Town of Amherst v. Omnipoint Communications Enterprises, Inc.

173 F.3d 9, 1999 WL 174253
CourtCourt of Appeals for the First Circuit
DecidedApril 2, 1999
Docket98-2061
StatusPublished
Cited by151 cases

This text of 173 F.3d 9 (Town of Amherst v. Omnipoint Communications Enterprises, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Amherst v. Omnipoint Communications Enterprises, Inc., 173 F.3d 9, 1999 WL 174253 (1st Cir. 1999).

Opinion

BOUDIN, Circuit Judge.

This is an appeal by the Town of Amherst, New Hampshire; from an injunction granted by the district court. The injunction, granted on cross-motions for summary judgment, directed the town to grant permits to Omnipoint Communications Enterprises, Inc. (“Omnipoint”), to build facilities to provide wireless telephone services. The case presents difficult issues under the Telecommunications Act of 1996, 47 U.S.C. § 151 et seq. The background events are generally undisputed.

Omnipoint is a major provider of wireless telephone service to the public. In March 1997 or thereabouts, Omnipoint began designing a wireless digital system for southern New Hampshire. 1 In that same month, the Town of Amherst adopted at the town meeting an ordinance governing the placement of wireless communications facilities in the town. See Amherst, N.H., Ordinance (Mar. 11, 1997) (“the March 1997 ordinance”). The town meeting also authorized the town Board of Selectmen (“the Selectmen”) to make agreements with carriers to site towers on town properties. Under New Hampshire law, the town meeting legislates for the town and the Selectmen are the principal executive body. See N.H.Rev.Stat. Ann. § 672 et seq.

For zoning purposes, Amherst is divided into 13 districts. The March 1997 ordinance prohibits siting of the towers in four of the districts, although those prohibitions may be overcome if a variance is obtained. In four other districts, towers are allowed only through the grant of a “special exception”; the conditions for such a special *11 exception are set out in the ordinance. 2 The ordinance also imposes setback requirements for towers in the “allowed” districts, requiring towers to be set back at least 500 feet from Route 101, set back twice the tower height from residential property lines, and set back a distance equivalent to the tower height from all other roads and certain other prescribed areas. See March 1997 ordinance.

In April 1997, the Amherst Selectmen began negotiating with Omnipoint and also advertised to solicit interest from other carriers who might wish to locate a system in Amherst. Omnipoint then designed a system comprising four 190-foot towers— tall enough to allow co-location of antennas by up to four other providers who might compete with Omnipoint. Towers are very expensive, often costing $500,000 or so each; co-location increases tower height but reduces the number of towers and greatly reduces overall costs because fewer towers are needed and because a tower’s cost does not increase proportionately with height.

In late April 1997, the Federal Communications Commission granted Omnipoint a non-exclusive license to provide wireless digital telephone service in New England, including southern New Hampshire. Under the license, Omnipoint must make service available to 25 percent of the population in the region within five years and 50 percent within ten years. Omnipoint wants to provide service not only within the town of Amherst but also for transients who are using Route 101, an important travel route in southern New Hampshire that traverses Amherst, running roughly from northeast to southwest.

Omnipoint and the Selectmen reached agreement in August 1997 and signed leases for three town-owned sites along Route 101; on each, Omnipoint proposed to construct a 190-foot tower. It was also agreed that the town would receive a portion of revenue from Omnipoint and any other providers co-loeating on the towers constructed on town-owned land. The Selectmen wrote a letter endorsing the proposed towers to the Amherst Zoning Board of Adjustment (“the Board”), a separate local body that regulates zoning matters. See N.H.Rev.Stat. Ann. § 674:33. The leases made clear- that the responsibility to procure Board approval rested on Omnipoint’s shoulders.

Starting in the northeast, the first tower was to be sited near the northern entrance to the town on the so-called Bragdon Farm site owned by the town. Construction of this tower required a special exception under the Amherst ordinance and two variances from the setback restrictions from the Board; no use variance was required. This was also true of the second site on which a town-owned recycling center was located. Under state law, variances require a showing of hardship. See note 6, below.

The third tower site agreed to by the Selectmen — clearly the most controversial — was a town-owned “public safety” complex where a somewhat shorter tower already exists for wireless communication by the police and fire department. Omni-point proposed to construct a 190-foot tower that could also be used by the police and fire department. However, this area is denominated a historic district and siting towers in such a district is prohibited under the town’s March 1997 zoning ordinance absent a use variance. Thus, Omni-point required a use variance, a setback variance, and a separate permit from the Historic District Commission, another local body.

Omnipoint also reached agreement with a church to locate a fourth tower on church *12 land near Route 101. The fourth site was in a district where a tower could be constructed with a special exception and, in this case, with one setback variance. This area, located to the south of the other proposed sites, lay just north of the main population center in Amherst. Omnipoint also applied for and secured a single site in the southern area of the town — where neither special exception nor variance was required and neither, therefore, was Board approval. There is no indication that service for Amherst can be provided using this single tower.

In early September 1997, Omnipoint applied to the Board for the required special exceptions and variances on all four sites. It also applied to the Historic District Commission for approval to construct on the site located at the safety complex. On September 16, 1997, Omnipoint made a presentation before the Board, which received public comment and then deferred matters until October. The Board’s minutes summarize such oral presentations but no transcript exists. Two days later, the Historic District Commission met in public session and denied Omnipoint’s application, apparently in Omnipoint’s absence.

Omnipoint immediately appealed the Commission’s decision to the Zoning Board of Adjustment, which can override the Historic District Commission. On October 21, 1997, the Zoning Board met again. Omni-point provided additional information and answered more questions from the Board, and public comments were again taken. The hearing was continued until November 1997, when the same process was repeated. The Board then deferred decision until December 1997, saying that there would be no more presentations or public testimony. At all of these meetings, a number of residents questioned or opposed the project, citing primarily concerns about visual blight and impairment of property values.

On December 8, 1997, Omnipoint filed the present lawsuit against the town asserting that Amherst’s delay violated the Telecommunications Act of 1996.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Industrial Commc’ns v. Town of Alton, et al.
2012 DNH 168 (D. New Hampshire, 2012)
New Cingular Wirelss v. Town of Stoddard, et
2012 DNH 046 (D. New Hampshire, 2012)
MetroPCS New York, LLC v. Village of East Hills
764 F. Supp. 2d 441 (E.D. New York, 2011)
T-Mobile Northeast LLC v. Fairfax County Board of Supervisors
759 F. Supp. 2d 756 (E.D. Virginia, 2010)
T-MOBILE NORTHEAST LLC v. City of Lawrence
755 F. Supp. 2d 286 (D. Massachusetts, 2010)
New Cingular v. Candia, NH, et al.
2010 DNH 145 (D. New Hampshire, 2010)
MetroPCS New York, LLC v. City of Mount Vernon
739 F. Supp. 2d 409 (S.D. New York, 2010)
Wireless Towers, LLC v. CITY OF JACKSONVILLE, FLORIDA
712 F. Supp. 2d 1294 (M.D. Florida, 2010)
Wireless Towers, LLC v. St. Johns County, Fla.
690 F. Supp. 2d 1282 (M.D. Florida, 2010)
T-MOBILE CENTRAL LLC v. City of Fraser
675 F. Supp. 2d 721 (E.D. Michigan, 2009)
T-MOBILE NORTHEAST LLC v. Town of Ramapo
701 F. Supp. 2d 446 (S.D. New York, 2009)
Industrial Tower v. East Kingston, NH
2009 DNH 127 (D. New Hampshire, 2009)
Industrial Tower v. Town of Epping
2009 DNH 121 (D. New Hampshire, 2009)
Sprint Spectrum L.P. v. Town of Swansea
574 F. Supp. 2d 227 (D. Massachusetts, 2008)
T-MOBILE SOUTH LLC v. City of Jacksonville, Fla.
564 F. Supp. 2d 1337 (M.D. Florida, 2008)
Rweyemamu v. Cote
Second Circuit, 2008
Verizon Wireless v. DOUGLAS CNTY. KS BD. OF COM'RS.
544 F. Supp. 2d 1218 (D. Kansas, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
173 F.3d 9, 1999 WL 174253, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-amherst-v-omnipoint-communications-enterprises-inc-ca1-1999.