Tocci Building Corporation v. Trane U.S. Inc. a/k/a Trane Company

CourtDistrict Court, W.D. Wisconsin
DecidedNovember 14, 2025
Docket3:23-cv-00110
StatusUnknown

This text of Tocci Building Corporation v. Trane U.S. Inc. a/k/a Trane Company (Tocci Building Corporation v. Trane U.S. Inc. a/k/a Trane Company) is published on Counsel Stack Legal Research, covering District Court, W.D. Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tocci Building Corporation v. Trane U.S. Inc. a/k/a Trane Company, (W.D. Wis. 2025).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF WISCONSIN

TOCCI BUILDING CORPORATION,

Plaintiff, OPINION and ORDER v.

23-cv-110-jdp TRANE U.S. INC. a/k/a TRANE COMPANY,

Defendant.

Plaintiff Tocci Building Corporation and defendant Trane U.S. Inc. were both involved in the construction of a new hotel owned by Connell Hospitality LLC. Tocci was the general contractor; Trane was a subcontractor that was hired to design and manufacture the hotel’s HVAC system. Tocci and Trane did not deal with each other directly. Rather, Tocci paid another subcontractor, Quality Construction Heating and Air, Inc., which was supposed to pay Trane. But Quality Construction did not pay Trane, leading Trane to file a lien against the construction project. That led to trouble for Tocci. Tocci says that Trane harmed Tocci in two main ways. First, Tocci says that it only continued to pay Quality Construction because Trane represented that it was receiving payments and waived its lien rights. Second, Tocci says that Trane agreed to allow Tocci to purchase the HVAC equipment directly from Trane after Tocci learned that Quality Construction was not making payments, but Trane then reneged on that agreement by negotiating directly with Connell while also making misrepresentations to Connell about Tocci. This, Tocci says, led to Connell terminating its contract with Tocci. Tocci asserts claims against Trane for tortious interference with a contract, breach of implied contract, promissory estoppel, and indemnity. Trane moves to dismiss each of Tocci’s claims for multiple reasons, including that they are untimely, fail to state a claim, and are barred by an arbitration proceeding between Tocci and Connell. The court agrees with Trane that the tortious interference and implied contract claims are untimely and that Tocci has not stated a claim for indemnity. The case will proceed

on the promissory estoppel claim.

ALLEGATIONS OF FACT The following allegations are taken from the complaint, attached documents, and supplemental allegations in Tocci’s brief. The court accepts the allegations as true for the purpose of Trane’s motion to dismiss. In 2015, Connell Hospitality LLC hired Tocci to serve as the general contractor for the construction of a hotel in Berkely Heights, New Jersey. Tocci hired Quality Construction Heating and Air, Inc. as the subcontractor for the HVAC systems. Quality Construction hired

Trane “to design, fabricate, furnish, and test the HVAC equipment,” including the chillers. Dkt. 1, ¶ 8. Trane was supposed to deliver the chillers in August 2016, but Trane had not yet delivered the chillers by early February 2017. At that time, Trane told Tocci that Quality Construction had not made the downpayment for the chillers, and Trane would not make and deliver the chillers until it received the down payment. “Tocci then requested, and Trane agreed, that Tocci could acquire the Chillers and remaining equipment needed for the Project directly from Trane.” Id. ¶ 28.

On February 21, Trane filed a construction lien against the hotel project, alleging that it was owed $469,667.15. The following week, Connell issued a notice of termination to Tocci. The notice included allegations based on statements from Trane that Tocci had overbilled for Trane’s work and that Tocci had failed to contact Trane about purchasing the chillers. In May 2017, Tocci initiated arbitration proceedings against Connell. Other contractors were part of that arbitration, but Trane was not one of them. (The parties do not say why

Trane was excluded.) In 2023, while the arbitration was pending, Tocci filed this lawsuit against Trane. Shortly thereafter, the court stayed the case at the parties’ request pending a decision in the arbitration. Earlier this year, the arbitration panel found that Connell had wrongfully terminated its contract with Tocci, awarding Tocci more than $11 million in damages and more than $2 million in attorney fees. This court then lifted the stay, and Trane moved for judgment on the pleadings. Tocci is incorporated in Massachusetts, and its principal place of business is also in

Massachusetts. Trane is incorporated in Delaware, and its principal place of business is in North Carolina.1 Tocci seeks more than $1 million in damages, so it is reasonable to infer that more than $75,000 is in controversy.

1 Trane’s state of incorporation is not identified in the complaint, Trane’s answer, or Trane’s corporate disclosure form. However, other cases state that Trane is incorporated in Delaware, see, e.g., Montgomery Bank, N.A. v. Alico Rd. Bus. Park, LP, No. 2:13-CV-802-FTM-29, 2013 WL 6231363, at *2 (M.D. Fla. Dec. 2, 2013), and that is confirmed by the website for the Delaware Secretary of State, see https://icis.corp.delaware.gov/ecorp/entitysearch/NameSearch. aspx. Neither party is incorporated in Wisconsin, neither party is headquartered here, and the hotel project is in New Jersey, raising the question of why the lawsuit was filed here. The parties do not answer this question directly, but Tocci says in its brief that Trane’s “administrative offices were based in Wisconsin, and its administrative processes for issuing invoices and lien waivers were undertaken in Wisconsin.” Dkt. 28, at 38. Regardless, personal jurisdiction and venue are waivable issues. See York Group, Inc. v. Wuxi Taihu Tractor Co., Ltd., 632 F.3d 399, 403 (7th Cir. 2011); Auto. Mechanics Local 701 Welfare & Pension Funds v. Vanguard Car Rental USA, Inc., 502 F.3d 740, 746 (7th Cir. 2007). Trane does not seek dismissal or transfer for lack of jurisdiction or improper venue, so the court does not consider those issues. The court will discuss additional allegations as they become relevant to the analysis.

ANALYSIS Tocci asserts four claims against Trane: (1) tortious interference with Tocci’s contract with Connell; (2) breach of an implied contract to sell the HVAC equipment directly to Tocci;

(3) promissory estoppel based on a promise not to file a lien; and (4) indemnity for damages caused by Trane’s construction lien. Trane seeks dismissal of all these claims, contending that all of them are untimely, Tocci has not stated a claim for some of the claims, and the arbitration proceeding bars the tortious interference claim. Trane also contends that issue preclusion bars Tocci “from seeking the same damages sought, litigated, and considered by the arbitration panel.” Dkt. 27, at 57.2 To state a claim, the plaintiff must provide fair notice of its claim and “plead a plausible claim for relief,” Balle v. Kennedy, 73 F.4th 545, 557 (7th Cir. 2023), which means that the

allegations in the complaint raise a right to relief above the speculative level, McCray v. Wilkie, 966 F.3d 616, 620 (7th Cir. 2020). Stated another way, the plaintiff must “present a story that holds together” under the relevant law. Taylor v. Salvation Army National Corp., 110 F.4th 1017, 1028 (7th Cir. 2024). The court may not dismiss a claim based on an affirmative defense such as the statute of limitations or issue preclusion unless it is clear from the face of the complaint that the defense applies. See Hyson USA, Inc. v. Hyson 2U, Ltd., 821 F.3d 935, 939 (7th Cir. 2016).

2 Citations to documents filed on the docket reflect the page numbers as they appear on the headers in the court’s electronic case file, not the page numbers on the documents themselves. A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

York Group, Inc. v. Wuxi Taihu Tractor Co., Ltd.
632 F.3d 399 (Seventh Circuit, 2011)
Brian K. Thomson v. Odie Washington
362 F.3d 969 (Seventh Circuit, 2004)
Integrity Material v. Deluxe Corp.
722 A.2d 552 (New Jersey Superior Court App Division, 1999)
BD. OF TRUSTEES OF UNION COLLEGE v. Kennerly, Slomanson & Smith
400 A.2d 850 (New Jersey Superior Court App Division, 1979)
Leonardis v. Burns International Security Services, Inc.
808 F. Supp. 1165 (D. New Jersey, 1992)
DiIorio v. Structural Stone & Brick
845 A.2d 658 (New Jersey Superior Court App Division, 2004)
Toll Bros., Inc. v. BD. OF CHOSEN FREEHOLDERS, CTY. OF BURLINGTON
944 A.2d 1 (Supreme Court of New Jersey, 2008)
R.J. Longo Construction Co. v. Transit America, Inc.
921 F. Supp. 1295 (D. New Jersey, 1996)
Boldt v. State
305 N.W.2d 133 (Wisconsin Supreme Court, 1981)
Meyers v. Henderson Construction Co.
370 A.2d 547 (New Jersey Superior Court App Division, 1977)
Docteroff v. Barra Corp.
659 A.2d 948 (New Jersey Superior Court App Division, 1995)
Hyson USA, Inc. v. Hyson 2U, Ltd.
821 F.3d 935 (Seventh Circuit, 2016)
Anne O' Boyle v. Real Time Resolutions, Inc.
910 F.3d 338 (Seventh Circuit, 2018)
Scott McCray v. Robert Wilkie
966 F.3d 616 (Seventh Circuit, 2020)
Kopin v. Orange Products, Inc.
688 A.2d 130 (New Jersey Superior Court App Division, 1997)
Quality Guaranteed Roofing, Inc. v. Hoffmann-La Roche, Inc.
694 A.2d 1077 (New Jersey Superior Court App Division, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
Tocci Building Corporation v. Trane U.S. Inc. a/k/a Trane Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tocci-building-corporation-v-trane-us-inc-aka-trane-company-wiwd-2025.