Enerdyne Corporation v. Wm. Lyon Development Co., Inc., and Panorama Company, Inc., Intervenor-Appellant

488 F.2d 1237, 1973 U.S. App. LEXIS 6259
CourtCourt of Appeals for the Tenth Circuit
DecidedDecember 28, 1973
Docket73-1345, 73-1346
StatusPublished
Cited by6 cases

This text of 488 F.2d 1237 (Enerdyne Corporation v. Wm. Lyon Development Co., Inc., and Panorama Company, Inc., Intervenor-Appellant) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Enerdyne Corporation v. Wm. Lyon Development Co., Inc., and Panorama Company, Inc., Intervenor-Appellant, 488 F.2d 1237, 1973 U.S. App. LEXIS 6259 (10th Cir. 1973).

Opinion

BARRETT, Circuit Judge.

Enerdyne Corporation (Enerdyne) brought this suit against William Lyon Development Company (Lyon) for damages, alleging wrongful termination and breach of a written contract to purchase land. The trial court granted Lyon’s Motion to Dismiss. The Court also dismissed Panorama Company’s (Panorama) intervenor action for a brokerage commission. The Court held that a firm commitment from the FHA guaranteeing an insurable mortgage in the amount of $2,561,000 by Enerdyne was a condition precedent to a valid and binding contract and that Enerdyne failed to perform the condition precedent.

In January, 1971, Enerdyne filed an Application-Project Mortgage Insurance with the FHA requesting a feasibility letter for Dorado Village Apartments, Albuquerque, New Mexico. The feasibility letter was issued on May 13, 1971 to Enerdyne. It stated that the insurable mortgage would not exceed $2,561,000.

A Purchase Agreement between Ener-dyne, Seller, and Lyon, Buyer, was executed on June 15, 1971. It contained the following as a condition precedent to closing:

Seller shall have obtained from the Department of Housing and Urban Development, and/or the Federal Housing Administration a commitment guaranteeing an insurable mortgage in the amount of Two Million Five Hundred Sixty-One Thousand and No/100 Dollars ($2,561,000.00) for Dorado Village Apartments, Project Number 116-35031-PM Section 221(d)(4) said commitment to be transferred to Buyer.

Thus Lyon was not obligated to pay Enerdyne the purchase-money consideration until the firm commitment had been obtained.

Lyon was to obtain bids from contractors and determine construction costs on the Dorado Village Apartments. Lyon brought personnel to Albuquerque and opened an office. It asked Enerdyne for several delays in filing the application for conditional commitment, each of which Enerdyne agreed to. Building costs in the Albuquerque area rose substantially between June and November of 1971. The bids Lyon obtained far exceeded the costs allowed in the feasibility letter. Lyon’s and Enerdyne’s representatives met in October of 1971 in attempts to solve the high cost problem. However, no solution was reached.

On November 2, 1971 Lyon wrote Enerdyne advising that it was terminating all negotiations between them. Enerdyne had not furnished the firm commitment, the condition precedent to closing the Purchase Agreement.

Enerdyne contends that: (1) Lyon was not justified in terminating the contract; (2) there is evidence of bad faith; and (3) the District Court erred in granting Lyon’s Motion to Dismiss and further that the Court should have granted it a new trial.

Enerdyne alleges that Lyon was responsible for its failure to secure the firm commitment in that it could not obtain the firm commitment until Lyon had fulfilled its tasks. Enerdyne argues that Lyon took over the tasks of obtaining bids, cost estimates, and the preparation of applications to be submitted to the FHA for the firm commitment, and that Enerdyne could not obtain the firm commitment until Lyon had acted to completion. The delays requested by Lyon and granted by Enerdyne . for changes in the specifications caused a time lapse during which the cost of building construction materials rose dramatically. Enerdyne contends that Lyon’s performance was, accordingly, a condition precedent to its perform- *1239 anee and that Lyon’s delays placed Ener-dyne in a position where it could not perform.

The trial court’s findings cannot be set aside unless they are clearly erroneous. Sta-Rite Industries, Inc. v. Johnson, 453 F.2d 1192 (10th Cir. 1971), cert. denied, 406 U.S. 958, 92 S.Ct. 2062, 32 L.Ed.2d 344 (1972); Dailey v. City of Lawton, Oklahoma, 425 F.2d 1037 (10th Cir. 1970); United States v. Goldfield Corporation, 384 F.2d 669 (10th Cir. 1967).

We uphold the Court’s finding that Enerdyne’s failure to furnish the FHA firm commitment in accordance with the contract was no fault of Lyon and thqt Lyon did not assume Enerdyne’s duty to obtain the commitment. Enerdyne could not obtain the firm commitment because the costs of the project rose in excess of the amount estimated for the project in the feasibility letter by the time Lyon terminated the agreement.

A contracting party may repudiate his performance if a condition precedent to that performance cannot be satisfied. 3A Corbin, Contracts § 762 (1960). On the date that Lyon terminated the agreement Enerdyne could not have obtained a firm FHA commitment in accordance with the feasibility letter. The risk of a rise in construction costs belonged to Enerdyne,

Enerdyne contends that there is substantial evidence of bad faith because there was testimony that Lyon was looking for loopholes in order to terminate the agreement. The credibility of one of Lyon’s witnesses was in question. He testified that Lyon’s profits were off and it would lose profits if the contract was carried out. His credibility was a function of the trial court to evaluate. Ruth v. Utah Construction & Mining Co., 344 F.2d 952 (10th Cir. 1965). The court did not err in finding that “at all times material herein, Buyer dealt with the Seller in good faith.”

Enerdyne asserts that the Court erred in granting Lyon’s Motion to Dismiss and in refusing to grant a new trial. These contentions have been answered; we hold that they have no merit.

The intervenor, Panorama, alleges that it earned a brokerage commission when it brought Enerdyne and Lyon together.

Christopher Kelly, a real estate broker, is president of Panorama. Lyon engaged Panorama, as a broker, to find single family lots and multi-family lots where townhouses and apartments could be built. Subsequently, Kelly met Han-osh, president of Enerdyne. Hanosh had just received the feasibility letter earlier referred to from the FHA relating to an apartment development and was seeking out a buyer. Following initial negotiations between Kelly and Han-osh, Kelly brought representatives of Enerdyne and Lyon together for final discussions regarding a purchase agreement. Enerdyne was made an offer by Lyon which it accepted. Kelly, for Panorama, was then instructed by Lyon to prepare the Purchase Agreement. The contract, as drawn by Kelly and later redrafted by Lyon, contained this identical clause:

5. Commission. SELLERS agree to pay Christopher T. Kelly, d/b/a Panorama Company, Inc., a commission in the amount of six percent (6%) of the sale price of the land under this contract, plus four percent (4%) tax on the amount of the commission. (Emphasis ours).

The trial court held that Panorama (the broker) was a party to the Real Estate Purchase Agreement and was to be paid a commission only if the sale was completed and closed. We agree.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
488 F.2d 1237, 1973 U.S. App. LEXIS 6259, Counsel Stack Legal Research, https://law.counselstack.com/opinion/enerdyne-corporation-v-wm-lyon-development-co-inc-and-panorama-ca10-1973.