Tocci Building Corp. v. Zurich American Insurance

659 F. Supp. 2d 251, 2009 U.S. Dist. LEXIS 93976
CourtDistrict Court, D. Massachusetts
DecidedSeptember 25, 2009
DocketCivil Action 07-10597-NMG
StatusPublished
Cited by6 cases

This text of 659 F. Supp. 2d 251 (Tocci Building Corp. v. Zurich American Insurance) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tocci Building Corp. v. Zurich American Insurance, 659 F. Supp. 2d 251, 2009 U.S. Dist. LEXIS 93976 (D. Mass. 2009).

Opinion

NATHANIEL M. GORTON, District Judge.

ORDER ON REPORT AND RECOMMENDATIONS — accepted and adopted. *253 Action on motion: motion for summary judgment allowed.

REPORT AND RECOMMENDATION ON DEFENDANT’S MOTION FOR SUMMARY JUDGMENT

DEIN, United States Magistrate Judge.

September 9, 2009

I. INTRODUCTION

Plaintiffs, Tocci Building Corporation (“Tocci”) and Candlewood Hotel Company, Inc. (“Candlewood”), have brought this action against Zurich American Insurance Company (“Zurich”) seeking insurance payments for work done on a retaining wall and related business interruption losses. Zurich has denied coverage. This matter is presently before the court on Zurich’s Motion for Summary Judgment pursuant to which Zurich is seeking judgment in its favor on all counts of the complaint. As detailed more fully herein, the undisputed facts establish that the work on the retaining wall was not done because of “direct physical loss or damage” to the wall. Consequently, this court finds that there was no insurance coverage under Zurich’s policy and recommends to the District Judge to whom this case was assigned that Zurich’s Motion for Summary Judgment (Docket No. 46) be ALLOWED.

II. STATEMENT OF FACTS 1

In ruling on a motion for summary judgment, the court must view the record in the light most favorable to the non-moving party and indulge all reasonable inferences in that party’s favor. See O’Connor v. Steeves, 994 F.2d 905, 907 (1st Cir.1993). Applying these principles to the instant case, the relevant facts are as follows:

Damage to the Retaining Wall

This action involves construction work done to a retaining wall at a hotel construction site in Burlington, Massachusetts. Tocci was the general contractor on the job, and Candlewood owned the site. Zurich issued a builders risk insurance policy to Candlewood that covered the construction of the hotel during the relevant period. (SF ¶ 1).

The hotel construction site incorporated an extensive retaining wall separating elevated portions of the site from the Middle-sex Turnpike, among other things. (SF ¶ 2). The retaining wall at issue was multi-tiered and over 1200 feet in length. (Id.). It was constructed from loosely laid large boulders and fill from the construction site. (Id.).

There was a substantial rainstorm in Burlington on the evening of June 6, 2000 which caused damage to the retaining wall. 2 (SF ¶ 4; Resp. ¶ 4). As Tocci has admitted:

The direct physical damage to the Retaining Wall that occurred on June 6, 2000 was limited to less than 100 feet of the 1200 foot wall. As characterized by Tocci’s engineers ... *254 An approximate 35-foot long portion of the upper wall slid and toppled into the lower wall. The overall affected length of the upper wall where stones had visually moved is about 65 feet long. Approximately 35 feet of the lower wall was also affected.
The remainder of the 1200 foot long wall suffered no physical loss or damage on June 6, 2000 or thereafter.

(SF ¶ 6; Resp. ¶ 6).

On June 9, 2000, the Town of Burlington issued a stop work order and declared the wall unsafe as a result of the damage incurred in the storm. (Zurich Ex. G). In early August 2000, the Town gave Tocci permission to repair the 100' section of the wall that had been damaged on June 6, 2000. (SF ¶ 9). Those repairs took less than one week and were completed by August 14, 2000. (Id.). Meanwhile, however, upon inspection, the Town concluded that the retaining wall had not been built in accordance with the approved plans, and notified Tocci by letter dated August 15, 2000 that the wall needed to be demolished and reconstructed. (Zurich Ex. D). Tocci disputed this conclusion, 3 and argued to the Town that the demolition was unnecessary, expensive and time-consuming. (Tocci Ex. Q). Tocci’s engineering firm, Jaworski Geotech, Inc., who designed the wall and supervised its construction, insisted that it was built correctly. (See Tocci Ex. C at 30-31, 85).

Tocci and the Town engaged in negotiations about how to proceed. In November 2000, the Town agreed to permit the hotel to open if Tocci would grout the entire wall. (Tocci Ex. Q). According to Tocci, plaintiffs only agreed to this plan in order to prevent further delays; it was not structurally necessary. (Id.). The grouting of the entire wall was completed on November 11, 2000. (SF ¶ 13; Resp. ¶ 13). The hotel, which was originally scheduled to open on July 31, 2000, eventually opened on November 17, 2000. (See id.; Opp. (Docket No. 52) at 3). In the instant litigation, the plaintiffs are seeking coverage for the grouting of the wall and the delay in the hotel opening.

Conway Construction Litigation

In May 2001, G. Conway, Inc. (“Conway”), the construction sub-contractor who built the retaining wall, sued Tocci to recover amounts allegedly owed under its contract. (Tocci Ex. H) (the “Conway litigation”). Conway contended that the damage to the wall was not due to construction defects. Tocci and Candlewood counterclaimed against Conway, and brought claims against other parties, including Tocci’s engineers, alleging, inter alia, that there had been faulty workmanship in the construction of the retaining wall. (See SF ¶ 20; Resp. ¶ 20; Tocci Ex. I). See note 3, supra. There was no adjudication of this issue on the merits, and the case was settled and dismissed, with prejudice, on December 11, 2006. (SF ¶ 20; Trombetta Aff. ¶ 19).

The Commonwealth Insurance Litigation

Candlewood also had insurance at the Burlington property with Commonwealth Insurance Company (“Commonwealth”), and submitted a claim following the storm. Commonwealth agreed to pay for the repair of the damaged portion of the wall, cleanup and public safety expenses, and *255 two weeks of business interruption. It declined coverage for the grouting of the rest of the wall, and for the balance of the delay in opening the hotel pending completion of the grouting. Thereafter, on May 30, 2002, Tocci and Candlewood brought suit against Commonwealth in the Massachusetts Superior Court, claiming “that Commonwealth failed to comply with the terms of the policy by (1) failing to cover the costs incurred in bringing the retaining wall into compliance with the Town’s building code, and (2) compensating the plaintiffs for only two weeks of business interruption rather than the entire 110-day delay in opening the hotel.” Tocci Bldg. Corp. v. Commonwealth Ins. Co., 22 Mass. L. Rep. 522, 2007 WL 1830829, at *2, 2007 Mass.Super. LEXIS 181, at *4 (Mass.Super.Ct. Apr. 23, 2007) (Zurich Ex. A).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
659 F. Supp. 2d 251, 2009 U.S. Dist. LEXIS 93976, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tocci-building-corp-v-zurich-american-insurance-mad-2009.