Thor Electric, Inc. v. Oberle & Associates, Inc.

741 N.E.2d 373, 2000 Ind. App. LEXIS 2040, 2000 WL 1844267
CourtIndiana Court of Appeals
DecidedDecember 18, 2000
Docket33A05-9812-CV-614
StatusPublished
Cited by21 cases

This text of 741 N.E.2d 373 (Thor Electric, Inc. v. Oberle & Associates, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thor Electric, Inc. v. Oberle & Associates, Inc., 741 N.E.2d 373, 2000 Ind. App. LEXIS 2040, 2000 WL 1844267 (Ind. Ct. App. 2000).

Opinion

OPINION

BROOK, Judge

Case Summary

Appellant-third-party plaintiff Thor Electric, Inc. (“Thor”) appeals the trial court’s judgment in favor of appellee-plain-tiff Oberle & Associates, Inc. (“Oberle”). Oberle cross-appeals the trial court’s award of attorney fees to Thor. We affirm in part, reverse in part, and remand with instructions.

Issues

Thor raises two issues for our review, which we restate as follows:

whether the trial court erred in its computation of the prejudgment interest awarded to Thor; and I.
whether the trial court erred in finding that there was insufficient evidence to support Thor’s claim of damages for lost bonding capacity. II.

On cross-appeal, Oberle raises one issue for our review, which we restate as whether the trial court erred in awarding Thor attorney fees as consequential damages in Thor’s breach of contract action against Oberle.

Facts and Procedural History

This case arises from the parties’ involvement in the renovation of the Leland Hotel in Richmond, Indiana (“the project”). Richmond Hotel Limited (“the Owner”) retained Oberle as the general contractor on the renovation project. Owner and Oberle entered into a written construction contract on May 26, 1985. Thereafter, on July 17, 1985, Oberle entered into a written contract with Thor, retaining Thor as a subcontractor to perform specified work on the project, including plumbing, heating, ventilation, and air conditioning. On August 7, 1985, Thor, in turn, entered into a subcontract with Hill Brothers Plumbing & Heating, Inc. (“Hill”) to perform plumbing work on the project. Thor also retained Godby Brothers, Inc. (“Godby”) for heating, cooling, ventilation, and sheet metal work on August 12, 1985. Under the Oberle/Thor contract, Thor was required to furnish Ob-erle with payment and performance bonds in the contract amount, which Thor provided on September 6, 1985, with Fidelity & Deposit Company (“F & D”) as surety. On the same date, Daniel Stamper (“Stamper”), president of Thor, entered into an agreement of indemnity with F & D as indemnitor.

The Oberle/Owner contract was a “cost plus” contract whereby Oberle was to be paid for its costs of construction, plus a fee, with a maximum contract price of $3.6 million, subject to adjustments. Simulta *376 neously with that agreement, Oberle and Owner entered into an escrow agreement appointing the First National Bank of Richmond as agent to hold five percent of the amounts payable to Oberle as retain-age until the project was completed. Pursuant to the contract, Oberle provided Owner with payment and performance bonds with Wausau Insurance Companies (“Wausau”) as surety.

The Oberle/Thor contract specified a contract price of $1,558,250, subject to any addition and/or deductions, for Thor’s work. Under the contract, Thor was required to submit monthly invoices to Ob-erle. Oberle would then pay Thor ninety-five percent of the invoiced amounts five days after Oberle was paid by the Owner. Thor would receive the five percent retain-age upon satisfactory completion of the work. Should Oberle fail to pay Thor, the contract provided that Thor could stop work until payment of the amount owed and the contract price would be adjusted for the additional costs of shutdown, delay, and start-up. The contract did not expressly provide for the recovery of attorney fees or other damages.

Through the course of the project, Ob-erle paid Thor ninety-five percent of the contract amounts. In 1986, the project experienced financial difficulties. As of May 30, 1986, Oberle had not been paid over $760,000 of its contract amount. On June 11,1986, Owner executed a promissory note in favor of Oberle for $225,000 to be paid on September 5, 1986, which Owner failed to pay when due. On April 27, 1987, Oberle filed suit against Owner on the promissory note. On June 15, 1987, Oberle filed a third-party complaint against Thor, Godby, and Hill to answer as to any lien or claim they may have against the project. On August 11, 1987, Thor filed its answer and cross-claim.

In its cross-claim, Thor sought payment of its retainage from Oberle. Thor was entitled to $82,633.30 in retainage under the Oberle/Thor contract. Thor also sought consequential damages for damage to its business reputation and lost bonding capacity as well as attorney fees. Additionally, Thor sought prejudgment interest on the retainage. Thor failed to pay its subcontractors; thus, Godby and Hill filed claims against Thor and F & D for retain-ages due under their subcontracts with Thor. F & D paid Godby and Hill’s claims under the payment bond issued on behalf of Thor.

On July 18, 1995, the trial court dismissed all claims except Thor’s claims against Oberle and Wausau and F & D’s claims against Thor and Stamper. A bench trial on these remaining claims was held in August and October 1995. On July 2, 1998, the trial court rendered its judgment, awarding Thor attorney fees, prejudgment interest, and damages against Oberle; awarding F & D damages against Thor and Stamper; and ordering that Thor take nothing against Wausau.

On July 17, 1998, Oberle filed its motion to correct error and motion for stay of execution of judgment. On August 28, 1998, the court held a hearing on the motion. Approximately two weeks later, the court entered its order on the motion, reducing Thor’s judgment against Oberle by approximately $1,500 in attorney fees, but otherwise denying Oberle’s motion to correct errors. The court also ordered execution of the judgment stayed upon Oberle’s posting of a bond in the amount of $220,000.

Discussion and Decision

I. Prejudgment Interest

Thor contends that the trial court erred in computing the prejudgment interest. Specifically, Thor asserts that the trial court improperly relied on Indiana Code Section 34-51-4 1 in determining the inter *377 est rate. Thor argues that the contract provided the appropriate interest rate: prime rate plus two percent. In the alternative, Thor contends that the proper interest rate is determined by Indiana Code Section 24-4.6-1-102. 2 In response, Ob-erle argues that the award of prejudgment interest was improper because the damages and the due date were not readily ascertainable. Alternatively, Oberle asserts that the determination of the amount of prejudgment interest is discretionary. Thus, the trial court properly looked to the tort prejudgment interest statute for guidance in determining the interest rate to be applied.

A. Entitlement to Prejudgment Interest

We first address Oberle’s argument that Thor is not entitled to prejudgment interest. Oberle contends that the damages were not readily ascertainable because Thor had not completed approximately $10,000 of the work. Further, Oberle argues that the due date was not ascertainable because it was uncertain when Thor satisfactorily completed the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Techna-Fit, Inc. and Stuart Trotter v. Fluid Transfer Products, Inc.
45 N.E.3d 399 (Indiana Court of Appeals, 2015)
Kathy Inman v. State Farm Mutual Automobile Insurance Company
981 N.E.2d 1202 (Indiana Supreme Court, 2012)
Rockford Mutual Insurance Co. v. Pirtle
911 N.E.2d 60 (Indiana Court of Appeals, 2009)
Baumgart Ex Rel. Baumgart v. DeFries
888 N.E.2d 199 (Indiana Court of Appeals, 2008)
Hanson v. Valma M. Hanson Revocable Trust
855 N.E.2d 655 (Indiana Court of Appeals, 2006)
Coca-Cola Co. v. Babyback's International, Inc.
841 N.E.2d 557 (Indiana Supreme Court, 2006)
Harlan Bakeries, Inc. v. Muncy
835 N.E.2d 1018 (Indiana Court of Appeals, 2005)
Utica Mutual Insurance v. Vigo Coal Co.
393 F.3d 707 (Seventh Circuit, 2004)
McLinden v. Coco
765 N.E.2d 606 (Indiana Court of Appeals, 2002)
DiMizio v. Romo
756 N.E.2d 1018 (Indiana Court of Appeals, 2001)
Allapattah Services, Inc. v. Exxon Corp.
157 F. Supp. 2d 1291 (S.D. Florida, 2001)
United Farm Family Ins. Co. v. Riverside Auto Sales
753 N.E.2d 681 (Indiana Court of Appeals, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
741 N.E.2d 373, 2000 Ind. App. LEXIS 2040, 2000 WL 1844267, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thor-electric-inc-v-oberle-associates-inc-indctapp-2000.