Thomas Creek Lumber & Log Co. v. Board of Forestry

69 P.3d 1238, 188 Or. App. 10, 2003 Ore. App. LEXIS 662
CourtCourt of Appeals of Oregon
DecidedMay 29, 2003
DocketG60275, G60283 A114870 (Control), A114871
StatusPublished
Cited by20 cases

This text of 69 P.3d 1238 (Thomas Creek Lumber & Log Co. v. Board of Forestry) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thomas Creek Lumber & Log Co. v. Board of Forestry, 69 P.3d 1238, 188 Or. App. 10, 2003 Ore. App. LEXIS 662 (Or. Ct. App. 2003).

Opinion

*12 LANDAU, P. J.

Thomas Creek Lumber and Log Co. (Thomas Creek) and Nel-Log, Inc. (Nel-Log), petition for judicial review of two orders on reconsideration of the Board of Forestry (board). In the first order, the board (1) determined that Thomas Creek had violated ORS 527.670(6), requiring an operator, timber owner, or landowner to notify the State Forester 1 before commencing any “operation,” that is, any commercial activity relating to the harvest of forest tree species; (2) concluded that Thomas Creek had violated OAR 629-605-0150(1), providing for a 15-day waiting period after notification and before commencing a harvest operation, unless the waiting period is waived; and (3) assessed civil penalties for those violations. In its second order, the board determined that Nel-Log also had violated the notice and 15-day waiting period requirements and assessed civil penalties. We affirm.

I. FACTUAL BACKGROUND

We take the facts from the board’s orders on reconsideration and from the record. Brent C. Walker owns Thomas Creek. He also owns timberland located in Sections 3, 4, and 34 of what is commonly known as the Powers Creek area of central Marion County. Section 3 is located immediately to the east of Section 4, while Section 34 is located immediately to the north of Section 3. A county road runs generally from southwest to northeast from Section 4 into Section 34.

In November 1998, Walker submitted to the State Forestry Department (department) a notification of timber harvest operation on approximately 20 acres of land along Powers Creek in Section 4. The notification named Thomas Creek as the landowner and Nel-Log as the operator and stated that the operation would begin on November 18 and end on December 31, 1998. The notification also requested waiver of the requirement under OAR 629-605-0150 that the operator, landowner, or timber owner provide at least 15 days’ notice before commencing operations. By written *13 notation on the notification, Forest Practice Forester (FPF) Jackson waived the waiting period.

In December 1998, again on behalf of Thomas Creek and Nel-Log, Walker submitted another notification and request for waiver pertaining to a timber harvest operation in Section 4, stating that the operation would begin on December 23 and end on December 31, 1998. Jackson again waived the waiting period in writing.

After Thomas Creek and Nel-Log had completed their operations in Section 4, they moved their equipment approximately one-quarter mile northeast along the county road and 300 to 400 feet north and east along a logging road into Section 34. In mid-January, they commenced a timber harvest operation at the new location, with Thomas Creek felling the trees and Nel-Log hauling. Neither Thomas Creek nor Nel-Log filed a notification or requested a waiver of the waiting period before beginning that operation.

On January 26, 1999, a department employee reported the existence of the timber operation in Section 34 to FPF Gisler, who had temporarily replaced Jackson. On January 27, after determining that no notification had been filed for an operation in Section 34, Gisler went to the site, where she saw workers yarding and loading logs.

Gisler also saw two small streams near an old barn in Section 34. She directed the workers not to cut any more timber within 100 feet of the streams. On her return to her office, Gisler determined that the streams in question were classified on department water maps as “Type N” streams. Type N streams do not contain fish. OAR 629-635-0200(4)(c). Lands located near such streams do not require riparian management plans dr buffers from logging operations. OAR 629-605-0170(1)(a). Gisler reviewed Oregon Department of Water Resources records and learned that there was a registered domestic water right on one of the streams. She then summarily reclassified the stream as a Type D stream, a type of stream with domestic water use, OAR 629-635-0200(4)(b), that requires a riparian management plan for forest operations within 100 feet of its edge, OAR 629-635-0170(1)(a). She did not give notice of the reclassification to adjacent landowners, but she did notify Thomas Creek.

*14 On January 29, Gisler told Walker that a notification was required for the operation in Section 34. That same day, Walker faxed a notification and request for waiver for that operation. The notification named Thomas Creek as the landowner and timber owner and named Nel-Log as the operator. It stated that the operation encompassed five acres, that its estimated starting date was January 18, that its estimated ending date was February 28, and that it pertained to Section 34. The notification was signed by Walker and was dated January 15, 1999. Gisler, however, did not waive the 15-day waiting period.

On February 9,1999, Gisler told workers at the site to stop all operations at the site. By that time, Thomas Creek and Nel-Log had harvested approximately 27 loads of logs from Section 34. That same day, she also sent a facsimile to Walker and mailed a letter to Nel-Log to the same effect.

On February 24, Gisler issued three citations to Thomas Creek, alleging that it had violated ORS 527.670(6) by failing to notify the State Forester before conducting its operation in Section 34, that it had violated OAR 629-605-0170(1)(a) by failing to obtain prior approval of a written plan before conducting harvest activity within 100 feet of a Type D stream, and that it had violated OAR 629-605-0150(1) by failing to wait at least 15 days following notification before commencing its operation in section 34. Gisler also issued three citations to Nel-Log, asserting the same violations. ORS 527.680(1). In August 1999, the department issued notices of civil penalty and “orders” arising out of the citations. ORS 527.680(2) - (5); ORS 527.683; ORS 527.687; ORS 183.090.

Thomas Creek and Nel-Log requested hearings on the orders. ORS 527.687; ORS 527.700(1). The three citations issued to Thomas Creek were consolidated into a single contested case, as were the three citations issued to Nel-Log. The two contested cases were then consolidated for hearing, which, pursuant to ORS 527.687, was held before a hearing officer assigned from the Hearing Officer Panel established under Oregon Laws 1999, chapter 849, section 3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Answorth, Inc. v. OLCC
344 Or. App. 470 (Court of Appeals of Oregon, 2025)
Rushton v. Oregon Medical Board
497 P.3d 814 (Court of Appeals of Oregon, 2021)
Wolff v. Board of Psychologist Examiners
395 P.3d 44 (Court of Appeals of Oregon, 2017)
Stoltz v. Liberty Northwest Insurance Corp.
393 P.3d 239 (Court of Appeals of Oregon, 2017)
Watts v. Oregon State Board of Nursing
386 P.3d 34 (Court of Appeals of Oregon, 2016)
Phillips v. Department of Public Safety Standards & Training
364 P.3d 717 (Court of Appeals of Oregon, 2015)
Spurger v. SAIF Corp.
337 P.3d 883 (Court of Appeals of Oregon, 2014)
Read v. OREGON MEDICAL BOARD
260 P.3d 771 (Court of Appeals of Oregon, 2011)
Whaley v. Driver & Motor Vehicle Services Division
208 P.3d 1019 (Court of Appeals of Oregon, 2009)
Crooked River Ranch Water Co. v. Public Utility Commission
198 P.3d 967 (Court of Appeals of Oregon, 2008)
Roseburg Forest Products v. Hardenbrook-Hardy
171 P.3d 393 (Court of Appeals of Oregon, 2007)
Birmingham v. Department of Forestry
149 P.3d 600 (Court of Appeals of Oregon, 2006)
Fraser v. Land Conservation & Development Commission
138 P.3d 932 (Court of Appeals of Oregon, 2006)
Larsen v. Board of Parole
138 P.3d 16 (Court of Appeals of Oregon, 2006)
Tye v. McFetridge
112 P.3d 435 (Court of Appeals of Oregon, 2005)
Wahlgren v. Department of Transportation
102 P.3d 761 (Court of Appeals of Oregon, 2004)
Becklin v. Board of Examiners for Engineering & Land Surveying
97 P.3d 1216 (Court of Appeals of Oregon, 2004)
Baker v. City of Woodburn
79 P.3d 901 (Court of Appeals of Oregon, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
69 P.3d 1238, 188 Or. App. 10, 2003 Ore. App. LEXIS 662, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thomas-creek-lumber-log-co-v-board-of-forestry-orctapp-2003.