TOMI LLC v. BREAKWATER DESIGN & BUILD INC

District Court, D. Maine·Decided July 1, 2025·No. 2:25-cv-00081·Unknown

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF MAINE TOMI LLC, ) ) Plaintiff ) ) v. ) 2:25-cv-00081-SDN ) BREAKWATER DESIGN & BUILD ) INC. et al., ) ) Defendants ) ORDER ON MOTION FOR ATTACHMENT AND ATTACHMENT ON TRUSTEE PROCESS The matter is before the Court on Plaintiff’s Motion for Attachment and Attachment on Trustee Process. (Motion, ECF No. 3.) Through the motion, Plaintiff asks the Court to approve an attachment and an attachment on trustee process in the amount of $572,975 on the property of Defendant Breakwater Design & Build Inc. (Breakwater).1 Defendants oppose the motion. (Response, ECF No. 11.) After consideration of the parties’ arguments and following a review of the record, the Court denies Plaintiff’s motion.

1 Ginny Savage and Mike Jones are also named as defendants. Plaintiff does not seek an attachment against their property. FACTUAL BACKGROUND2 In May 2022, Plaintiff and Breakwater entered a contract for the renovation of Plaintiff’s house.3 (Declaration of Thomas D. Fina ¶ 8, ECF No. 3-1 (hereinafter “Fina

1”); Declaration of Ginny Savage ¶ 7, ECF No. 11-1.) The contract for the project lists “allowances” for various aspects of the project, including labor and materials. (See Exhibit A, ECF No. 1-1.) The contract states that the monetary amount of the “total allowances” for the project is $749,300.4 (Exhibit A at 10.) Defendant contends the contract was a time and materials contract and charged

Plaintiff a 20% surcharge on materials and subcontractor work. (Savage ¶¶ 8–9.) Plaintiff asserts Defendant informed Plaintiff that the cost of the renovation “[m]ight be less, shouldn’t be more” than $749,300. (Fina 2 ¶ 1(c)). Breakwater maintains that at the start of the project, Breakwater discussed with Plaintiff the surcharge that would be added to the materials and subcontractor charges. (Savage ¶ 9.) The surcharge is not included in

2 The factual background is derived from the complaint, and the affidavits and exhibits submitted by the parties regarding the motion for attachment. In support of its motion, Plaintiff submitted affidavits by Thomas D. Fina, a 50% owner/member of TOMI, LLC, Robert L. Fulmer, the owner of Fulmer Associates, and Cameron Rubenstein, the founder and owner of Diversified Builders, Inc. Breakwater submitted affidavits from Ginny Savage, a project manager at Breakwater, and Mike Jones, Breakwater’s founder and owner. 3 Prior to this contract, in September 2021, Plaintiff contracted with Breakwater to design a renovation of Plaintiff’s house in Owl’s Head, Maine. (Fina 1 ¶ 6; Savage ¶ 4.) Throughout the design process, Plaintiff made several changes to reduce the cost of the renovation. (Declaration of Thomas D. Fina ¶ 1(a), ECF No. 13-1 (hereinafter “Fina 2”).) In late 2021, Plaintiff and Breakwater also contracted for Breakwater to perform basement remediation work. (Fina 1 ¶ 7; Savage ¶ 5.) Due to flooding, however, Plaintiff and Breakwater changed plans. (Fina 1 ¶ 7; Savage ¶ 5.) The basement remediation contract does not appear to be relevant to the current dispute. 4 Plaintiff contends the contract price for the project is $742,300, and the incorrect amount listed in the contract is due to a miscalculation. (Complaint ¶ 14; Fina 1 ¶ 9. But see Fina 2 ¶ 1(c) (stating contract price was $749,300).) the written contract. (See generally Exhibit A; Fina 1 ¶ 16(a).) Plaintiff requested that rather than impose a surcharge, Breakwater charge $50 per hour for the supervisory time

of Defendants Jones and Savage. (Fina 1 ¶ 16(a); Savage ¶ 9.) Plaintiff contends that Breakwater “would not do it, and [Plaintiff] had no choice but to pay the [surcharges] that were not being billed in accordance with the original contract.” (Fina 1 ¶ 16(a).) Breakwater asserts that it did charge for supervisory time as requested until Plaintiff changed its mind and told Breakwater to use the surcharge approach. (Savage ¶ 9.) The contract did not include a specific completion date but provided for a $10,000

bonus if the work was completed by June 15, 2023. (Exhibit A at 10; Fina 1 ¶ 11.) Plaintiff maintains that before the contract was signed, Breakwater informed Plaintiff the renovation would take “about a year” and construction would be complete by the summer of 2023. (Fina 1 ¶ 11.) At some point after the contract was signed, Plaintiff and Breakwater agreed to

revise the scope of the work. (Fina 1 ¶ 10.) The modifications increased the contract price to $765,972. (Id.) Plaintiff asserts that Breakwater also required Plaintiff to agree to change orders for work already within the scope of the original contract, increasing the contract price cost to $822,266. (Id.) Plaintiff objected to the additional change orders. (Id.)

Throughout the renovation, Breakwater and Plaintiff met regularly by videoconference to discuss the status of the project. (See Savage ¶ 12.) Plaintiff asserts that during the conferences, it expressed its concern about the cost of the renovation but Breakwater repeatedly assured Plaintiff that the project was on budget. (Fina 2 ¶ 1(f).) Plaintiff contends that eight months into the project, Breakwater informed Plaintiff that the project was over on the labor budget. (Id.) The contract included a labor allowance of

$180,000 (Exhibit A at 10); the total amount Breakwater ultimately charged Plaintiff for labor was $396,420. (Savage ¶ 13.) Breakwater maintains that the increased labor costs were due to customer decisions and conditions beyond Breakwater’s control. (Id.) Breakwater also contends that Plaintiff was aware “as the job progressed, of the fact that labor costs for the work requested were considerably outpacing the labor allowance.” (Id. ¶ 14.)

According to Plaintiff, at this point in the renovation, the house “had been completely open to the weather for more than six months” which caused damage to the house. (Fina 2 ¶ 1(g).) After the house had a “mostly completed roof and working heat,” in December 2023, Plaintiff terminated the relationship with Breakwater. (Id. ¶ 1(i).) Plaintiff claims that by this time, it had paid Breakwater $931,773.75, (Fina 1 ¶ 19);

Breakwater states Plaintiff had paid $917,502.83. (Savage ¶ 16.) Plaintiff claims that some of Breakwater’s renovation work was substandard. (Complaint ¶ 36; Fina 1 ¶ 16(c).) In support of its contention, Plaintiff cites Breakwater’s work related to the master bath shower, exterior columns, sliding glass door, wrap-around deck, exterior vent for the range hood, the casement windows, Azek exterior trim, heat

pumps and AC, two-panel door to the basement, lack of siding on the back of the house, exterior electrical outlet, subflooring, front and back doors, vanity for powder room, and new walls on first and second floors. (Fina 1 ¶ 16(c).) Breakwater disputes Plaintiff’s contentions and argues that any issues regarding the quality of the work are the result of Plaintiff’s termination of the parties’ agreement before Breakwater could complete the necessary work or due to work performed by others after Breakwater’s services were

terminated. (See Jones ¶ 6(a)–(s).) Plaintiff’s complaint, filed on March 7, 2025, contains four counts: (I) breach of contract, (II) intentional misrepresentation, (III) negligent misrepresentation, and (IV) unfair trade practices. (Complaint ¶¶ 35–67.) Defendant filed a partial motion to dismiss, seeking to dismiss the unfair trade practices claim, which motion is pending before the Court. (Motion to Dismiss, ECF No. 9; Report and Recommended Decision on Motion to

Dismiss, ECF No. 16 (recommending denial of motion).) LEGAL STANDARD Pursuant to Federal Rule of Civil Procedure 64 and District of Maine Local Rule 64, the Court applies Maine law when presented with a motion for attachment and attachment on trustee process.

Free access — add to your briefcase to read the full text and ask questions with AI

TOMI LLC v. BREAKWATER DESIGN & BUILD INC, (D. Me. 2025).

TOMI LLC v. BREAKWATER DESIGN & BUILD INC (TOMI LLC v. BREAKWATER DESIGN & BUILD INC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Parker v. Ayre
612 A.2d 1283 (Supreme Judicial Court of Maine, 1992)
Wilson v. DelPapa
634 A.2d 1252 (Supreme Judicial Court of Maine, 1993)
Porrazzo v. Karofsky
1998 ME 182 (Supreme Judicial Court of Maine, 1998)
John Sweet II v. Carl E. Breivogel
2019 ME 18 (Supreme Judicial Court of Maine, 2019)
Sweet v. Breivogel
201 A.3d 1215 (Supreme Judicial Court of Maine, 2019)