South Willow Properties, LLC v. Burlington Coat Factory of New Hampshire, LLC

986 A.2d 506, 159 N.H. 494
CourtSupreme Court of New Hampshire
DecidedDecember 16, 2009
Docket2008-706
StatusPublished
Cited by22 cases

This text of 986 A.2d 506 (South Willow Properties, LLC v. Burlington Coat Factory of New Hampshire, LLC) is published on Counsel Stack Legal Research, covering Supreme Court of New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
South Willow Properties, LLC v. Burlington Coat Factory of New Hampshire, LLC, 986 A.2d 506, 159 N.H. 494 (N.H. 2009).

Opinion

Broderick, C.J.

This is a commercial landlord/tenant dispute between the landlord, plaintiff South Willow Properties, LLC (South Willow), and the tenant, defendant Burlington Coat Factory of New Hampshire, LLC (BCF). BCF appeals an order of the Manchester District Court (Emery, J.) finding that it failed to obtain South Willow’s permission before replacing the roof at its retail store, and that such failure constitutes a breach of the lease and grounds for eviction. We affirm.

The record contains the following facts. BCF, a retail clothing merchant, is a tenant in a shopping plaza in Manchester owned by South Willow. In late 2002, BCF assumed the obligations under a 1974 lease between the parties’ predecessors-in-interest and took occupancy of the space at issue.

When BCF moved into the premises, there were occasional leaks in the roof that were satisfactorily repaired by South Willow. In 2003, BCF undertook renovations to the property that included removing an interior concrete load-bearing wall, which caused serious structural problems; removing seven HVAC units and installing sixteen new units, which resulted in several large holes in the roof; and changing the facade of the building, which required four large holes in the roof to attach the support beams. As a result of these renovations, the roof developed numerous, severe leaks. The deflection in the roof caused by removal of the load-bearing wall and the negligent installation of the structural steel installed to support the remaining wall resulted in a “waterfall” coming through the roof. In 2004, BCF acknowledged responsibility for the structural problems, including the leaks, and agreed to pay for the engineering services and construction costs required to remedy them.

In September 2004, South Willow informed BCF that “none of the outstanding issues,” including those concerning roof damage, had been resolved. The parties continued to disagree about the adequacy of BCF’s repairs to the roof into 2005. In August 2005, BCF alleged that fixing the roof leaks was South Willow’s responsibility and that it would replace the *497 roof if South Willow did not. South Willow responded by instructing BCF not to engage in any type of roof replacement without its written consent and notifying BCF that doing so would be “a default under the lease.”

On September 8, 2005, BCF sent a letter to South Willow in which it stated, “[Replacement of the roof is Landlord’s responsibility under Article 14 of the Lease. Further, under Article 28 of the Lease, in the event Landlord fails to perform any of its obligations under the Lease, and after seven (7) days notice, Tenant may cure such default on Landlord’s behalf.” By letter dated the following day, South Willow reiterated that BCF “does not have the Landlord’s permission to perform any work on the roof’ and doing so “without landlord’s written consent would be a default under the lease.” On October 13, 2005, BCF sent an email to South Willow attaching bids for a new roof and requesting a decision by October 19. On October 31, without notification to South Willow, BCF signed a contract for replacement of the roof.

On February 23, 2006, South Willow sent a letter to BCF stating that it was locating a contractor to install a new roof. On March 2, BCF faxed a letter to South Willow stating that it had “already contracted with a roofing contractor to replace the roof.” Demolition of the roof commenced that same day. South Willow responded on March 2, instructing BCF to cease all roof work, but BCF proceeded to have its contractor replace the existing roof.

On October 17, 2006, South Willow served a notice to quit and in May 2007, filed its landlord-tenant writ. On October 31, 2007, the district court concluded that the notice to quit was not sufficiently specific and dismissed the case. Two days later, South Willow issued a new eviction notice and notice to quit. A new possessory action was filed and, following a bench trial, the court ordered the issuance of a writ of possession.

BCF appeals, arguing that the trial court erred: (1) in ruling that South Willow’s second action was not barred by the doctrine of res judicata; (2) in ruling that South Willow’s continued acceptance of rent did not constitute a waiver of South Willow’s right to evict; (3) in its interpretation of the lease; (4) in excluding expert testimony; (5) in failing to find that BCF’s replacement of the roof was a non-material breach of the parties’ lease; and (6) in finding that there was insufficient evidence to prove the property was not safe or unsuitable for its intended use.

We first address BCF’s argument that the trial court erred by not dismissing South Willow’s second lawsuit under the doctrine of res judicata. BCF argues that the judgment in the first lawsuit was a “final judgment on the merits” in that South Willow failed to prove service of a proper eviction notice, which BCF contends was a “material element of its claim.”

*498 The applicability of res judicata is a question of law, which we review de novo. Meier v. Town of Littleton, 154 N.H. 340, 342 (2006). Res judicata precludes litigation in a later case of matters actually decided, and matters that could have been litigated, in an earlier action between the same parties for the same cause of action. Id. For the doctrine to apply, three elements must be met: (1) the parties must be the same or in privity with one another; (2) the same cause of action must be before the court in both instances; and (3) a final judgment on the merits must have been rendered in the first action. Id. The parties do not dispute that the first two elements are met. The issue before us, therefore, is whether a final judgment on the merits was rendered in the first action.

On October 17, 2006, South Willow served BCF with a thirty-day notice to quit. The notice stated: ‘You are hereby notified to quit and deliver possession of 1525 South Willow Street... no later than November 18,2006 (30 days from the date of this Notice) for your failure to comply with Section 15 of the Lease requiring the tenant to provide plans and specifications and obtain the written consent of the Landlord prior to engaging in structural work on the demised Premises.” BCF filed a special plea and brief statement of defenses arguing, in part, that the notice to quit was defective because it set forth two different notice periods, it failed to allege that BCF committed a material breach of the lease, it failed to state with sufficient specificity the reason(s) for the eviction, and its notice period was insufficient.

The court held a bench trial and at the close of evidence BCF argued that the notice to quit failed to comply with RSA 540:3 because the notice was not specific as to the tenant’s alleged conduct and it did not give a sufficient notice period. The trial court agreed and granted BCF’s motion to dismiss. In its order, the court stated: “Given this decision, the court did not address the other issues raised by the defendant nor did the court rule on the requests for findings.” Two days later, South Willow served BCF with a second eviction notice and notice to quit.

RSA chapter 540 (2007 & Supp. 2008) authorizes summary possessory actions to simplify and facilitate the landlord’s recovery of possession of the premises. Lavoie v. Szumiez, 115 N.H.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Petition of State of N.H.
2024 N.H. 18 (Supreme Court of New Hampshire, 2024)
Charles D. Finch v. U.S. Banik, N.A.
2024 ME 2 (Supreme Judicial Court of Maine, 2024)
Roger Pratt & a. v. Agel Corman Realty, Inc. & a.
Supreme Court of New Hampshire, 2023
Estate of Bowen S. Downes v. Dennis Greenwood
Supreme Court of New Hampshire, 2023
John Lukens v. Kevin Quigley & a.
Supreme Court of New Hampshire, 2021
Taras W. Kucman & a. v. Katherine Matos & a.
Supreme Court of New Hampshire, 2020
Richard Horton & a. v. David Clemens & a.
Supreme Court of New Hampshire, 2020
Appeal of Steven Silva
Supreme Court of New Hampshire, 2019
Kenneth T. Riso & a. v. Gregory R. Riso & a.
210 A.3d 879 (Supreme Court of New Hampshire, 2019)
In re Silva
210 A.3d 887 (Supreme Court of New Hampshire, 2019)
Stewart v. Virgin Islands Board of Land Use Appeals
66 V.I. 522 (Supreme Court of The Virgin Islands, 2017)
Ken Henderson & a. v. Jenny DeCilla
Supreme Court of New Hampshire, 2016
Bartlett v. Commerce Insurance
114 A.3d 724 (Supreme Court of New Hampshire, 2015)
Village Green Condominium Ass'n v. Hodges
114 A.3d 323 (Supreme Court of New Hampshire, 2015)
State of New Hampshire v. Paul A. Costella
166 N.H. 705 (Supreme Court of New Hampshire, 2014)
State of New Hampshire v. Ashley Hayward
166 N.H. 575 (Supreme Court of New Hampshire, 2014)
Syncom Industries, Inc. v. Wood (In re Wood)
488 B.R. 265 (D. Connecticut, 2013)
Town of Atkinson v. Malborn Realty Trust
53 A.3d 561 (Supreme Court of New Hampshire, 2012)
Groleau v. American Express et al.
2011 DNH 166 (D. New Hampshire, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
986 A.2d 506, 159 N.H. 494, Counsel Stack Legal Research, https://law.counselstack.com/opinion/south-willow-properties-llc-v-burlington-coat-factory-of-new-hampshire-nh-2009.