BROCK, J.

The question before us is whether certain language in a well-drilling contract can be construed as a guarantee that the contractor will establish a water-producing well as a condition precedent to receiving payment for his services.

The plaintiff, a well-drilling contractor, brought this action to recover the contract price for drilling a well hole on the defendant’s land. The defendant claims that he has no obligation to compensate the plaintiff because the well hole did not produce water. Trial to the court resulted in a verdict for the defendant. The plaintiff moved to set aside the verdict on the grounds that it was contrary to the evidence and erroneous as a matter of law. The trial court granted the motion on June 30, 1978. On July 14, 1978, the trial court issued a second order abrogating its June 30 order and denying the plaintiff’s motion. The plaintiff’s exception was reserved and transferred by Loughlin, J.

The trial court granted most of the plaintiff’s requests for findings of fact, which are binding on this court on review of a motion to set aside the verdict where the proceedings below are not recorded. Merchants Nat'l Bank v. Adams, 114 N.H. 46, 314 A.2d 664 (1974); see Beaudoin v. Beaudoin, 118 N.H. 325, 386 A.2d 1261 (1978). In September 1977, the defendant asked the plaintiff to drill a well hole on his property in Weare. After considerable discussion and negotiation, the parties came to an agreement. The plaintiff, in the defendant’s presence, drafted a one-page agreement, using a preprinted form but making handwritten additions and changes that reflected their negotiations. The most significant change was due to the defendant’s insistence that the contract be for a stated price rather than for a price per foot as is the plaintiff’s usual practice. The parties executed the contract in duplicate.

The plaintiff then brought his equipment onto the defendant’s land. The defendant rejected the plaintiff’s recommendation for the location of the well hole, selected the drilling site himself, and prevented the plaintiff from drilling at any other location. The plaintiff drilled to a depth of 600 feet without finding water. He offered to continue digging at an additional cost of $7 per foot, but the defendant rejected that offer. The defendant did not suggest that the plaintiff continue digging at no additional cost or dig at a different location, or else forfeit all compensation. The plaintiff then removed his equipment.

When the plaintiff submitted his bill for the contract price of $2,000, the defendant refused to pay on the grounds that the plaintiff had *601 failed to establish a water-producing well. The defendant has not at any time claimed that the work was not performed in a workmanlike manner. The defendant subsequently engaged another well driller, who drilled a water-producing well at a different location on the defendant’s property.

The uncertainty whether a well hole will produce a supply of good water, no matter how skillfully the work may be done, is a matter of common knowledge. Atwood Vacuum Machine Co. v. Varner Well and Pump Co., 3 Ill. App. 2d 571, 122 N.E.2d 834 (1954); Annot., 90 A.L.R.2d 1346 (1963). Therefore “the general rule is that under a contract to sink a well, the contractor does not, in the absence of any provision to this effect, guarantee the results of the undertaking in respect of the quantity or quality of the water to be produced.” O’Haire v. Breton, 102 N.H. 448, 452, 159 A.2d 805, 808 (1960). Any guarantee must be “by express statement or very clear implication, especially where the contractor does not choose the site.” Schofield v. School District No. 113, 105 Kan. 343, 346, 184 P. 480, 481-82 (1919); see O’Haire. o. Breton, 102 N.H. at 452, 159 A.2d at 808; 78 Am. JUR. 2d Waters § 189 (1975). The question before us is whether this contract, reasonably construed, contains an express warranty that water will be produced.

The preprinted contract form contained the following express disclaimer of guarantee:

7. The Contractor undertakes to perform all work under this agreement in a workmanlike manner and in accordance with standard practices for the drilling of wells in the vicinity of the Owner’s premises, and to proceed to the completion of the work with reasonable diligence. It is fully understood, however, that the Contractor does not warrant or guarantee that the work will result in the establishment of a water-producing well.

The defendant claims that, notwithstanding this express disclaimer, a guarantee of water was implied by some handwritten language added during the parties’ negotiations. That provision reads:

Contractor agrees to drill well for ($2,000.00) two thousand dollars, and get the minimum flow of five gal. at 100 ft., 3 gal. at 200 ft., 1 gal. at 310 ft. 3/4 gal. at 400 ft. & 1/2 gal. at 500 ft. Maximum 600 ft.

*602 The defendant’s position, which was apparently accepted by the trial court, is that the handwritten language constitutes a guarantee that the plaintiff will establish a water-producing well and that it prevails over the express printed disclaimer. We do not think the contract, taken as a whole, supports that interpretation.

It is this court’s task to interpret the contract, using facts found by the trial court. See MacLeod v. Chalet Susse Int’l, Inc., 119 N.H. 238, 401 A.2d 205 (1979). In our search for the interpretation that will best reflect the parties’ intention, the court considers “the written agreement of these parties, all of its provisions, its subject matter, the situation of the parties at the time, and the object intended.” Griswold v. Heat Inc., 108 N.H. 119, 123, 229 A.2d 183, 186 (1967).

The handwritten clause states that the contractor will drill a well and obtain a specified minimum flow at designated levels. A “well” is a hole dug for the purpose of obtaining water, and does not by itself indicate a successful water-producing well. BLACK’S LAW Dictionary 1766 (4th ed. 1951); 78 Am. Jur. 2d Waters § 182 (1975); accord, Littrell v. Wilcox, 11 Mont. 77, 84, 27 P. 394, 396 (1891). The trial court approved the plaintiff’s explanation that the list of minimum flow specifications meant that his obligation to continue drilling would cease if he obtained any one of the specified mínimums at that depth. The dispute between the parties centers, therefore, on what “maximum 600 feet” means. The plaintiff contends that drilling to 600 feet was his maximum obligation, which, if completed, would entitle him to compensation even if no water was found.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

International Business Machines Corp. v. Gary Joseph Khoury
177 A.3d 724 (Supreme Court of New Hampshire, 2017)
Catholic Medical Center v. Executive Risk Indemnity, Inc.
867 A.2d 453 (Supreme Court of New Hampshire, 2005)
Anderson v. Century Products Co.
D. New Hampshire, 1996
Merrimack School District v. National School Bus Service, Inc.
661 A.2d 1197 (Supreme Court of New Hampshire, 1995)
Holden Engineering & Surveying, Inc. v. Pembroke Road Realty Trust
628 A.2d 260 (Supreme Court of New Hampshire, 1993)
Gamble v. University System
610 A.2d 357 (Supreme Court of New Hampshire, 1992)
Lowell v. U.S. Savings Bank of America
572 A.2d 184 (Supreme Court of New Hampshire, 1990)
MacFarlane v. Rich
567 A.2d 585 (Supreme Court of New Hampshire, 1989)
Heaton v. Boulders Properties, Inc.
566 A.2d 1127 (Supreme Court of New Hampshire, 1989)
Centronics Data Computer Corp. v. Salzman
531 A.2d 348 (Supreme Court of New Hampshire, 1987)
Appeal of Concerned Corporators of the Portsmouth Savings Bank
525 A.2d 671 (Supreme Court of New Hampshire, 1987)
ELCA of New Hampshire, Inc. v. McIntyre
523 A.2d 90 (Supreme Court of New Hampshire, 1987)
Restaurant Operators, Inc. v. Jenney
519 A.2d 256 (Supreme Court of New Hampshire, 1986)
R. Zoppo Co. v. City of Dover
475 A.2d 12 (Supreme Court of New Hampshire, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
406 A.2d 115, 119 N.H. 598, 1979 N.H. LEXIS 361, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thiem-v-thomas-nh-1979.