Toll Bros., Inc. v. BD. OF CHOSEN FREEHOLDERS, CTY. OF BURLINGTON

944 A.2d 1, 194 N.J. 223, 2008 N.J. LEXIS 310
CourtSupreme Court of New Jersey
DecidedMarch 31, 2008
StatusPublished
Cited by99 cases

This text of 944 A.2d 1 (Toll Bros., Inc. v. BD. OF CHOSEN FREEHOLDERS, CTY. OF BURLINGTON) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Toll Bros., Inc. v. BD. OF CHOSEN FREEHOLDERS, CTY. OF BURLINGTON, 944 A.2d 1, 194 N.J. 223, 2008 N.J. LEXIS 310 (N.J. 2008).

Opinion

Justice LONG

delivered the opinion of the Court.

In enacting the Municipal Land Use Law (MLUL), the Legislature set forth, in detail, the procedural and substantive standards it intended to guide municipalities in the exercise of the delegated zoning power over the use and development of land. Among the questions presented on this appeal are the following: (1) whether, by way of a developer’s agreement, a developer can contract to pay more than its pro-rata share for off-tract improvements, which payments could not be imposed by resolution under the MLUL; (2) whether conditions regarding off-tract improvements must be satisfied even when the scope of the developer’s project materially changes; and (3) whether a developer’s agreement immunizes such conditions from a changed circumstances analysis.

We answer all three questions in the negative. Under the MLUL, a planning board may only impose off-tract improvements on a developer if they are necessitated by the development. *230 Concomitantly, a developer cannot be compelled to shoulder more than its pro-rata share of the cost of such improvements. N.J.S.A. 40:55D-42; Holmdel Builders Ass’n v. Twp. of Holmdel, 121 N.J. 550, 570-71, 583 A.2d 277 (1990). It follows that a planning board violates the MLUL when a condition unrelated to the needs generated by a development is imposed or, if related, places on the developer an exaction in excess of its proportional share. That is so even if the developer is a willing participant in a separate developer’s agreement. A developer’s agreement is a contract between the developer and the municipality that details the manner in which the conditions of approval will be fulfilled. It is aneillaiy to those conditions and is only enforceable to the extent that the conditions on which it is based are enforceable. Moreover, conditions of approval are not immutable; when the proportional effect of the public need generated by a project is materially changed by virtue of a significant reduction in the scope of the proposed development, the developer is entitled to an opportunity to demonstrate before the planning board that a recalculation of its contribution is warranted. The fact that the developer has entered into a developer’s agreement is of no consequence to that entitlement.

I

The facts of this case unfold over several decades with multiple characters playing various roles. The principal property is a 540-acre site located in Burlington County: 499.25 acres are in Moorestown Township and 31.06 acres are in Mount Laurel Township. In 1987, the Moorestown Foursome Partnership (Foursome) owned the property and intended to build a multiple-use development named Laurel Creek. Foursome envisioned Laurel Creek as a commercial, residential and retail destination, with 1.2 million square feet of office space, 47,000 square feet of retail space, 460 residential units, and an 18-hole golf course with a 25,000-30,000 square-foot country club. The largest portion of the development *231 was to be located in Moorestown Township, with only the country club and retail property located in Mount Laurel Township.

One of the general partners of Foursome was Thomas R. Whitesell. In addition to his equity interest in Foursome, White-sell was also a general partner in TRW Land, L.P. (TRW). TRW bought property adjacent to the Foursome site with the intention of building a 500,000 square-foot office park to be known as Laurel Creek Corporate Center (the Corporate Center). That property is exclusively located in Mount Laurel Township.

In the late 1980s, Foursome and TRW sought various zoning variances and waivers from Moorestown Township, Mount Laurel Township, and Burlington County for the development of their parcels. Interstate 295 provided an exit ramp near the properties. The surrounding area was essentially rural and undeveloped, and the roads bordering the properties were all primarily two-lane minor arteries. Thus, the proposed developments raised obvious concerns regarding increased traffic. Of particular concern were Centerton Road and Creek Road, which intersect in Mount Laurel near the 1-295 interchange.

Although it is not clear whether Foursome and TRW considered Laurel Creek and the Corporate Center a common concept plan, the local governing bodies handled both developments as one overall planning concern. To address the potential traffic problems generated by the proposed developments, two traffic engineering studies were produced. The reports are highly detailed and resist easy summary. However, two conclusions are clear: the Centerton Road/Creek Road intersection would be unable to accommodate the projected increased traffic to be generated by the combined Foursome and TRW projects at completion, and Centerton Road would have to be realigned to intersect with Creek Road further north in order to decrease congestion. The reports offered further suggestions, such as road-widening, physical barriers, and signalizing. Those recommendations were predominantly based on increased traffic patterns in peak hours due to the various types of forecasted development.

*232 In response to the reports, the local planning authorities conditioned their preliminary approvals on the developers’ willingness to make the requisite improvements. On September 8, 1988, the Mount Laurel Planning Board granted Foursome conditional preliminary subdivision approval for the portions of Laurel Creek located in its municipality, premised on the relocation of the intersection: “[U]ntil the intersection of Centerton and Creek Road is relocated, no building permit shall be issued which will permit more than 18% build out of the project.” Although the conditional approval was for Laurel Creek, the 18% trigger accounted for the traffic that would result from TRW’s development of the Corporate Center as well, as evidenced by the Board’s requirement that Foursome submit a letter setting forth the amount of build out that Foursome and TRW would each produce prior to the roadway development. In a letter dated September 23, 1988, Foursome notified the Board that, along with TRW, it agreed to “construct the improvements depicted on the Concept Plan/Centerton Road Realignment.” That letter was followed by a joint letter signed by Foursome and TRW, dated March 21, 1989, wherein both developers acknowledged their commitments and outlined the amount each developer would individually construct to reach the 18% trigger.

On November 3,1988, the Moorestown Planning Board granted Foursome conditional preliminary major subdivision approval for the Moorestown portion of Laurel Creek. Again, treating the projects as a single unit, the Board resolution stated that Foursome, “together with [TRW], shall be responsible for all of the improvements to the intersection of the relocated Centerton Road and Creek Road.”

The Burlington County Planning Board likewise required the roadway improvements. In a letter to the Burlington County Engineer’s Officer dated October 24, 1988, Foursome agreed that it, along with TRW, would be responsible for certain off-tract improvements.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mary Reinhold Brown v. HSBC
D. New Jersey, 2025
Brainbuilders, LLC v. Oscar Garden State Insurance Corporation
New Jersey Superior Court App Division, 2025
Grace C. Chen v. Ubs Business Solutions US LLC
New Jersey Superior Court App Division, 2025
REINHOLD BROWN v. HSBC
D. New Jersey, 2025
Tequesta Ecd, LLC v. Steven Enders
New Jersey Superior Court App Division, 2025
CHEN v. WANG
D. New Jersey, 2024

Cite This Page — Counsel Stack

Bluebook (online)
944 A.2d 1, 194 N.J. 223, 2008 N.J. LEXIS 310, Counsel Stack Legal Research, https://law.counselstack.com/opinion/toll-bros-inc-v-bd-of-chosen-freeholders-cty-of-burlington-nj-2008.