Tobin v. Town Council

17 P.2d 666, 45 Wyo. 219, 84 A.L.R. 902, 1933 Wyo. LEXIS 5
CourtWyoming Supreme Court
DecidedJanuary 4, 1933
Docket1768, 1769
StatusPublished
Cited by37 cases

This text of 17 P.2d 666 (Tobin v. Town Council) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tobin v. Town Council, 17 P.2d 666, 45 Wyo. 219, 84 A.L.R. 902, 1933 Wyo. LEXIS 5 (Wyo. 1933).

Opinion

*224 Riner, Justice.

Tbes© two cases, before tbe court by separate direct appeals from a judgment of tbe District Court of Crook County, are based upon tbe same record, botb plaintiff and defendant in that court being dissatisfied with tbe result there reached and each asking for a review of tbe record. Tbe cases can accordingly be disposed of by one opinion. Tbe action which culminated in tbe judgment thus attacked was instituted below by T. J. Tobin, doing business under tbe firm name and style of T. J. Tobin Construction Company, as plaintiff, hereinafter generally so referred to, or as tbe “contractor,” against tbe Town Council of the Town of tbe City of Sundance, as defendant subsequently so mentioned, or as the “town.”

Summarized, plaintiff’s petition alleges a written contract between him and tbe town for tbe filling, grading, and graveling of certain of tbe latter’s streets, a copy of this agreement dated September 21, 1929, being attached to and made a part of tbe pleading. Performance of tbe work thus contracted for is averred in that plaintiff leveled and graded tbe town’s streets, placing thereon as directed, 1442 yards of dirt at tbe agreed price of 40 cents per yard and 2754.11 tons of gravel, crushed and prepared by tbe contractor, at tbe agreed price of $1.87 per ton. Tbe completion of tbe work by tbe plaintiff and its acceptance by tbe defendant is alleged to have occurred on January 23,1930 when, at a special meeting of tbe defendant’s town council, bis account was by it accepted and be was paid tbe sum of $2740.71 thereon, leaving a balance of $2878.27 due him, after deducting a charge of $118.00 for water furnished by tbe town. The rejection on November 3, 1930, by tbe defendant, of a verified claim made by tbe plaintiff for tbe balance aforesaid, and a denial by it of all liability for tbe work and materials furnished, is pleaded. Tbe petition also charges that tbe actual and reasonable cost of tbe labor and material thus furnished is the sum *225 $2878.27 and that tbe defendant has been unjustly enriched thereby at the expense of plaintiff in said sum, judgment for which, with costs, is prayed.

The written contract aforesaid, after detailing the streets and the portions thereof to be improved, the depth of the gravel to be laid, the prices for dirt and gravel as set out in plaintiff’s petition, and the supervision of the work by the defendant’s engineer, provided that the work should be paid for ‘ when the work is satisfactorily completed, one-half of the amount due the second party shall be paid in cash, and the said party of the second part shall and does hereby agree to accept the remaining one-half in warrants of the said party of the first part, which said warrants shall be payable not more than one year from date of issue. ’ ’

This petition was filed November 22, 1930. March 13, 1931, the town filed its answer in substance asserting that the contract relied upon by the plaintiff was void and without force (1) for failure on the part of the town to obey the provisions of Sec. 1774, Wyo. Comp. St. 1920, in that the expense 'under said agreement exceeded the sum of $200 and the contract was not let to the lowest bidder after advertisement as required by law and no bond with proper sureties was demanded of plaintiff as the law directs; (2) for failure to comply with Sections 1756 and 1757, Wyo. Comp. St. 1920, in that no valid appropriation had been made by the defendant for the improvements attempted to be made under the terms of said contract and they had not been ordered by a four-fifths vote of the defendant’s town council. The answer also denied that plaintiff had completed the work called for by the contract, denied that the town approved, ratified and accepted the work done inasmuch as it was, as plaintiff knew, without legal power so to do and disclaimed all indebtedness to the plaintiff. The answer further set forth a counterclaim alleging that the town had paid plaintiff *226 without authority of. law and illegally the sum of $2,740.71, which he took and received with knowledge of that fact, and that this amount is now due from him to the defendant. The recovery of this sum with interest was prayed as well as the dismissal of plaintiff’s action.

Plaintiff’s reply denied each and every allegation in the answer which was not an admission of the allegations of plaintiff’s petition. It also pleaded in detail several matters which, it is averred, relieved the town of compliance with the statutes referred to in defendant’s answer; viz., the inability of the defendant to procure anyone to do the work desired by the town prior to the time of making the contract; the low prices for the work fixed by the contract, said prices representing its actual cost; the existence of an emergency on account of the streets of the town being boggy, deeply rutted and impassable, through excessive rains. The reply further alleged that the work contracted for and performed by plaintiff was on the principal streets of the town, which is a small incorporated village of about 300 inhabitants, and that each of said inhabitants knew of the work being done and the terms of the contract; that no objection was made by any one of them until long after the completion of said work and payment of one-half of the cost to the plaintiff and that the defendant is estopped to deny liability for the work done and material furnished.

Replying to defendant’s counterclaim, in addition to reiterating the preceding averments of the reply, it is averred that after the completion of said work by the plaintiff, its acceptance by the town and a part payment on account thereof, as aforesaid, the defendant promised to pay the plaintiff the balance within a short time thereafter, which promise was repudiated by a new town council elected in May 1930; that, although repudiating the obligations of the town, the latter has accepted the benefits of the work done and materials furnished by plaintiff and *227 has not offered to return same or make compensation therefor and is now estopped to recover back the payment made or to deny liability for the balance claimed by plaintiff to be due. Other matters are pleaded in the reply which will be referred to hereinafter only in ease, in our opinion, they affect the disposition of the contentions here urged by the respective parties.

The ease was tried to the court without a jury, resulting in findings being made “that the plaintiff should take nothing by his petition and that the same should be dismissed at plaintiff’s cost and that the defendant should take nothing by its counterclaim and that the same should be dismissed.” A judgment was entered accordingly, the costs of the action being taxed against the plaintiff.

In order to fully understand the pleadings and contentions of the parties, it is proper at this point to refer to certain sections of the state law dealing with the letting of contracts for public improvements by town officials and limiting the appropriations of town money and the expenditures thereof. So much only of the several sections will be quoted as is pertinent to the questions hereinafter discussed.

See. 1774, Wyo. Comp. St. 1920 (now Sec. 22-1447, Wyo. Rev. St. 1931) provides in part:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Aberdeen v. Rich
2003 SD 26 (South Dakota Supreme Court, 2003)
Bozied v. City of Brookings
2001 SD 150 (South Dakota Supreme Court, 2001)
Elview Construction Co. v. North Scott Community School District
373 N.W.2d 138 (Supreme Court of Iowa, 1985)
Opinion No. 75-288 (1975) Ag
Oklahoma Attorney General Reports, 1975
Bak v. Jones County
210 N.W.2d 65 (South Dakota Supreme Court, 1973)
Thompson v. L. J. Voldahl, Inc.
188 N.W.2d 377 (Supreme Court of Iowa, 1971)
Twitchell v. Bowman
440 P.2d 513 (Wyoming Supreme Court, 1968)
State Ex Rel. Callaway v. Axtell
393 P.2d 451 (New Mexico Supreme Court, 1964)
Town of Lovell v. Menhall
386 P.2d 109 (Wyoming Supreme Court, 1963)
State Ex Rel. Russell County v. Fourth National Bank
117 So. 2d 145 (Supreme Court of Alabama, 1959)
Town of Worland v. Odell & Johnson
329 P.2d 797 (Wyoming Supreme Court, 1958)
Bentzen v. H. N. Ranch, Inc.
320 P.2d 440 (Wyoming Supreme Court, 1958)
City of Sheridan v. Montana-Dakota Utilities Co.
157 F. Supp. 664 (D. Wyoming, 1958)
CAPITAL BRIDGE COMPANY v. County of Saunders
83 N.W.2d 18 (Nebraska Supreme Court, 1957)
Fonder v. City of South Sioux Falls
71 N.W.2d 618 (South Dakota Supreme Court, 1955)
Bethesda v. Mallonee
136 N.E.2d 457 (Belmont County Court of Common Pleas, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
17 P.2d 666, 45 Wyo. 219, 84 A.L.R. 902, 1933 Wyo. LEXIS 5, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tobin-v-town-council-wyo-1933.