Bess Caroline Molett, Ind., Etc. v. Penrod Drilling Company, Gearench, Inc., Third Party v. Columbus-Mckinnon, Inc., Third Party

919 F.2d 1000, 1990 U.S. App. LEXIS 22130, 1990 WL 193273
CourtCourt of Appeals for the Third Circuit
DecidedDecember 26, 1990
Docket90-4170
StatusPublished
Cited by9 cases

This text of 919 F.2d 1000 (Bess Caroline Molett, Ind., Etc. v. Penrod Drilling Company, Gearench, Inc., Third Party v. Columbus-Mckinnon, Inc., Third Party) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bess Caroline Molett, Ind., Etc. v. Penrod Drilling Company, Gearench, Inc., Third Party v. Columbus-Mckinnon, Inc., Third Party, 919 F.2d 1000, 1990 U.S. App. LEXIS 22130, 1990 WL 193273 (3d Cir. 1990).

Opinion

CLARK, Chief Judge:

The plaintiffs in this action entered into a settlement agreement with defendant Gear-ench, Inc. (Gearench). A prior decision of this court established that Gearench is entitled to indemnification from third-party defendant Columbus-MeKinnon, Inc. (Columbus-McKinnon). See Molett v. Penrod Drilling Co., 826 F.2d 1419, 1429 (5th Cir. 1987) (“Molett I In Molett I, we held that Gearench could recover the entire settlement amount from Columbus-MeKinnon if the settlement was reasonable. See id. at 1430. We remanded the case to the district court for a determination of whether the settlement was reasonable. The district court held that it was. On a second appeal, we held that the district court lacked admiralty jurisdiction, and we remanded for a determination of whether the district court had diversity or ancillary jurisdiction. See Molett v. Penrod Drilling Co., 872 F.2d 1221, 1222 (5th Cir.1989) (“Molett II”), cert. denied, — U.S.-, 110 S.Ct. 563, 107 L.Ed.2d 558 (1989). The district court held that it had ancillary jurisdiction over Gearench’s third-party claim and reaffirmed that the settlement was reasonable. Columbus-McKinnon’s third appeal to this court raises the following issues: (1) subject matter jurisdiction, (2) the reasonableness of the settlement, and (3) prejudice from failure to give notice of settlement negotiations or to timely tender defense of the suit. We affirm.

I. Background facts and proceedings below.

On January 27, 1983, John Molett, III (Molett) and Harold E. Landry (Landry) were killed in an accidental fall while constructing the derrick on a jack-up barge owned by Penrod Drilling Company (Pen-rod). Penrod had contracted with Marathon LeTourneau Company (Marathon) to construct the rig at Marathon’s shipyard near Vicksburg, Mississippi. The completed rig would have been too tall to pass under bridges between Vicksburg and the Gulf of Mexico. Marathon therefore towed the rig to Belle Chasse, Louisiana for final outfitting which included erection of leg sections and a derrick. Marathon subcontracted with McBroom Rig Builders, Inc. (McBroom) to erect the derrick. McBroom employed Molett and Landry.

On the day of the accident, Molett and Landry were completing construction of the top sections of the derrick. In order to lift materials to the top of the derrick, McBroom used an apparatus known as a “gin pole” which Penrod had fabricated. The forty-foot pole was equipped with pulleys and other tackle. The pole could be used as a portable stiff-leg crane by anchoring one end to the derrick and leaning the other end away from the derrick. As construction progressed, it was occasionally necessary to “jump” the gin pole farther up the derrick so that materials could be lifted higher. “Jumping the gin pole” consisted of drawing the pole upward by means of pulleys and a chain attached to the uppermost derrick beams. The base of the gin pole would be detached from the derrick, the lift executed, and the gin pole resecured at a higher level.

During the first jump on the day of the accident, Molett and Landry were standing on a scaffold 147 feet above the rig floor waiting for the gin pole to be raised. To lift the gin pole, McBroom employees wrapped a new spinning chain around the top derrick beams and attached to it a snatch block and related tackle. Two hooks had been attached to the chain, and one was inserted into the chain to secure it to the beam. The second hook was left dangling, unused, over the side of the beam. As the lift was attempted, the gin *1003 pole suddenly broke loose and fell, hitting the scaffold on which Molett and Landry were standing. Molett and Landry and most of their equipment fell to the rig floor and both men were killed. Neither man was wearing a safety line when the accident occurred.

After the accident, McBroom employees discovered a chain still hanging from the top derrick beam, almost entirely unwound and missing one hook, and the snatch block and its tackle were found intact on the rig floor. The missing hook and any remnant of the chain that may have been attached to it were never recovered.

The survivors of Molett and Landry brought wrongful death actions against Penrod, Marathon, and other companies believed to be the manufacturers of the chain and hook used to lift the gin pole. After some time, it was discovered that the chain bore Gearench’s trademark and that Kulko-ni, Inc. (Kulkoni) manufactured the hook. Plaintiffs thereupon amended their complaint to name Gearench and Kulkoni as defendants guilty of manufacturing defective products. Gearench filed a third-party demand against Columbus-McKinnon contending that Columbus-McKinnon had actually manufactured the allegedly defective chain and that Gearench had not contributed to the alleged defect in any way. Gear-ench also contended that Penrod was at fault for failing to ensure that McBroom employees used safety lines and sought contribution from Penrod.

The case was tried to a jury. During jury deliberations, Gearench settled and agreed to pay each plaintiff family $1,000,-000. While Gearench’s counsel was informing the judge that Gearench had settled, the jury announced that it had reached a verdict. The judge stated that it was his intention not to receive the jury verdict because of the settlement and that he would proceed to decide Gearench’s indemnity and contribution claims against Columbus-McKinnon and Penrod. None of the parties objected. The judge discharged the jury and decided the indemnity and contribution issues after argument and briefing.

The judge found that the accident occurred because the chain suspending the gin pole broke. He also found that Columbus-McKinnon manufactured the chain and that the chain was manufactured defectively. The judge found that Gearench was unaware of the manufacturing defect. Penrod was found to owe no duty to ensure that McBroom employees wore safety lines.

The court concluded that, under either Louisiana or maritime law, Columbus-McKinnon was strictly liable for manufacturing the defective chain. The court also concluded that Gearench would have been strictly liable to the plaintiffs as a non-negligent retailer but was entitled to full indemnity for the settlement from Columbus-McKinnon under either Louisiana or maritime law.

Columbus-McKinnon appealed the district court’s ruling on indemnity. This court affirmed Gearench’s entitlement to indemnity, held that Louisiana law rather than maritime law governed Gearench’s indemnity or contribution claims, and remanded “for specific findings on the reasonableness of the amount of the settlement.” Molett I, 826 F.2d at 1430. On remand, the district court declared that the settlement was reasonable and assigned reasons for this conclusion.

Columbus-McKinnon’s second appeal argued that the settlement was unreasonable and that the district court lacked subject matter jurisdiction. Plaintiffs had originally pleaded admiralty and diversity jurisdiction, but Molett I established that maritime law did not govern Gearench’s indemnity or contribution claims.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
919 F.2d 1000, 1990 U.S. App. LEXIS 22130, 1990 WL 193273, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bess-caroline-molett-ind-etc-v-penrod-drilling-company-gearench-ca3-1990.