Holden Engineering & Surveying, Inc. v. Pembroke Road Realty Trust

628 A.2d 260, 137 N.H. 393, 1993 N.H. LEXIS 87
CourtSupreme Court of New Hampshire
DecidedJuly 7, 1993
DocketNo. 92-486
StatusPublished
Cited by28 cases

This text of 628 A.2d 260 (Holden Engineering & Surveying, Inc. v. Pembroke Road Realty Trust) is published on Counsel Stack Legal Research, covering Supreme Court of New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Holden Engineering & Surveying, Inc. v. Pembroke Road Realty Trust, 628 A.2d 260, 137 N.H. 393, 1993 N.H. LEXIS 87 (N.H. 1993).

Opinion

JOHNSON, J.

The plaintiff, Holden Engineering and Surveying, Inc., sued the defendants, Pembroke Road Realty Trust and Jerry McCarthy (individually and as trustee of Pembroke), for payment pursuant to a contract between the parties. The Concord District Court {Sullivan, J.) ruled in favor of the defendants, finding that the plaintiff had not performed a condition precedent to payment. The plaintiff appeals this decision, and we reverse.

In early August 1991, the defendants hired the plaintiff to help them subdivide a plot of land. The parties’ contract specifies the “Ob[394]*394jectives and Scope of Services” as follows: “Conduct boundary survey of 19 acre parcel, subdivide 1 acre abutting Cole lot. Prepare minor subdivision plan for submission to City of Concord. To present subdivision plan and procure Planning Board approval.” Under the heading, “Budget Estimate,” the contract states, “Work to be done at standard hourly rates. Lump sum figure $3,000.00.” Immediately following the number, “$3,000.00,” appear the handwritten words, “(Not to exceed),” and defendant Jerry McCarthy’s initials. Paragraph eleven of the contract states, in pertinent part:

’’Billing/Payments. Invoices for [the plaintiff’s] services shall be submitted on a semi-monthly basis .... All such invoices shall be payable within fifteen (15) days after the date thereof and shall, in the event that payment is not duly made, bear interest at the rate of two percent (2%) a month from date of original billing .... It is further understood that if there be failure by [the defendants] to pay any invoice due to the [plaintiff] within fifteen (15) days after the date thereof, the [plaintiff] may . . . terminate its performance hereunder. In the event that the [plaintiff] places any invoice which is unpaid after the due date in the hands of any agency or an attorney for collection, [the defendants] shall pay all costs and expenses of such collection, including reasonable attorney’s fees and court costs.”

At the end of this paragraph appear more handwritten words— ’’Based upon Percentage of Completion” — and, again, Jerry McCarthy’s initials. Both parties agree that the handwritten words are binding amendments to the contract.

The plaintiff performed “a substantial amount of work” under the contract and obtained conditional approval from the Concord Planning Board for the defendants’ proposed subdivision.on September 18, 1991. The conditions placed on final approval stemmed from the discovery that the defendants’ land contains a habitat for the Earner Blue butterfly, an endangered species. The conditions require “[t]he conveyance of a buffer easement to the New Hampshire Natural Heritage Inventory (NHNHI) for lot 19 for the area so noted on the subdivision plan ... [and] [t]he development of a management agreement between the owner of lot 12 for the Earner Blue Habitat on said lot.” These two conditions apparently have not been met, and therefore, the defendants have yet to receive final board approval for their proposed subdivision.

[395]*395The defendants have also yet to pay the plaintiff for any of the work performed under the contract, although the plaintiff sent them four invoices for services rendered. The invoices were dated August 9,1991, August 23,1991, September 6,1991, and November 15,1991, and listed, respectively, the following amounts due: $65, $3,010, $100, and $1,185.51. In response to the plaintiff’s suit to recover these amounts, the defendants claimed that the parties’ contract obligates the plaintiff to procure final board approval and makes such approval a condition precedent to any payment. The plaintiff disagreed, maintaining that it fully performed under the contract, and that the conditions imposed by the board for final approval were unforeseeable and beyond the scope of the plaintiff’s expertise. Each party alleged that the other failed to cooperate in attempting to obtain final approval.

The district court held a hearing and admitted extrinsic evidence to interpret the contract. The court decided:

“While the testimony is clearly in conflict, I conclude that based upon my review of the testimony and documentary evidence the Plaintiff has not completed the contract as envisioned by the parties. Final sub-division approval has not been obtained and I conclude that the Plaintiff is not entitled to be paid under the contract as I interpret its terms and conditions.”

This appeal followed.

Before this court, the plaintiff makes the same arguments it made below and asks that we enter judgment in its favor. The defendants also repeat their earlier contentions, arguing first that the contract provision regarding the plaintiff’s obligation to procure board approval is ambiguous. Consequently, they contend, the district court properly admitted extrinsic evidence to determine whether such approval is a condition precedent to payment under the contract. See Erin Food Servs., Inc. v. 688 Props., 119 N.H. 232, 235, 401 A.2d 201, 203 (1979). Because the plaintiff has not provided us with a transcript of the trial proceedings, the defendants maintain that the district court’s findings are presumed to be supported by the evidence and, hence, are unreviewable.

We note that the interpretation of a contract, including whether a contract term is ambiguous, is ultimately a question of law for this court to decide. See Gamble v. University of New Hampshire, 136 N.H. 9, 13, 610 A.2d 357, 360 (1992). As elaborated below, [396]*396our review of the entire contract persuades us that the provisions relating to board approval are not ambiguous and, in fact, manifestly support the plaintiff’s argument that final board approval is not a condition precedent to payment. Accordingly, extrinsic evidence should not have been used to contradict the contract, see Parkhurst v. Gibson (Parkhurst), 133 N.H. 57, 62, 573 A.2d 454, 457 (1990); Logic Assoc’s, Inc. v. Time Share Corp., 124 N.H. 565, 572, 474 A.2d 1006, 1010 (1984), and we need not accord deference to any findings based on such evidence. Instead, we conduct an independent examination of the contract and derive its meaning therefrom.

We turn now to the question of final board approval and the plaintiff’s right to collect payment in the absence thereof. We first note that “conditions precedent are not favored, and we will not so construe such conditions unless required by the plain language of the agreement.” In re Estate of Kelly, 130 N.H. 773, 781, 547 A.2d 284, 289 (1988). “As a rule of thumb, provisions which commence with words such as ‘if,’ ‘on condition that,’ ‘subject to’ and ‘provided’ create conditions precedent.” J. Calamari & J. Perillo, The Law of Contracts § 11-9, at 448 (3rd ed. 1987). In the provision of the contract relied on by the defendants, none of these signal words appear to alert a party that a condition precedent may exist.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Evan Greenwald & a. v. Richard Keating & a.
212 A.3d 936 (Supreme Court of New Hampshire, 2019)
Santos v. Metro. Prop. & Cas. Ins. Co.
201 A.3d 1243 (Supreme Court of New Hampshire, 2019)
Estate of Theodore R. Mortner & a. v. Lindsay Thompson
182 A.3d 1260 (Supreme Court of New Hampshire, 2018)
National Pasteurized Egg v. Davidson
2011 DNH 208 (D. New Hampshire, 2011)
Carrier v. American Bankers Life
2006 DNH 048 (D. New Hampshire, 2006)
ikon GmbH v. Enterasys Networks
2003 DNH 031 (D. New Hampshire, 2003)
Lake v. Sullivan
766 A.2d 708 (Supreme Court of New Hampshire, 2001)
Piascik-Lambeth v. Textron Automotive
2000 DNH 264 (D. New Hampshire, 2000)
West v. Turchioe
761 A.2d 382 (Supreme Court of New Hampshire, 1999)
Appeal of the City of Manchester
743 A.2d 821 (Supreme Court of New Hampshire, 1999)
Ostler v. Codman Research
D. New Hampshire, 1999
Hopkins v. Fleet Bank
724 A.2d 1287 (Supreme Court of New Hampshire, 1999)
Appeal of Reid
722 A.2d 489 (Supreme Court of New Hampshire, 1998)
Galloway v. Chicago-Soft, Ltd.
713 A.2d 982 (Supreme Court of New Hampshire, 1998)
S t . Marys Bank v. Creme
D. New Hampshire, 1998

Cite This Page — Counsel Stack

Bluebook (online)
628 A.2d 260, 137 N.H. 393, 1993 N.H. LEXIS 87, Counsel Stack Legal Research, https://law.counselstack.com/opinion/holden-engineering-surveying-inc-v-pembroke-road-realty-trust-nh-1993.