Los Angeles Dredging Co. v. City of Long Beach

291 P. 839, 210 Cal. 348, 71 A.L.R. 161, 1930 Cal. LEXIS 394
CourtCalifornia Supreme Court
DecidedSeptember 29, 1930
DocketDocket No. L.A. 10532.
StatusPublished
Cited by80 cases

This text of 291 P. 839 (Los Angeles Dredging Co. v. City of Long Beach) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Los Angeles Dredging Co. v. City of Long Beach, 291 P. 839, 210 Cal. 348, 71 A.L.R. 161, 1930 Cal. LEXIS 394 (Cal. 1930).

Opinion

LANGDON, J.

This is an appeal from a judgment of the Superior Court of Los Angeles County, in favor of plaintiff, for money due under two contracts.

On February 18, 1924, the city manager of defendant published a notice inviting bids for the dredging of a certain channel in Long Beach harbor. Plaintiff corporation filed its bid for the work and on March 19, 1924, a contract was entered into between plaintiff and defendant for the dredging of the said channel in accordance with specifications set forth in the published notice and incorporated into the contract by reference. The contract provided, among other things, that the plaintiff should diligently prosecute the work and complete it on or before January 9, 1926; that a certain proportion of the work should be completed at the end of each month; that the plant of plaintiff should be of sufficient size to meet the requirements of the work, and should be kept at all times in condition for efficient work. It was also agreed that, the city engineer would permit the laying of a pipe-line on public streets and across public lands.

The present action is not concerned with this original contract, but with two oral contracts subsequently made by the city manager of defendant with plaintiff, and thereafter ratified by the city council of defendant. The circumstances giving rise to these contracts are hereinafter set forth.

Plaintiff commenced to perform and continued to do so in full compliance with the terms of its contract up to about July 21, 1925. At this time the bathing season of the city was at its height, and the depositing of dredged materials in the places and in the manner specified resulted in pollu *351 tian of the waters and interfered with the use of the beach for bathing purposes. Thereupon, on or about the said date of July 21, 1925, the city manager of defendant entered into an oral contract with plaintiff, whereby it was agreed that if plaintiff would cease its dredging operations at such times as directed, defendant would pay to plaintiff for the time lost by such cessation the sum of $30 per hour. It was stipulated, and the court found that it was necessary for plaintiff to maintain its plant ready for work during such cessation of operations; that the reasonable cost therefor, including wages, insurance and overhead, was the said sum of $30 per hour; and that it had been agreed between the city manager and plaintiff that the said sum of $30 was reasonable. Pursuant to this agreement plaintiff ceased its dredging operations at various times during the months of July and August, 1925, for a total of 380% hours.

The second contract upon which this action is brought had its origin as follows: In accordance with the provisions of the dredging contract, plaintiff had laid its pipe-lines along public streets and ways within the city in order to obtain the shortest route for transporting dredged materials from the place of operation to the place of disposal. The parties stipulated that at the time of the bid and original contract plaintiff relied upon the representations of defendant that the use of public streets and ways would be given. The findings of the court state that subsequently, “on or about the 1st day of April, 1925, the use of the public streets and ways within the City of Long Beach was refused plaintiff herein by defendant, by reason of the fact that the normal leakage and overflow from said pipe-lines would so hinder and obstruct the use of the public streets and ways for normal use as to be detrimental to the health and safety of those so using said public streets and ways, and that certain of the citizens of defendant threatened to enjoin the dredging operations of plaintiff and defendant; and that by reason of said refusal, and at the request of defendant, it was necessary for plaintiff and plaintiff was forced to obtain rights of way over other lands to transport dredged materials over and through greater lengths of pipe and distances than originally contemplated when its said bid was made and accepted.” At the time of the request to change the route the city manager *352 of defendant entered into another oral agreement with plaintiff to pay the additional cost of transporting the dredged materials over the more circuitous route at the rate of 1.5 cents per yard over and above the contract price. The court found that such sum was the reasonable additional cost to plaintiff of the said change of route.

During the months of April, May, June, July and August, 1925, plaintiff transported 373,439 yards of dredged materials over such increased distance.

The charter of the City of Long Beach contains the following provision relevant to the situation herein presented:

“See. 294. All contracts, except as otherwise provided in this charter, or by general law, for the city or any of the departments or public institutions thereof, must be made by the City Manager with the lowest responsible bidder, whose bid is in regular form, not less than five days nor more than twenty days after one publication of a notice calling for bids in the official newspaper of the city; said notice shall contain a brief description of the supplies or materials required and amount of the bonds required of the successful bidder, and state the hour and day on which said bids will be opened; except, that the City Council may, by a resolution adopted by the affirmative vote of five members of the City Council, authorize the City Manager to enter into a contract on behalf of the city, in writing or otherwise, without advertising for bids, for labor, material or supplies for actual emergency work.”'

On or about January 28, 1927, the city council of defendant passed a resolution ratifying and confirming on behalf of the city, the contract for cessation of dredging operations and the contract for the payment of the additional sum per yard for materials transported over the longer route. The resolution reads in part as follows:

“Section 1. That the several contracts hereinafter particularly described, entered into by the City Manager of the City of Long Beach, on behalf of the City of Long Beach, and acting as such official, and not otherwise, on the one hand, and the Los Angeles Dredging Company, a corporation, on the other hand, without advertising for bids, are hereby authorized, ratified and confirmed as and for the actual emergency work as hereinafter described at the price *353 thereof, and as and of the dates when each of said agreements was made.”

Section 4 of the resolution states that “it was impracticable to advertise for bids for such contracts as Los Angeles Dredging Company had already the contracts for said work; that it would be a useless and futile act to ask for bids on such contracts, as none except Los Angeles Dredging Company could or would bid thereon.”

The said resolution was passed by the affirmative vote of five members of the council.

Subsequently plaintiff presented its claim to defendant for the sums due under the contracts. The claim was not allowed. This action was thereupon commenced on May 28, 1927. The complaint contained thirty-four causes of action. The first count was for the agreed cost of cessation of dredging operations for the period of 380% hours, on the theory of a single agreement therefor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

County of Santa Clara v. Superior Court
California Supreme Court, 2023
Childhelp, Inc. v. City of L.A.
California Court of Appeal, 2023
Childhelp v. City of Los Angeles CA2/7
California Court of Appeal, 2023
Amelco Electric v. City of Thousand Oaks
38 P.3d 1120 (California Supreme Court, 2002)
Lewis C. Nelson & Sons, Inc. v. Clovis Unified Sch. Dist.
108 Cal. Rptr. 2d 715 (California Court of Appeal, 2001)
County of Orange v. Fuji Securities, Inc.
31 F. Supp. 2d 768 (C.D. California, 1998)
Domar Electric, Inc. v. City of Los Angeles
885 P.2d 934 (California Supreme Court, 1994)
Trimont Land Co. v. Truckee Sanitary District
145 Cal. App. 3d 330 (California Court of Appeal, 1983)
Estate of Stober
108 Cal. App. 3d 591 (California Court of Appeal, 1980)
Graydon v. Pasadena Redevelopment Agency
104 Cal. App. 3d 631 (California Court of Appeal, 1980)
City of Kenai v. Filler
566 P.2d 670 (Alaska Supreme Court, 1977)
Meakin v. Steveland, Inc.
68 Cal. App. 3d 490 (California Court of Appeal, 1977)
Malibu West Swimming Club v. Flournoy
60 Cal. App. 3d 161 (California Court of Appeal, 1976)
Advance Medical Diagnostic Laboratories v. County of Los Angeles
58 Cal. App. 3d 263 (California Court of Appeal, 1976)
Foster v. Day & Zimmermann, Inc.
502 F.2d 867 (Eighth Circuit, 1974)
County of Riverside v. Whitlock
22 Cal. App. 3d 863 (California Court of Appeal, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
291 P. 839, 210 Cal. 348, 71 A.L.R. 161, 1930 Cal. LEXIS 394, Counsel Stack Legal Research, https://law.counselstack.com/opinion/los-angeles-dredging-co-v-city-of-long-beach-cal-1930.