Transcontinental Gas Pipe Line Corp. v. Federal Energy Regulatory Commission

659 F.2d 1228, 212 U.S. App. D.C. 344, 1981 U.S. App. LEXIS 10952
Court of Appeals for the D.C. Circuit·Decided July 30, 1981·No. Nos. 78-1632, 78-2193·Published·Cited by 2 cases

Opinion

Opinion for the Court filed by Chief Judge SPOTTSWOOD W. ROBINSON, III.

SPOTTSWOOD W. ROBINSON, III, Chief Judge:

The challenge here is to orders of the Federal Power Commission1 denying Transcontinental Gas Pipe Line Corporation (Transco) a rate increase on natural gas shipments made while a presidential price freeze was in effect.2 The issues presented are close and complex, but we believe the Commission ultimately ruled correctly. We accordingly affirm the orders under review.

I. THE TWO STATUTES

Natural gas companies must, under Section 4(a) of the Natural Gas Act, charge just and reasonable rates for the transportation and sale of their product.3 Should they undertake to change their rates unilaterally, the proposed modifications must in most instances be filed with the Commission thirty days before going into effect.4 The Commission, either on complaint or on its own initiative, may investigate the lawfulness of any such rate, and implementation of increases may be delayed for up to five months pending a decision.5 As a rule, the Commission approves as just and reasonable those rates that cover the company’s costs of supplying the service and provide a fair margin of return.6

The regulatory impact of a second statute — the Economic Stabilization Act of 1970 7 — however, precipitated the present controversy. That legislation, since exp[347]*347ired,8 gave the President authority to freeze wages and prices in an effort to combat inflation.9 This measure was dutifully greeted by the Commission, which pledged to “carry out [its] responsibilities under the Natural Gas Act ... by establishing just and reasonable rates with a view toward consistency of those rates with the Economic Stabilization Act.”10 It is the relationship between these two statutes that we must consider.

II. THE RATE INCREASE

Transco, an interstate gas pipeline company subject to the Natural Gas Act,11 filed with the Commission in late 1972 a higher rate calculated to generate additional revenues of more than $42 million annually. The Commission suspended the new charges until July 1, 1973, and scheduled a hearing. The President imposed a 60-day price freeze on June 13,12 however, forcing postponement of any rate elevation until August 13.

Subsequently, Transco and protestants against the proposed rates settled their differences, agreeing to an increase of approximately $35 million. Of particular importance here is that the agreement, in Article IV, addressed the 43-day period from July 1 through August 12 during which the new rates had been frozen by presidential decree, and provided that Transco would be permitted to recoup its foregone revenues.13 The agreement, however, expressly conditioned the operation of Article IV on “the approval of the Cost of Living Council or any successor agency under the Economic Stabilization Act of 1970,” 14 and specified that “such rate treatment shall not be effectuated by Transco unless the Cost of Living Council or successor agency . . . permits . ...”15

Despite objections to Article IV,16 the Commission, by order on April 4, 1974, accepted the settlement, arguably in its entirety. On the controversial recoupment point, the Commission found itself “unable to determine . . . whether authority to approve Article IV resides with this Commission or with the Cost of Living Council,” 17 but announced that “[t]o the extent jurisdiction rests with this Commission, we find that Article IV is reasonable, and should be approved,” 18 Transco was accordingly directed to seek the Council’s approbation and report to the Commission on its efforts.19 The order then cryptically added that the Commission would “consider such representations by Transco in determining the action to be taken.” 20

The status of Article IV was thrown into additional confusion when the Cost of Living Council balked at endorsement of the recoupment feature of the agreement. The Council refused to expressly approve or disapprove Article IV but left little doubt as to its position, declaring that “the [Commission] should not approve any rate increase which is specifically based upon the principle of retroactive recovery of revenues ...”21 A similar position was later taken by the Council’s successor, the Office of Economic Stabilization of the Treasury Department, upon Transco’s application for [348]*348reconsideration.22 Faced with the loss of its Article IV revenues, Transco brought suit against the Treasury Department, seeking to set aside its conclusion on Article IV.23

Again fate intervened. The Economic Stabilization Act had expired on April 30, 1974;24 and five months thereafter the Temporary Emergency Court of Appeals— which has exclusive jurisdiction to consider issues arising under that legislation 25 — held in unrelated litigation26 that the Council was without authority, except in narrowly circumscribed circumstances, to issue orders affecting events transpiring after expiration of the Act.27 Consonantly, Transco and the Treasury Department stipulated that the Department lacked jurisdiction under the Stabilization Act to bar operation of the rate increase during the period of the price freeze, that Transco’s suit was moot, and that consequently the “determinations by the Cost of Living Council and Office of Economic Stabilization, respectively, do not prohibit the implementation of Article IV. . . . ”28 Transco’s suit was accordingly dismissed.29

Transco then returned to the Commission, requesting unqualified approval of Article IV. Pending resolution of the problem, the Commission allowed Transco to collect, subject to refund, the new charges from the date of expiration of the Commission’s suspension, including the 43-day period during which they were frozen by presidential order.30

Free access — add to your briefcase to read the full text and ask questions with AI

Transcontinental Gas Pipe Line Corp. v. Federal Energy Regulatory Commission, 659 F.2d 1228, 212 U.S. App. D.C. 344, 1981 U.S. App. LEXIS 10952 (D.C. Cir. 1981).

659 F.2d 1228 (Transcontinental Gas Pipe Line Corp. v. Federal Energy Regulatory Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related