Tonya, Inc. v. United States

39 Cont. Cas. Fed. 76,544, 28 Fed. Cl. 727, 1993 U.S. Claims LEXIS 106, 1993 WL 298711
CourtUnited States Court of Federal Claims
DecidedAugust 4, 1993
DocketNo. 91-1091C
StatusPublished

This text of 39 Cont. Cas. Fed. 76,544 (Tonya, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tonya, Inc. v. United States, 39 Cont. Cas. Fed. 76,544, 28 Fed. Cl. 727, 1993 U.S. Claims LEXIS 106, 1993 WL 298711 (uscfc 1993).

Opinion

ORDER

MOODY R. TIDWELL, III, Judge:

This case is before the court on cross-motions for summary judgment. Oral argument is deemed unnecessary. Plaintiff sought to recover bid preparation costs incurred in an attempt to negotiate a contract with the United States. For the reasons set forth below, plaintiff’s cross-motion for summary judgment is denied and defendant’s motion for summary judgment is granted.

I. Facts

In July 1988, defendant, the United States Department of the Air Force, through the Air Force Computer Acquisition Center, entered into a contract with Grumman Data Systems. The contract, entitled Headquarters Systems Replacement Program (HSRP), required Grumman to replace mainframe computers and convert existing computer programs for the 7th Communications Group at the Pentagon (7CG).

As it originally stood, the HSRP only provided for three “technical engineering management services” (TEMS) personnel. It soon became evident that the HSRP required an increase in personnel outside the scope of the original contract. As a result, on March 21,1989, Grumman presented the Air Force with an unsolicited proposal entitled “Technology Upgrade Proposal for TEMS Personnel Upgrade,” recommending the addition of eight TEMS categories. The Air Force rejected this proposal on June 7, 1989. However, soon thereafter the Director of Program Management for the HSRP noted that, while the current HSRP required Grumman to provide TEMS personnel to assist the Government in establishing and maintaining effective opera[729]*729tions, “the current TEMS support provided lack[ed] sufficient breadth, technical expertise and familiarity with the software and hardware systems acquired for the HSRP.”

In an effort to contract the needed support personnel, and in keeping with the policy of the Deputy Chief of Small Business for the Air Force District of Washington Contracting Office (AFDW) to review all new procurements for potential set aside under the Small Business Act’s Section 8(a) Set Aside Program, 15 U.S.C. §§ 631-650 (1988), the Air Force met with fifteen Small Business Administration (SBA) approved Section 8(a) prospective contractors. Plaintiff, Tonya, Inc., was among the contractors selected.

On May 18, 1989, plaintiff’s president met with 7CG technical personnel to discuss plaintiff’s corporate and technical capabilities in connection with the proposed solicitation. On June 28, 1989, the AFDW wrote to the SBA requesting approval of plaintiff for a potential set-aside commitment. In this letter, the AFDW indicated the need for, among other things, eleven labor categories of TEMS support for the 7CG, six of which carried the same title as those proposed by Grumman in their unsolicited proposal. On July 10,1989, the SBA approved the AFDW’s petition, thereby clearing the Air Force to commence negotiations with plaintiff. Later that month, the Air Force issued solicitation documents to plaintiff.

After several initial meetings with the AFDW, plaintiff submitted a draft proposal on August 3, 1989. After review and evaluation, the Air Force returned the draft proposal with comments. In September 1989, plaintiff submitted a revised proposal dated August 15, 1989. In November 15, 1989, the Air Force suffered substantial budget cuts. On November 15, 1989, at a meeting between plaintiff and the AFDW, the AFDW told plaintiff that the Air Force had no work for them. Negotiations between the Air Force and plaintiff deteriorated and the Air Force eventually canceled the solicitation.

On December 20, 1989, the Air Force conducted a meeting with Grumman to discuss the addition of nine TEMS labor categories to the original HSRP. As a result of this meeting, Grumman presented the Air Force with a modification proposal on December 21, 1989. This proposal stated that the additional categories were “necessary to increase the skill level of TEMS personnel available to the Government to parallel the technology enhancements which [had] modified the [original] con-tract____” On December 26, 1989, the AFDW, wrote plaintiff and informed it that negotiations were being canceled due to “funding constraints” and that the Air Force intended to fulfill its personnel needs under the original HSRP. Inexplicably, plaintiff’s contract file was destroyed approximately four months thereafter, in April 1989.

On April 16, 1991, plaintiff filed a complaint with this court claiming that the Air Force breached its implied obligation of fair and honest treatment of its solicitation with plaintiff, and asked for $269,750 in bid preparation costs. Plaintiff’s case was originally assigned to Judge Andewelt. Defendant moved for summary judgment on August 12, 1992. On September 30, 1992, the case was reassigned to Judge Tidwell pursuant to RCFC 77(f). The court suspended the case on November 2, 1992, in response to plaintiff’s request for extended discovery to adequately respond to defendant’s motion. On May 17, 1993, after the additional discovery, plaintiff filed a supplemental response and cross-motion for summary judgment.

II. Discussion

A. Summary Judgment

Summary judgment is appropriate when “the pleadings ... together with the affidavits ... show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” RCFC 56(c). A material fact is one which makes some difference in the outcome of a case. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247-48, 106 S.Ct. 2505, 2509-10, 91 L.Ed.2d 202 (1986); Curtis v. United States, 168 [730]*730F.Supp. 213, 216, 144 Ct.Cl. 194 (1958), cert. denied, 361 U.S. 843, 80 S.Ct. 94, 4 L.Ed.2d 81 (1959). In order to show that a material fact is genuinely at issue, the non-movant must do more than present “some” evidence on the disputed issue. Anderson, 477 U.S. at 248-50, 106 S.Ct. at 2510-11. Conclusory statements are not sufficient to defeat summary judgement. Barmag Barmer Maschinenfabrik AG v. Murata Mach., Ltd., 731 F.2d 831, 836 (Fed.Cir.1984). “If the evidence [of the non-movant] is merely colorable, or is not significantly probative, summary judgment may be granted.” Anderson, 477 U.S. at 249-50, 106 S.Ct. at 2511 (citations omitted). Because the court finds that there are no genuine issues of material fact in dispute, the case is properly before the court for disposition on cross-motions for summary judgment.

B. Standard of Review

“The recovery of bid preparation costs is a remedy that has been available to unsuccessful bidders for at least the past 30 years.” Refine Constr. Co. v. United States, 12 Cl.Ct. 56, 64 (1987). In Heyer Products Co. v. United States (Heyer I), 140 F.Supp. 409, 413, 135 Ct.Cl. 63 (1956), the Court of Claims recognized “that the bidder [has] certain rights, and that the Government [is] under an obligation to respect those rights.” As a result, the Government impliedly promises to give honest and fair consideration to all bids received and to not reject any of them arbitrarily or capriciously. Refine Constr., 12 Cl.Ct. at 64 (citing Heyer Prods. Co. v. United States (Heyer II), 177 F.Supp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Chemical Foundation, Inc.
272 U.S. 1 (Supreme Court, 1926)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Keco Industries, Inc. v. The United States
428 F.2d 1233 (Court of Claims, 1970)
Heyer Products Company v. United States
177 F. Supp. 251 (Court of Claims, 1959)
Curtis v. United States
168 F. Supp. 213 (Court of Claims, 1958)
Heyer Products Company v. United States
140 F. Supp. 409 (Court of Claims, 1956)
Refine Construction Co. v. United States
34 Cont. Cas. Fed. 75,242 (Court of Claims, 1987)
Librach v. United States
147 Ct. Cl. 605 (Court of Claims, 1959)
Continental Business Enterprises, Inc. v. United States
452 F.2d 1016 (Court of Claims, 1971)
Keco Industries, Inc. v. United States
492 F.2d 1200 (Court of Claims, 1974)
United States Fidelity & Guaranty Co. v. United States
676 F.2d 622 (Court of Claims, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
39 Cont. Cas. Fed. 76,544, 28 Fed. Cl. 727, 1993 U.S. Claims LEXIS 106, 1993 WL 298711, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tonya-inc-v-united-states-uscfc-1993.