Trafficware Group, Inc. v. Sun Industries, L.L.C.

CourtCourt of Appeals for the Fifth Circuit
DecidedSeptember 8, 2018
Docket17-30909
StatusUnpublished

This text of Trafficware Group, Inc. v. Sun Industries, L.L.C. (Trafficware Group, Inc. v. Sun Industries, L.L.C.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trafficware Group, Inc. v. Sun Industries, L.L.C., (5th Cir. 2018).

Opinion

Case: 17-30909 Document: 00514632898 Page: 1 Date Filed: 09/07/2018

IN THE UNITED STATES COURT OF APPEALS FOR THE FIFTH CIRCUIT United States Court of Appeals Fifth Circuit No. 17-30909 FILED Summary Calendar September 7, 2018 Lyle W. Cayce Clerk

TRAFFICWARE GROUP, INCORPORATED, Individually and as Successor in Interest to Naztec, Incorporated,

Plaintiff,

versus

SUN INDUSTRIES, L.L.C.; SUN ELECTRICAL & INSTRUMENTATION, L.L.C.,

Defendants–Appellees Cross–Appellants,

COMMAND CONSTRUCTION INDUSTRIES, L.L.C.; OHIO CASUALTY INSURANCE COMPANY,

Third Party Defendants– Appellants Cross–Appellees.

Appeals from the United States District Court for the Middle District of Louisiana No. 3:15-CV-106 Case: 17-30909 Document: 00514632898 Page: 2 Date Filed: 09/07/2018

No. 17-30909 Before JONES, SMITH, and COSTA, Circuit Judges. JERRY E. SMITH, Circuit Judge:*

This is a dispute over a construction subcontract. In this appeal from a jury verdict, Command Construction Industries, L.L.C. (“Command”), chal- lenges the district court’s ruling on its Federal Rule of Civil Procedure 50(b) motion, its attorney fees award, and the award of damages. Sun Industries, L.L.C. (“Sun”), cross-appeals seven of the jury’s findings on sufficiency grounds, the award of attorney fees to Command, and the grant of Command’s motion in limine.

I. Command served as the general contractor to complete a road project for the Louisiana Department of Transportation and Development (“DOTD”). Command executed a subcontract with Sun to provide signalization and elec- trical work, which commenced in the summer of 2013. Several disputes arose, causing Sun to walk off the job before completion. Sun claims that was because of nonpayment and Command’s failure to provide a time schedule and to super- vise. Command asserts the delays were on account of Sun’s leaving the project and its failure to order materials timely after DOTD had expanded the scope of the project. Sun eventually returned to complete the subcontract work, but disagreement continued, leading to a four-day jury trial.

Command prevailed on the contract issues. The jury found that Sun had defaulted on its contractual obligations and awarded Command $60,936.26, less than the $247,469.32 requested in Command’s sworn statement of

* Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not be published and is not precedent except under the limited circumstances set forth in 5TH CIR. R. 47.5.4. 2 Case: 17-30909 Document: 00514632898 Page: 3 Date Filed: 09/07/2018

No. 17-30909 damages. The jury also found that Command had made all required payments to Sun before Sun demobilized.

There were two findings in favor of Sun. First, the jury found Command liable in tort for damage caused to a conduit Sun had constructed before leav- ing the project. The jury awarded only $20,872.18 of the $62,616.55 Sun claimed it incurred for repairs. Second, the jury found that Command did not have reasonable cause to withhold payments to Sun after it returned to the job.

The district court made several post-trial rulings. It first denied Com- mand’s Rules 50(b) and 59(e) motions. It then found Command was the pre- vailing party for attorney fees, awarded Command seventy-five percent of its attorney fees, and apportioned costs between both parties. The district court also awarded Sun prejudgment interest on the net amount Command still owed Sun under the subcontract.

In this diversity case, 1 we look to Louisiana law for the rule of decision. In re Katrina Canal Breaches Litig., 495 F.3d 191, 206 (5th Cir. 2007). We affirm with the exception of the denial of Command’s Rule 50(b) motion regard- ing the damaged conduit and the reduction of Command’s attorney fee award.

II. Sun challenges seven of the jury’s findings, claiming there is insufficient evidence. But because Sun never filed a Rule 50 motion, those issues are raised for the first time on appeal. “Absent a postverdict 50(b) motion, we are

1 The initial suit was brought by Trafficware Group, Inc. (“Trafficware”), against Sun and Merchants Bonding Co. (“Merchants”). Complete diversity existed between those parties under 28 U.S.C. § 1332. After Trafficware sued, Sun filed a third-party demand against Command. Both Sun and Command are Louisiana citizens for purposes of § 1332. The dis- trict court exercised ancillary jurisdiction over the third-party demand. That jurisdiction existed even after Trafficware settled its suit three days before trial. See Molett v. Penrod Drilling Co., 919 F.2d 1000, 1004 (5th Cir. 1990). 3 Case: 17-30909 Document: 00514632898 Page: 4 Date Filed: 09/07/2018

No. 17-30909 ‘powerless’ to compel, on the basis of insufficiency of the evidence, the district court to enter judgment contrary to the one it allowed to stand or to order a new trial.” 2 Thus we do not review those evidentiary challenges.

A. Command challenges two of the jury’s findings and raised a Rule 50(b) motion for each. In reviewing a motion for judgment as a matter of law in a case tried to a jury, our review is “especially deferential,” and “we draw all reasonable inferences and resolve all credibility determinations in the light most favorable to the nonmoving party.” 3 “A jury verdict must be upheld unless there is no legally sufficient evidentiary basis for a reasonable jury to find as the jury did.” 4

1. Command challenges the amount of damages for Sun’s breach of con- tract. Under the subcontract, Command’s sworn itemization of damages is presumptively correct. Because Sun’s only rebuttal of the presumption was that Command was entitled to no damages, and the jury did not make that finding, Command claims the jury relied on speculation and conjecture by not awarding it the full amount of $247,469.32 shown in its itemization. The evidence is sufficient to support the verdict. The jury was free to give the degree of credibility to Command’s witnesses and evidence it thought proper. It was not confined to choosing an all-or-nothing damages calculation.

McLendon v. Big Lots Stores, Inc., 749 F.3d 373, 374 (5th Cir. 2014) (quoting Ortiz 2

v. Jordan, 562 U.S. 180, 190 (2011)). Carley v. Crest Pumping Techs., L.L.C., 890 F.3d 575, 578 (5th Cir. 2018) (quoting 3

Heck v. Triche, 775 F.3d 265, 272 (5th Cir. 2014)). 4 Heck, 775 F.3d at 273 (quoting Foradori v. Harris, 523 F.3d 477, 485 n.8 (5th Cir. 2008)). 4 Case: 17-30909 Document: 00514632898 Page: 5 Date Filed: 09/07/2018

No. 17-30909 2. Command questions the jury’s award of partial damages to Sun for the damaged conduit. The damage occurred sometime between March and May 2014, during which time Sun had walked off the project. Command cites Sec- tion 6 of the Subcontract, which makes Sun “solely responsible for all materials . . . until the subcontract work is completed to [DOTD’s] satisfaction.” The state did not issue acceptance of the work until August 31, 2015, so Command claims that a straightforward reading of the subcontract placed the risk of loss squarely on Sun.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mathis v. Exxon Corporation
302 F.3d 448 (Fifth Circuit, 2002)
United States v. Ragsdale
426 F.3d 765 (Fifth Circuit, 2005)
Foradori v. Harris
523 F.3d 477 (Fifth Circuit, 2008)
Ortiz v. Jordan
131 S. Ct. 884 (Supreme Court, 2011)
Melancon Equipment v. National Rental Co.
978 So. 2d 1053 (Louisiana Court of Appeal, 2008)
In Re Katrina Canal Breaches Litigation
495 F.3d 191 (Fifth Circuit, 2007)
Peyton Place, Condominium Associates, Inc. v. Guastella
18 So. 3d 132 (Louisiana Court of Appeal, 2009)
Cangelosi v. Allstate Ins. Co.
680 So. 2d 1358 (Louisiana Court of Appeal, 1996)
Mini Togs Products, Inc. v. Wallace
513 So. 2d 867 (Louisiana Court of Appeal, 1987)
Green v. Taca International Airlines
304 So. 2d 357 (Supreme Court of Louisiana, 1974)
Stone Insurance, Inc. v. Beyer-Beeson Insurance Agency, Inc.
45 So. 3d 1125 (Louisiana Court of Appeal, 2010)
Charles McLendon v. Big Lots Stores, Incorporated
749 F.3d 373 (Fifth Circuit, 2014)
Raymond Heck v. Kenneth Buhler
775 F.3d 265 (Fifth Circuit, 2014)
Southern Siding Co. v. Raymond
703 So. 2d 44 (Louisiana Court of Appeal, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
Trafficware Group, Inc. v. Sun Industries, L.L.C., Counsel Stack Legal Research, https://law.counselstack.com/opinion/trafficware-group-inc-v-sun-industries-llc-ca5-2018.