Thierer v. Board of County Commissioners

512 P.2d 343, 212 Kan. 571, 1973 Kan. LEXIS 554
CourtSupreme Court of Kansas
DecidedJuly 14, 1973
Docket46,856
StatusPublished
Cited by11 cases

This text of 512 P.2d 343 (Thierer v. Board of County Commissioners) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thierer v. Board of County Commissioners, 512 P.2d 343, 212 Kan. 571, 1973 Kan. LEXIS 554 (kan 1973).

Opinion

The opinion of the court was delivered by

Owsley, J.:

This is an appeal by plaintiffs, Henry and Nellie Thierer, from a decision of the trial court denying judgment for damages due to flooding and denying a mandatory injunction' against the defendant county commissioners. Defendants cross-appeal from a mandatory injunction ordering them to provide access to plaintiffs’ farm land by mean's of a suitable crossing over Thierer Branch of McDowell Creek.

Plaintiffs are owners and operators of a farm in Geary County, Kansas, through which meanders a stream. Their thirteen-acre tract of creek bottom land is protected from high water by a levee maintained by plaintiffs. In 1959, defendants caused the channel of Thierer Branch upstream from plaintiffs’ land to be altered in connection with relocating a bridge and county road. Due *572 to drought conditions, plaintiffs noticed no immediate effect on their property. In 1962, the effect o£ the upstream alteration of the channel was first manifest when the levee broke and the thirteen-acre tract was partly flooded. They repaired the levee, but it was broken by high water and the field flooded again in 1966. Plaintiffs contend the flooding was due to the increased flow caused by re-channeling upstream.

Access to the thirteen-acre tract was gained by a low-water crossing from Davis Creek Road; that is, the crossing was not by bridge over the stream, but was made by turning off the road and driving through shallow water at a point where the stream bed had a rock-gravel bottom. Plaintiffs testified they first became aware that their low-water crossing was no longer passable by truck or other farm implement in 1966. The water at that place was four or five feet deeper than formerly and it was unsafe to drive a vehicle through. The raising of the level of the adjacent roadway made the bank opposite their land higher and the incline too steep for farm equipment. They could sometimes drive from the county road through the creek into their field, but only if the water was below normal level. They could not get implements for harvesting the crops out of the field, even at low water periods, due to the incline of the bank. Plaintiffs testified they lost about half their crops due to lack of access at harvest time in 1966, 1967, 1968 and 1969. The county commissioners attempted to restore the crossing several times during 1966 and 1967 by gradirig the banks and hauling gravel into the stream, but the crossings were washed out by the normal flow of the stream and by harvest time of each year were impassable.

In 1967, plaintiffs brought this action praying for $10,000 damages for loss due to flooding in Count I, for a mandatory injunction against defendants ordering them to restore access to plaintiffs field in Count II, and for a mandatory injunction ordering defendants to restore the channel upstream to its former condition in Count III.

After trial to the court, plaintiffs were awarded judgment based upon Count II only, a mandatory injunction against defendants to provide access across the stream. Plaintiffs appeal from the judgment denying money damages for flooding (Count I), and denying a mandatory injunction ordering defendants to restore the upstream channel (Count III). Relief on Counts I and III was denied based upon the trial court’s finding that plaintiffs causes of action were *573 for permanent damages and that such damages were reasonably ascertainable when the levee broke in 1962. The court concluded as a matter of law that K. S. A. 60-513 (4), the two-year statute of limitations on tort actions, barred recovery on Counts I and III.

On appeal, plaintiffs assert their prayer in Count I was not for permanent damages from the channeling, but for temporary damages done by flood waters and erosion of the access crossing. Unfortunately, there was neither pretrial conference in this case, nor order clarifying the issues upon which the parties went to trial. We must rely upon the pleadings and evidence adduced at trial and as reproduced in the record on appeal for support of trial court’s findings and conclusions as to plaintiffs’ tiheory of recovery. The findings of fact of the trial court will not be disturbed on appeal if there is substantial competent evidence in the record to support them. (Fine v. Neale Construction Co., 186 Kan. 537, 352 P. 2d 404; Dennis v. Smith, 186 Kan. 539, 352 P. 2d 405.)

Count I of the petition filed November 15, 1967, reads as follows:

“2. That some time after June, 1958, the defendant, through its agents, servants and employees, changed the course, current, and cross-section of a stream known as Thierer Branch within the State of Kansas and without the consent or permit of the Chief Engineer of the Division of Water Resources as required by K. S. A. 82a-301.
“3. That due to a lack of rainfall in the area of the above-mentioned change in the course, current, and cross-section of Thierer Branch, no apparent damage was done to the property of these plaintiffs prior to April of 1966.
“4. Thereafter and since April, 1966, the water flowing in Thierer Branch and as a result of the change in the course, current and cross-section of Thierer Branch, as above mentioned, has overflowed the property of these plaintiffs and has otherwise been diverted from its regular and normal channel, to the damage of these plaintiffs.
“Wherefore, plaintiffs pray that they have judgment against the defendant in the sum of $10,000.00 and their costs.”

Considering the language of Count I and the testimony in connection therewith, we find ample support for the trial court’s finding that plaintiffs sought permanent damages. Plaintiffs made no effort in the trial court to amend their pleadings to include temporary damages. Likewise, they made no effort to submit to the trial court the issue of temporary damages. The first assertion of temporary damages appears on appeal. An issue not presented to the trial court cannot be a subject for appellate review. (Gray v. Ray Gill, Frontier Industries, Inc., 208 Kan. 95, 490 P. 2d 615.)

*574 When damage to the land from flooding becomes permanent, the statute of limitations bars recovery two years after the permanent damage is reasonably ascertainable. (K. S. A. 60-513 [4].) The trial court in this case found that “. . . it could have been ascertained, from the damage caused in 1962, that the said channel change would cause damage at any interval of high water.” This finding must be construed to include all damages from present and future flooding, as well as the incidental damage resulting from the destruction of the low-water crossing; therefore, plaintiffs’ prayer for permanent damages caused by defendants’ act in changing the channel was barred by the statute of limitations sometime in 1964. Plaintiffs brought this suit in 1967 and the trial court concluded as a matter of law that Counts I and III of their petition were barred by K. S. A. 60-513 (4). They assert the trial court’s finding that permanent damage was reasonably ascertainable in 1962 has no evidentiary support because they did not introduce evidence of the amount of flood damage in 1962.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dougan v. Rossville Drainage District
15 P.3d 338 (Supreme Court of Kansas, 2000)
Moon v. City of Lawrence
982 P.2d 388 (Supreme Court of Kansas, 1999)
Deisher v. Kansas Department of Transportation
958 P.2d 656 (Supreme Court of Kansas, 1998)
Isnard v. City of Coffeyville
917 P.2d 882 (Supreme Court of Kansas, 1996)
Johnson v. Board of County Commissioners
913 P.2d 119 (Supreme Court of Kansas, 1996)
Maxedon v. Texaco Producing, Inc.
710 F. Supp. 1306 (D. Kansas, 1989)
Olson v. State Highway Commission
679 P.2d 167 (Supreme Court of Kansas, 1984)
Schmeck v. City of Shawnee
651 P.2d 585 (Supreme Court of Kansas, 1982)
Gowing v. McCandless
547 P.2d 338 (Supreme Court of Kansas, 1976)
State v. Osbey
517 P.2d 141 (Supreme Court of Kansas, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
512 P.2d 343, 212 Kan. 571, 1973 Kan. LEXIS 554, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thierer-v-board-of-county-commissioners-kan-1973.