OPALA, Justice.
The case presents the following questions: (1) Should Tinker Investment & Mortgage Corporation’s [Timcorp] appeal in Cause No. 78,844 be dismissed because it is prosecuted from an
unappealable
summary judgment? (2) Can Timcorp secure in its
second
appeal [Cause No. 80,396] the relief sought by its
first
appeal [Cause No. 78,844] against Midwest City [the City], even though its attempt to secure this relief
comes here more than SO days after the date of the judgment from which the second appeal is prosecuted?
and (3) Did the district court err in rejecting Timcorp’s objection to Willow Wind/Beaver’s
suit, based on the latter party’s failure
to exhaust the City’s administrative remedies? We answer the
first
question in the affirmative and the
second two
in the negative. Timcorp’s quest for corrective relief from the trial court’s summary judgment to the City is dismissed. Timcorp’s attempt to transform a
nominal party
[Midwest City] into a
targeted party
appellee
in its second appeal offends the provisions of 12 O.S.1991 § 990A. Timcorp’s quest to enlarge its assignment of errors in the second appeal is unauthorized by Rule 1.17, Rules of Appellate Procedure in Civil Cases. Although allowing amendment of the petition in error
before
the brief in chief is filed, the cited rule does not sanction the
substitution or addition
of parties appellee or appellant
more than thirty days after the date of the judgment from which the appeal is prosecuted.
Because the City’s administrative procedure for enforcement of its municipal ordinances was concededly ineffective, the trial court correctly ruled that the exhaustion-of-remedy doctrine did not bar it from reaching the claims of Willow Wind/Beaver or from construing the
pay-back
ordinances.
I
ANATOMY OF LITIGATION
The City’s ordinances required subdivision developers to install water and sewer lines and to dedicate them to the City as a condition for municipal plat approval.
In 1982 new ordinances
were passed to encourage
private parties to build
trunk sewer lines
to service previously undeveloped lands. This local legislation, commonly referred to as
pay-back ordinances,
called for (1) a developer to pay the initial construction costs for the
trunk sewer lines
and (2) the City to charge
later developers
a one-time fee to connect their subdivisions to these lines.
Ninety
percent of the collected “tie-on” fee was to be paid to the developer who had constructed the original trunk line and
ten
percent was to be retained by the City to cover the costs of administering the
pay-back plan.
The payback period was limited to “no more than fifteen years”.
The City’s efforts to enforce the ordinances were not fully effective.
Willow Wind/Beaver,
a developer who had installed a sanitary sewer
trunk line, sued
for a declaration of its rights under the ordinances and, alternatively, for a writ of mandamus to compel their enforcement. Shortly after this suit was filed in 1986, the City repealed the
payback
ordinances,
deeming them unconstitutional.
Another developer, Timeorp, brought a
separate
action against the City to compel enforcement of the
pay-back
ordinances. Its claim was rested upon theories of
inverse condemnation
and
unjust enrichment.
Timcorp sought a declaration that a line it had built was a
trunk line
within the meaning of the ordinances and that reimbursement from the City for the line’s construction costs was hence its due. According to Timeorp, had it not been for the pay-back ordinances, it would
not
have planned a subdivision which called for water and sewer connections. Rather, it would have opted for a development in which septic tanks and water wells would have been used.
The two cases were consolidated below for disposition.
The trial judge
initially
ruled the pay-back ordinances unconstitutional and gave summary judgment to the City.
The Court of Appeals reversed that decision.
This court vacated the appellate court’s opinion and reached for resolution,
inter alia,
the question whether the
pay-back
ordinances were valid when tested against the provisions of Art. 10, §§ 14, 17, 26 and 27, Okl. Const.
Pronouncing the ordinances
constitutional,
this court reversed and remanded the case for trial. Following the remand, summary judgment went to the City
against
Timcorp.
When giving summary judgment to
the City, the trial court denied Timcorp’s motion for summary resolution of other issues, noting the presence of unresolved claims. Timcorp appealed for review of the summary judgment [the first appeal].
The remaining issues were later reached for trial, and judgment [the latter resolving
all
the issues and claims in the consolidated action] was entered for Willow Wind/Beaver.
Tim-corp appealed
this terminal disposition by judgment on the October 9, 1992 [the second appeal] and amended its petition in error on November 12, 1992.
We hold today that (1) Timcorp’s
first
appeal [Cause No. 78,844] is dismissible because it seeks review of an
unappealable summary judgment;
(2) Timcorp’s quest for relief against Isaacs Construction Co., Inc. [Isaacs] is denied because Timcorp faded to serve Isaacs or its counsel of record either with a copy of the petition in error or with any other notice; (3) the terms of 12 O.S. 1991 § 990A
and Rule 1.17,
Rules of Appellate Procedure in Civil Cases, prohibit this court from granting Timcorp leave to change,
after the maximum time for the second appeal has expired,
the City’s status in the later appeal from that of a
nominal party appellee
[against whom
no
relief was sought] to that of a
targeted party appellee;
Free access — add to your briefcase to read the full text and ask questions with AI
OPALA, Justice.
The case presents the following questions: (1) Should Tinker Investment & Mortgage Corporation’s [Timcorp] appeal in Cause No. 78,844 be dismissed because it is prosecuted from an
unappealable
summary judgment? (2) Can Timcorp secure in its
second
appeal [Cause No. 80,396] the relief sought by its
first
appeal [Cause No. 78,844] against Midwest City [the City], even though its attempt to secure this relief
comes here more than SO days after the date of the judgment from which the second appeal is prosecuted?
and (3) Did the district court err in rejecting Timcorp’s objection to Willow Wind/Beaver’s
suit, based on the latter party’s failure
to exhaust the City’s administrative remedies? We answer the
first
question in the affirmative and the
second two
in the negative. Timcorp’s quest for corrective relief from the trial court’s summary judgment to the City is dismissed. Timcorp’s attempt to transform a
nominal party
[Midwest City] into a
targeted party
appellee
in its second appeal offends the provisions of 12 O.S.1991 § 990A. Timcorp’s quest to enlarge its assignment of errors in the second appeal is unauthorized by Rule 1.17, Rules of Appellate Procedure in Civil Cases. Although allowing amendment of the petition in error
before
the brief in chief is filed, the cited rule does not sanction the
substitution or addition
of parties appellee or appellant
more than thirty days after the date of the judgment from which the appeal is prosecuted.
Because the City’s administrative procedure for enforcement of its municipal ordinances was concededly ineffective, the trial court correctly ruled that the exhaustion-of-remedy doctrine did not bar it from reaching the claims of Willow Wind/Beaver or from construing the
pay-back
ordinances.
I
ANATOMY OF LITIGATION
The City’s ordinances required subdivision developers to install water and sewer lines and to dedicate them to the City as a condition for municipal plat approval.
In 1982 new ordinances
were passed to encourage
private parties to build
trunk sewer lines
to service previously undeveloped lands. This local legislation, commonly referred to as
pay-back ordinances,
called for (1) a developer to pay the initial construction costs for the
trunk sewer lines
and (2) the City to charge
later developers
a one-time fee to connect their subdivisions to these lines.
Ninety
percent of the collected “tie-on” fee was to be paid to the developer who had constructed the original trunk line and
ten
percent was to be retained by the City to cover the costs of administering the
pay-back plan.
The payback period was limited to “no more than fifteen years”.
The City’s efforts to enforce the ordinances were not fully effective.
Willow Wind/Beaver,
a developer who had installed a sanitary sewer
trunk line, sued
for a declaration of its rights under the ordinances and, alternatively, for a writ of mandamus to compel their enforcement. Shortly after this suit was filed in 1986, the City repealed the
payback
ordinances,
deeming them unconstitutional.
Another developer, Timeorp, brought a
separate
action against the City to compel enforcement of the
pay-back
ordinances. Its claim was rested upon theories of
inverse condemnation
and
unjust enrichment.
Timcorp sought a declaration that a line it had built was a
trunk line
within the meaning of the ordinances and that reimbursement from the City for the line’s construction costs was hence its due. According to Timeorp, had it not been for the pay-back ordinances, it would
not
have planned a subdivision which called for water and sewer connections. Rather, it would have opted for a development in which septic tanks and water wells would have been used.
The two cases were consolidated below for disposition.
The trial judge
initially
ruled the pay-back ordinances unconstitutional and gave summary judgment to the City.
The Court of Appeals reversed that decision.
This court vacated the appellate court’s opinion and reached for resolution,
inter alia,
the question whether the
pay-back
ordinances were valid when tested against the provisions of Art. 10, §§ 14, 17, 26 and 27, Okl. Const.
Pronouncing the ordinances
constitutional,
this court reversed and remanded the case for trial. Following the remand, summary judgment went to the City
against
Timcorp.
When giving summary judgment to
the City, the trial court denied Timcorp’s motion for summary resolution of other issues, noting the presence of unresolved claims. Timcorp appealed for review of the summary judgment [the first appeal].
The remaining issues were later reached for trial, and judgment [the latter resolving
all
the issues and claims in the consolidated action] was entered for Willow Wind/Beaver.
Tim-corp appealed
this terminal disposition by judgment on the October 9, 1992 [the second appeal] and amended its petition in error on November 12, 1992.
We hold today that (1) Timcorp’s
first
appeal [Cause No. 78,844] is dismissible because it seeks review of an
unappealable summary judgment;
(2) Timcorp’s quest for relief against Isaacs Construction Co., Inc. [Isaacs] is denied because Timcorp faded to serve Isaacs or its counsel of record either with a copy of the petition in error or with any other notice; (3) the terms of 12 O.S. 1991 § 990A
and Rule 1.17,
Rules of Appellate Procedure in Civil Cases, prohibit this court from granting Timcorp leave to change,
after the maximum time for the second appeal has expired,
the City’s status in the later appeal from that of a
nominal party appellee
[against whom
no
relief was sought] to that of a
targeted party appellee;
and (4) because the administrative remedy made available by the municipal law does not afford Willow Wind/Beaver adequate relief, the
exhaustion-of-remedies doctrine
did not require this action’s abatement by the district court.
II
THE PROVISIONS OF 12 O.S.1991 § 1006 REQUIRE TIMCORP’S FIRST APPEAL TO BE DISMISSED BECAUSE IT IS PROSECUTED FROM AN UNAPPEALABLE SUMMARY JUDGMENT.
Although the district court gave to the City summary judgment against Tim-corp, that
nisi prius
disposition did not
then
rise to an
appealable event.
This is so because the decision which Timcorp tendered for review [in its
first
appeal] was not
advanced
for an immediate appeal under the
terms of 12 O.S.1991 § 1006.
In a multiparty, multi-claim action a decision disposing of
less than all the parties and all the claims
is
unappealable
unless the § 1006 criteria
are met. The provisions of § 1006 [then in effect] required that a
final decision
on
one but not on all claims
can be advanced by the trial judge for immediate appeal
only
by an
express determination,
included in the journal entry, that there is no reason for delay, coupled with an
express direction
for the filing of
“judgment".
Here the requisite expressions are absent.
The law views the earlier summary judgment, here under scrutiny, as
unappealable sans certification.
That disposition was not terminal in this multi-party, multi-claims case.
It remained subject to change before the court’s decision resolved
all
the other claims.
Because the summary judgment
was not advanced in conformity to 12 O.S. 1991 § 1006,
Cause No. 78,844 stands dismissed.
Ill
THE
TIMELY
COMMENCEMENT OF AN APPEAL INVESTS THE APPELLATE COURT WITH REVIEWING COGNIZANCE AND IDENTIFIES THE PARTIES APPELLANT AND APPELLEE.
Appellate review is commenced by a petition in error filed within thirty days of the judgment or final order date.
Timely commencement is jurisdictional.
Failure to file an appeal within the statutory time is fatal.
Timely filing serves the twofold purpose of apprising the appellate court and the parties appellant and appellee of the identity
and posture of the parties in the appeal as well as identifying the errors assigned for review. Rule 1.14,
Rules of Appellate Procedure in Civil Cases, mandates that the party appellant mail to each party to the appeal or to his counsel a copy of the petition in error.
The service of the petition in error is designed to ensure due process by affording timely notice to one who has been haled into court.
A
BECAUSE ISAACS HAD ENTERED ITS APPEARANCE BELOW, IT WAS A PARTY APPELLEE, EVEN THOUGH IT WAS NOT NAMED IN THE CAPTION OF THE PETITION IN ERROR. NONETHELESS, FAILURE TO SERVE ISAACS WITH A COPY OF THE PETITION IN ERROR OR WITH ANY OTHER NOTICE IS FATAL. IT PREVENTS THIS COURT FROM GRANTING ANY CORRECTIVE RELIEF AGAINST ISAACS.
Rule 1.14 requires that,
within thirty days of judgment date,
an appellant mail a copy of the petition in error to
each party to the
appeal,
The record demonstrates that
neither Isaacs nor its counsel of record was ever mailed a copy of the petition in error, was provided with any other notice or that Isaacs voluntarily entered its appearance in this appeal.
Timcorp is attempting to secure relief against Isaacs by reversal of the latter’s
nisi prius
victory.
Because Isaacs had entered its appearance below, it was a party appellee, even though it was not named in the caption of the petition in error.
Nonetheless, failure to serve Isaacs with a copy of the petition in error or with any other notice is fatal. It prevents this court from granting any corrective relief against Isaacs.
B
TIMCORP’S QUEST TO CONSOLIDATE ITS APPEALS WOULD IMPERMIS-SIBLY ADD A TARGETED PARTY APPELLEE MORE THAN THIRTY DAYS AFTER THE DATE OF THE JUDGMENT FROM WHICH THE SECOND APPEAL IS PROSECUTED.
In its second appeal [Cause No. 80,396] Timcorp seeks relief
only
from
Willow Wind/Beaver
arid
Isaacs.
None of its timely assigned errors adversely affects the City nor does its petition in error seek any relief from this party. In short, the City’s presence in the second appeal is only
nominal.
Timcorp’s quest to effect the desired transformation in the City’s status from a
nominal party appellee
to a
party appellee from whom (monetary) relief is sought
is
untimely
because
it came here more than thirty days after the date of the judgment from which the second appeal is
prosecuted,
The amendment, if granted, would offend the provisions of 12 O.S.1991 § 990A by allowing a belated appeal against the City.
IV
BECAUSE THE ENFORCEMENT MECHANISM IN THE MUNICIPAL ORDINANCES WAS INEFFECTIVE, THE EXHAUSTION-OF-REMEDIES DOCTRINE WAS NOT INVOCABLE.
Exhaustion of available administrative remedies is a general prerequisite for an aggrieved party’s resort to the courts.
A district-court action is not abatable
if the uninvoked administrative remedy was unavailable, ineffective or would have been futile to
pursue.
Timcorp urges that Willow Wind/Beaver should have first pursued its quest for relief from the Board of Review created by the City’s
pay-back
ordinances.
The administrative remedy available under the municipal law was conceded by all parties, including the City, to be
ineffective.
It would have been futile for Willow Wind to resort to a board which could not grant an effective remedy. There was hence no fatal
remedial impediment
to Willow Wind/Beaver’s pursuit of its district-court action.
V
AFTER FINDING THE ADMINISTRATIVE CONSTRUCTION OF THE ORDINANCES TO HAVE BEEN UNREASONABLE, THE TRIAL COURT CORRECTLY PROCEEDED TO CONSTRUE THE LANGUAGE OF THE PAY-BACK ORDINANCES.
The meaning of an ordinance, like that of a statute, is to be divined from the language found in its text.
The district court’s primary task was to examine the language of the
pay-back
ordinances in order to determine if it was ambiguous, incomplete, or in need of clarification. If, as here, a controversy arises about the scope and meaning of an ordinance, the cardinal rule of construction is to give effect to
the legislative intent expressed in the text.
The language of an ordinance, when given its
plain
and
ordinary
meaning, is the yardstick for ascertainment of the drafters’ intent.
In interpreting local legislation, the views of the city council and city administrators, though contemporaneous with enactment of the ordinance, should not be used to
alter
the
clear meaning
of the act’s language.
While construction of the ordinances by the department charged with their execution should be given weight
if the ordinances are
unclear,
it is the court’s duty to test the administrative interpretation pressed upon it for adoption against the text to be construed.
The trial court was especially concerned with the meaning of language found in Sections 37-185 and 37-189.
The City’s administrator of the
pay-back
program developed a policy that
only developers tieing onto a trunk line between the beginning and ending points of the line were assessable.
Parties tieing onto the
ends
of the line were not assessable. This policy was never re-
dueed to a formal regulation, but it was used to administer the program. The City administrator’s interpretation of these provisions did not pass muster. It was found so “simplistic, and just unreasonable” as to foist an “absurdity”.
Finding that municipal enforcement was based upon an
unreasonable
administrative interpretation, the trial court proceeded to give meaning to the ordinances in light of their general purpose and objective.
This approach culminated in the conclusions that (1) Timcorp, along with other defendants [not parties to this appeal], used [or was served by] the Willow Wind/Beaver
trunk line
to dispose of sewage from their additions and (2) the City was required by its ordinances to assess Timcorp a
tie-on fee.
Since the trial court’s construction and findings appear both reasonable and consistent with the textually demonstrable drafters’ intent, the
nisi prius
judgment must be affirmed.
VI
SUMMARY
The summary judgment tendered for review in Timcorp’s
first
appeal was unappeala-ble
sans
certification. It is hence dismissed. Timeorp’s failure
timely
to serve Isaacs with a copy of the petition in error or to otherwise give it notice of the
second
appeal is fatal to Timcorp’s quest for corrective relief against Isaacs. To permit Timcorp to reassert, in its second appeal, the errors assigned in the dismissed first appeal would offend § 990A. After the passage of more than 30 days after the date of the judgment from which the
second
appeal is prosecuted, Timcorp may not recast the City from a
nominal party appellee
to a
targeted party appellee
[against whom relief is sought]. Because the trial court correctly found that the available administrative remedies of the municipal law were ineffective, there was no remedial impediment to the pursuit of a district-court action. The
nisi prius
construction of the municipal ordinances is consistent with their plain and ordinary meaning and with the intent demonstrated on the face of the texts.
THE APPEAL IN CAUSE NO. 78,844 IS DISMISSED BECAUSE THAT APPEAL IS PROSECUTED FROM AN UNAP-PEALABLE SUMMARY JUDGMENT; THE MOTION TO AMEND THE PETITION IN ERROR IN CAUSE NO. 80,396 IS DENIED; AND THE JUDGMENT OF THE TRIAL COURT IS AFFIRMED.
LAVENDER, V.C.J., and SIMMS, HARGRAVE and ALMA WILSON, JJ., concur.
HODGES, C.J., and KAUGER and WATT, JJ., concur in part and dissent in part.
SUMMERS, J., dissents.