This text of Thomas, Tina R. v. Pearle Vision Inc (Thomas, Tina R. v. Pearle Vision Inc) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thomas, Tina R. v. Pearle Vision Inc, (7th Cir. 2001).

Opinion

In the United States Court of Appeals For the Seventh Circuit

No. 00-3681

Tina R. Thomas, O.D.,

Plaintiff-Appellant,

v.

Pearle Vision, Inc.,

Defendant-Appellee.

Appeal from the United States District Court for the Central District of Illinois. No. 97-1441--Joe B. McDade, Chief Judge.

Argued April 10, 2001--Decided May 30, 2001

Before Coffey, Rovner, and Diane P. Wood, Circuit Judges.

Coffey, Circuit Judge. When Pearle Vision, Inc. ("Pearle") refused to restore Dr. Tina Thomas to the optometrist position in its Peoria, Illinois, store after a medical leave related to the birth of her child, she sued Pearle, alleging that Pearle had breached her employment contract. Thomas claimed that Pearle’s 1997 Summary Plan Description of employee benefits incorporated into her contract the Family Medical Leave Act of 1993, 29 U.S.C. sec. 2601, et seq. Thomas also claimed Pearle violated the FMLA by failing to provide her with written notice that it considered her a highly compensated employee and that it intended to deny her job restoration upon the completion of her leave. The district court granted summary judgment to her employer, Pearle, holding that the "Problem Resolution" clause within the manual afforded Dr. Thomas an exclusive remedy for Pearle’s failure to comply with the FMLA and therefore, Dr. Thomas’s failure to comply with that clause defeated her claim. Dr. Thomas appeals.

I. Factual Background

Dr. Thomas began working at Pearle in September 1994 as a full-time doctor in its Peoria, Illinois store. Pearle employed only 12 employees at the Peoria store and less than 50 employees within 75 miles of the Peoria store. In 1996, however, Pearle distributed to all of its employees a 1997 Summary Plan Description of Employee Benefits ("1997 SPD"). In a section entitled, "The Family and Medical Leave Act of 1993," Pearle stated in the 1997 SPD that "all employees with one year of service who worked 1,250 hours with Pearle in the 12 months immediately prior to requesting leave" were eligible for leave under the FMLA. The 1997 SPD repeated this eligibility description clause later, stating "[i]f you have worked for Pearle for at least one year, and have worked 1,250 hours or more during the 12 month period prior to requesting leave, you are eligible for Family and Medical leave." The handbook further contained instructions on how to request leave, which required employees requesting leave to notify a supervisor at least 30 days in advance and complete the necessary FMLA forms. Additionally, the 1997 SPD contained a section entitled, "Problem Resolution." In that section, Pearle advised its employees that:

It is the policy of the organization not to discharge or discriminate against any employee exercising his or her rights under the federal Family and Medical Leave Act. If you think you have been treated unfairly, please contact the Vice President of Human Resources. The decision of the Vice President of Human Resources will be final and binding.

In September 1996 while expecting the birth of her first child, Dr. Thomas read over the potential benefits listed in the 1997 SPD to determine which one’s she might be eligible for, paying particular attention to potential benefits pursuant to the FMLA. Around February of 1997, Dr. Thomas notified her manager of her pregnancy and requested maternity leave under the FMLA. Dr. Thomas’s manager fur nished her with an FMLA checklist and other forms that had to be completed pursuant to the FMLA. On the FMLA request form, Dr. Thomas noted that she sought only eight weeks of leave (though the FMLA and Pearle’s plan allowed for up to twelve weeks of leave). Further, on the form for physician certification, which she completed before the birth of her child, Dr. Thomas and her physician answered in the affirmative that she was 1) able to perform work of any kind, and 2) able to perform the functions of her position.

Shortly after completing the forms, Dr. Thomas expressed a concern to Pearle regional manager, Cheryl Melquist, dealing with her eligibility because of the section in the 1997 SPD labeled "Job Restoration." In that section, Pearle noted that "[c]ertain highly compensated salaried employees are eligible for leave, but are not guaranteed restoration to their position if they choose to take leave."/1 Melquist advised Dr. Thomas that Pearle "would do everything [it] could to help, to get fill-in doctors for [her]" and that "as long as [it could] find fill-in help, [Thomas] would havenothing to worry about." Melquist also told Thomas to call Pearle’s human resources manager, Tim Hying, if she had any questions. Admittedly, both Melquist and Hying also told Thomas that there may not be a position for her when she returned, seemingly contradicting her earlier statement that Thomas had nothing to worry about. But neither Melquist nor Hying ever sent Thomas written notice to that effect or indicated definitively that she would not be offered job restoration upon completion of her leave.

Shortly before Thomas’s leave commenced, Pearle hired several doctors to serve part-time (both to cover Thomas’s absences before the delivery, and her leave after delivery). On April 24, Dr. Don Nelson told Thomas that he was going to fill in for her while she was on leave. Thomas’s manager, Traci Soots, confirmed that Dr. Nelson was temporary help. Thomas commenced her leave on April 29, several weeks earlier than she expected, because of a back problem asso ciated with her pregnancy. The next day, Thomas sent a letter via facsimile to Melquist, informing her that she still planned to take pregnancy leave and inquiring about what was planned for the future regarding her position and about Dr. Nelson’s status. On May 5, 1997, Melquist phoned Thomas and explained that Dr. Nelson was temporary help. But the following day, Hying instructed Melquist to hire a full-time regular employee doctor, and Dr. Nelson was hired shortly thereafter. Pearle did not notify Dr. Thomas at this time of its decision to hire Dr. Nelson full-time. In fact, Pearle never did notify Dr. Thomas in writing that they were unable to continue using temporary help to fill her position during her absence or much less that she would be denied job restoration upon her return from pregnancy leave.

Instead, sometime around July 1997 Dr. Thomas learned that Pearle had hired a full-time replacement for her when she noticed that her name was not on her office door. On July 24, 1997, regional manager Kurt Schaefer (who had recently replaced Melquist) informed Dr. Thomas (still, not in writing, but via a message left on her home telephone’s answering machine) that Pearle had hired Dr. Nelson as a full-time doctor and that there were currently no part-time or full-time positions available in the region. Schaefer did not explain that restoring Dr. Thomas to her position (or a similar one) would result in substantial and grievous economic injury to Pearle (thus necessitating the hire of Dr. Nelson). Dr. Thomas then commenced suit against Pearle for breach of contract, alleging that Pearle incorporated the FMLA into her contract through the 1997 SPD. Dr. Thomas further claimed that Pearle breached the contract when it failed to comply with the provision of the FMLA that an employer give highly compensated employees written notice at the time leave was requested that it intended to deny job restoration on the completion of leave. See 29 C.F.R. sec. 825.219.

Pearle moved for summary judgment, arguing that the 1997 SPD did not create an enforceable contract granting Dr. Thomas any rights under the FMLA, and in the alternative, that Dr. Thomas breached the contract by failing to take advantage of the "Problem Resolution" clause in the 1997 SPD.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chaffin v. John H Carter Co Inc
179 F.3d 316 (Fifth Circuit, 1999)
Hodgens v. General Dynamics Corp.
144 F.3d 151 (First Circuit, 1998)
Alfredo Diaz v. Fort Wayne Foundry Corporation
131 F.3d 711 (Seventh Circuit, 1997)
Regina R. King v. Preferred Technical Group
166 F.3d 887 (Seventh Circuit, 1999)
Michael Nero v. Industrial Molding Corporation
167 F.3d 921 (Fifth Circuit, 1999)
United States v. Pedro Morales
239 F.3d 113 (Second Circuit, 2000)
Duldulao v. Saint Mary of Nazareth Hospital Center
505 N.E.2d 314 (Illinois Supreme Court, 1987)
Omnitrus Merging Corp. v. Illinois Tool Works, Inc.
628 N.E.2d 1165 (Appellate Court of Illinois, 1993)
Dudek, Inc. v. Shred Pax Corp.
626 N.E.2d 1204 (Appellate Court of Illinois, 1993)
Lee v. Canuteson
573 N.E.2d 318 (Appellate Court of Illinois, 1991)
Pennsylvania Life Insurance v. Pavlick
637 N.E.2d 1160 (Appellate Court of Illinois, 1994)
Wheeler v. Phoenix Co. of Chicago
658 N.E.2d 532 (Appellate Court of Illinois, 1995)
Liccardi v. Stolt Terminals (Chicago), Inc.
669 N.E.2d 1192 (Appellate Court of Illinois, 1996)
In Re Marriage of Davis
678 N.E.2d 68 (Appellate Court of Illinois, 1997)
Epstein v. Yoder
391 N.E.2d 432 (Appellate Court of Illinois, 1979)
Perman v. ArcVentures, Inc.
554 N.E.2d 982 (Appellate Court of Illinois, 1990)
Dash Messenger Service Inc. v. Hartford Ins. Co. of Ill.
582 N.E.2d 1257 (Appellate Court of Illinois, 1991)
Mayfair Construction Co. v. Waveland Associates Phase I Limited Partnership
619 N.E.2d 144 (Appellate Court of Illinois, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Thomas, Tina R. v. Pearle Vision Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thomas-tina-r-v-pearle-vision-inc-ca7-2001.