated’s rate filing (the “filed cost of service”). The complex, multi-faceted settlement went on to resolve all issues save for the appropriate method for allocating cost of service among Consolidated’s customers. Under the terms of the settlement, that issue was reserved for subsequent resolution.

Transco does not challenge the settlement in these various respects. Its petition is directed, instead, at Article VII of the agreement. That provision purports to fix the distribution of costs among Consolidated’s customers pending resolution of the cost allocation issue. Under Article VII, all of Consolidated’s customers would, between January 1, 1986 and March 31, 1986, pay rates based on the settlement cost of service and the 100-A cost allocation method. However, from April 1, 1986 until the Commission’s resolution of the cost allocation issue, Transco and a group of its customers (known as GSS storage customers) would pay a higher rate computed by applying the 100-A allocation method to the filed (i.e., higher) cost of service. Order Approving Offer of Settlement Subject to Conditions, J.A. at 126. The settlement, the attentive reader will have deduced, requires Transco and its GSS customers to pay more than would have been the case had the settlement (i.e., lower) cost of service been applied to them. This displeases Transco. Perhaps in recognition of Transco’s understandable desire to pay less, Article VII went on to provide that this additional amount would be deposited in an escrow account, and that Transco and the GSS customers would be entitled to the amount paid in escrow, plus interest, if they ultimately “prevail” on the cost allocation issue. Id.

Transco now challenges the legality of the interim charges imposed by means of the Article VII escrow mechanism. Transco advances two grounds of attack: first, that FERC’s approval of the escrow provision unreasonably discriminates against Transco and its GSS customers and thus constitutes arbitrary and capricious action, 5 U.S.C. § 706 (1985); and second, that the practical and legal effect of the escrow arrangement is to impose a retroactive rate change, a step flatly interdicted by section 5 of the Natural Gas Act. 5 U.S.C. § 717d (1985); see also FPC v. Louisiana Power [279]*279& Light Co., 406 U.S. 621, 643-44, 92 S.Ct. 1827, 1839-40, 32 L.Ed.2d 369 (1972).

II

As we alluded to in the opening paragraph, the question whether Transco’s challenge is presently reviewable is affected by our well-known decision in Papago Tribal Util. Auth. v. FERC, 628 F.2d 235 (D.C.Cir.1980).1 In Papago, we looked to the Supreme Court’s teaching that

[t]he ultimate test of reviewability is not to be found in an overrefined technique, but in the need of review to protect from the irreparable injury threatened in the exceptional case by administrative rulings which attach legal consequences to action taken in advance of other hearings and adjudications that may follow, the results of which the regulations purport to control.

Id. at 239, quoting Columbia Broadcasting System v. United States, 316 U.S. 407, 425, 62 S.Ct. 1194, 1204, 86 L.Ed. 1563 (1942). Mindful of this caution against elevating formalistic reasoning, in which we have all been exquisitely trained, above common-sense analysis (which we in the law sometimes overlook), we stated that reviewability would normally depend on (1) whether the challenged order was “final”; (2) whether postponing judicial review would subject the party seeking review to “irreparable injury”; and (3) whether the exercise of judicial review would not “invade the province reserved to the discretion of the agency.” Id. Applying this tripartite framework, the Papago court went on to hold that FERC’s decision not to reject a rate filing as patently unlawful was not reviewable.2

A

With respect to the first inquiry, Transco’s challenge to the settlement’s escrow provision is similar in important respects to the question found unreviewable in Papa-go.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
866 F.2d 477, 275 U.S. App. D.C. 276, 1989 U.S. App. LEXIS 654, Counsel Stack Legal Research, https://law.counselstack.com/opinion/transcontinental-gas-pipe-line-corp-v-federal-energy-regulatory-cadc-1989.