New Cingular Wirelss v. Town of Stoddard, et

2012 DNH 046
CourtDistrict Court, D. New Hampshire
DecidedFebruary 16, 2012
DocketCV-11-388-JL
StatusPublished

This text of 2012 DNH 046 (New Cingular Wirelss v. Town of Stoddard, et) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New Cingular Wirelss v. Town of Stoddard, et, 2012 DNH 046 (D.N.H. 2012).

Opinion

New Cingular Wirelss v . Town of Stoddard, et CV-11-388-JL 2/16/12

UNITED STATES DISTRICT COURT DISTRICT OF NEW HAMPSHIRE

New Cingular Wireless PCS, LLC

v. Civil N o . 11-cv-388-JL Opinion N o . 2012 DNH 046 Town of Stoddard, New Hampshire, and Zoning Board of Adjustment of the Town of Stoddard, New Hampshire

MEMORANDUM ORDER

The question in this case is whether the Town of Stoddard’s

Zoning Board of Adjustment, by granting rehearing of its decision

to approve plaintiff New Cingular Wireless PCS, LLC’s application

to construct a wireless telecommunications facility, violated

§ 704(a) of the Telecommunications Act of 1996 by failing to act

on the application “within a reasonable period of time.” 47

U.S.C. § 332(c)(7)(B)(ii). By ruling of the Federal

Communications Commission, a local government must act on siting

applications like New Cingular’s within 150 days–-a timeframe

that can be extended with the applicant’s consent–-and failure to

act within this time is presumptively unreasonable under

§ 704(a). In the Matter of Petition for Declaratory Ruling to

Clarify Provisions of Section 332(c)(7)(B) to Ensure Timely

Siting Review, 24 FCC Rcd. 13994 (Nov. 1 8 , 2009) (colloquially

referred to as the “Shot Clock Ruling”). Here, New Cingular

agreed to extend the 150-day period by three months, and the Board approved its application within that agreed-upon deadline.

Two months after the deadline expired, however, the Board voted

to grant rehearing of its approval pursuant to a New Hampshire

law providing for rehearing of zoning decisions. See N.H. Rev.

Stat. Ann. §§ 677:2, 677:3.

New Cingular claims that this amounts to a violation of

§ 704(a), as clarified by the Shot Clock Ruling. New Cingular

further alleges that what it characterizes as the Board’s

“failure to act” also amounted to (a) an effective prohibition on

the provision of wireless services in and around Stoddard and (b)

a de facto denial of the application that was unsupported by

substantial evidence, both of which constitute further violations

of § 704(a). This court has jurisdiction pursuant to 28 U.S.C. §

1331 (federal question).

The Town and the Board (collectively referred to herein as

“the Town”) have moved to dismiss New Cingular’s complaint, see

Fed. R. Civ. P. 12(b)(6) arguing that the Board did act on the

application within a reasonable time by approving it before the

agreed-upon deadline, and that the subsequent decision to grant

rehearing is irrelevant. Alternatively, they argue, the Shot

Clock Ruling establishes only a presumption of unreasonableness,

and that presumption is overcome by the circumstances surrounding

their decisions, as alleged in New Cingular’s complaint. They

2 further argue that the “effective prohibition” and “substantial

evidence” claims must be dismissed because such claims may only

be premised on the denial of a siting application, and New

Cingular’s application was never denied.

After hearing oral argument, the motion to dismiss is

granted in part and denied in part. The Shot Clock Ruling

contemplates that local governments will resolve siting

applications for wireless facilities within its deadline. But

New Cingular’s application is not “resolved,” because New

Cingular may not act in accordance with the initial approval

until the rehearing process is complete. Nor can the court say

as a matter of law that the presumption of unreasonableness that

the Shot Clock Ruling assigns to a delay of this length is

overcome here, as the facts alleged in the complaint suggest that

rehearing was a tactic calculated to unduly prolong the

application process. Insofar as the motion seeks dismissal of

New Cingular’s claim that the Board failed to act on its

application within a reasonable time, then, it is denied.

Because, however, claims for effective prohibition and lack of

substantial evidence cannot lie unless a local government has

denied the plaintiff’s application, and the Board has not done so

here, the motion to dismiss those claims is granted.

3 I. Applicable legal standard

To survive a motion to dismiss under Rule 12(b)(6), the

plaintiff’s complaint must make factual allegations sufficient to

“state a claim to relief that is plausible on its face.”

Ashcroft v . Iqbal, 129 S . C t . 1937, 1949 (2009) (quoting Bell

Atl. Corp. v . Twombly, 550 U.S. 5 4 4 , 570 (2007)). In ruling on

such a motion, the court must accept as true all well-pleaded

facts set forth in the complaint and must draw all reasonable

inferences in the plaintiff’s favor. See, e.g., Martino v .

Forward Air, Inc., 609 F.3d 1 , 2 (1st Cir. 2010). Nonetheless,

the “allegations must be enough to raise a right to relief above

the speculative level,” Twombly, 550 U.S. at 555, and “[a]

pleading that offers labels and conclusions or a formulaic

recitation of the elements of a cause of action will not do,”

Iqbal, 129 S . C t . at 1949. The following summary is consistent

with that approach.

II. Background

On October 1 , 2010, New Cingular filed an application with

the Stoddard Zoning Board of Adjustment, seeking permission to

construct a wireless communications facility in the town. As

initially proposed, the facility consisted of a 150-foot lattice

tower with six panel antennae mounted near the top. New Cingular

4 currently has no wireless communications facilities in Stoddard

or the abutting communities, and has a significant coverage gap

throughout Stoddard and those communities. The proposed facility

would help address that gap.

On November 1 0 , 2010, the Board held an initial public

hearing on the application. At the hearing, opponents of the

proposed facility raised concerns about the alleged health

effects of radio frequency emissions and the potential impacts of

construction. New Cingular made efforts to respond to these

concerns, and the Board held a second public hearing on December

1 5 , 2010. At the second public hearing, opponents raised

additional concerns, such as the aesthetic impact of the proposed

facility and the availability of alternative sites. New Cingular

again made efforts to address these concerns, and the Board held

a third public hearing on January 5 , 2011. The Board

subsequently held fourth, fifth, and sixth public hearings on

February 1 5 , 2011; April 1 9 , 2011; and May 5 , 2011, respectively.

Between hearings, New Cingular conducted numerous tests, and

submitted voluminous additional materials, to address the

concerns raised by opponents and Board members.

As already mentioned, and described in more detail elsewhere

in this order, the Federal Communications Commission (“FCC”) has

prescribed a presumptive deadline of 150 days within which local

5 authorities must act to approve or deny an application to

construct a wireless communications facility. That 150-day

deadline would have expired on March 1 , 2011, but New Cingular

agreed to extend it to May 3 1 , 2011. On May 2 5 , 2011, the Board

voted 3-2 in favor of granting New Cingular’s application, with

some alterations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Martino v. Forward Air, Inc.
609 F.3d 1 (First Circuit, 2010)
USCOC of Greater Missouri v. City of Ferguson, MO.
583 F.3d 1035 (Eighth Circuit, 2009)
Federal Trade Commission v. Mylan Laboratories, Inc.
99 F. Supp. 2d 1 (District of Columbia, 1999)
Oil, Chemical & Atomic Workers International Union v. Pena
62 F. Supp. 2d 1 (District of Columbia, 1999)
Omnipoint Communications Enterprises, Inc. v. Town of Amherst
74 F. Supp. 2d 109 (D. New Hampshire, 1998)
Cox Communications PCS, L.P. v. City of San Marcos
204 F. Supp. 2d 1272 (S.D. California, 2002)
MetroPCS New York, LLC v. City of Mount Vernon
739 F. Supp. 2d 409 (S.D. New York, 2010)
Guzman-Camacho v. State Insurance Fund Corp.
418 F. Supp. 2d 3 (D. Puerto Rico, 2006)
Sandford v. Town of Wolfeboro
868 A.2d 1002 (Supreme Court of New Hampshire, 2005)
New Cingular Wireless PCS, LLC v. Town of Stoddard
853 F. Supp. 2d 198 (D. New Hampshire, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
2012 DNH 046, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-cingular-wirelss-v-town-of-stoddard-et-nhd-2012.