ikon GmbH v. Enterasys Networks

2003 DNH 031
CourtDistrict Court, D. New Hampshire
DecidedMarch 5, 2003
DocketCV-02-98-B
StatusPublished

This text of 2003 DNH 031 (ikon GmbH v. Enterasys Networks) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ikon GmbH v. Enterasys Networks, 2003 DNH 031 (D.N.H. 2003).

Opinion

ikon GmbH v. Enterasys Networks CV-02-98-B 03/05/03

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE

Ikon GmbH and TEWS Technologies GmbH

v. Civil No. 02-98-B Opinion No. 2003 DNH 031 Enterasvs Networks, Inc.

MEMORANDUM AND ORDER

Enterasys Networks, Inc. entered into an agreement to pay

ikon GmbH to design and develop circuit boards and software.

Under the agreement, ikon's development of the products were

scheduled to begin on the date Enterasys remitted an initial

payment egualing 35% of the total cost of ikon's services.

Although Enterasys never remitted the initial payment, ikon and

its subcontractor, TEWS Technologies GmbH, began working on the

design and development of the circuit boards and software. Ikon

and TEWS have sued Enterasys for breach of contract, seeking to

recover all costs associated with the work it performed under the

agreement. Enterasys moves for summary judgment, alleging that

the initial payment was a condition precedent to ikon's performance under the agreement, and that since it never remitted

the payment a contract was never formed.

I. STANDARD OF REVIEW

Summary judgment is appropriate only "if the pleadings,

depositions, answers to interrogatories, and admissions on file,

together with the affidavits, if any, show that there is no

genuine issue as to any material fact and that the moving party

is entitled to judgment as a matter of law." Fed. R. Civ. P.

56(c). A genuine issue is one "that properly can be resolved

only by a finder of fact because [it] may reasonably be resolved

in favor of either party." Anderson v. Liberty Lobby, Inc., 477

U.S. 242, 250 (1986). A material fact is one that affects the

outcome of the suit. See id. at 248.

In ruling upon a motion for summary judgment, I must

construe the evidence in the light most favorable to the non­

movant. See Navarro v. Pfizer Corp., 261 F.3d 90, 94 (1st Cir.

2001). The party moving for summary judgment, however, "bears

the initial responsibility of informing the district court of the

basis for its motion, and identifying those portions of [the

- 2 - record] which it believes demonstrate the absence of a genuine

issue of material fact." Celotex Corp. v. Catrett, 477 U.S. 317,

323 (1986). Once the moving party has properly supported its

motion, the burden shifts to the nonmoving party to "produce

evidence on which a reasonable finder of fact, under the

appropriate proof burden, could base a verdict for it; if that

party cannot produce such evidence, the motion must be granted."

Ayala-Gerena v. Bristol Myers-Sguibb Co., 95 F.3d 86, 94 (1st

Cir. 1996) (citing Celotex, 477 U.S. at 323; Anderson, 477 U.S.

at 249). Neither conclusory allegations, improbable inferences,

or unsupported speculation are sufficient to defeat summary

judgment. See Carroll v. Xerox Corp., 294 F.3d 231, 236-37 (1st

Cir. 2 002).

II. BACKGROUND

According to the agreement, ikon was "to design, have

designed, develop, or have developed" circuit board assemblies

and software. Def's Mem. in support of Mot. for Summ. J., Ex. 1

at 5 2.0 ("Agreement"). In exchange, Entrasys agreed to

compensate ikon for the project according to a payment schedule.

- 3 - Development of the circuit boards and software was scheduled to

start upon the date the first payment of 35% of the total project

costs was made by Enterasys. Agreement at Ex A, n.23(a).

According to Enterasys' director of hardware development, ikon

"would not consider Enterasys to be 'serious' about the

Agreement" until the first payment was received. Hirani Aff. at

5 3. Furthermore, ikon apparently insisted that it would not

begin the project until it received the first payment. Id. at 5

7.

About a month after entering the agreement, Enterasys

concluded that ikon would not be able to complete the project

according to the delivery schedule in the agreement.

Subseguently, Enterasys notified ikon that it would not remit the

first payment and, therefore, it considered the agreement void.

Although it did not receive the first payment, ikon had

already begun designing and developing the circuit boards and

software. Further, it had sought and received approval from

Enterasys to hire TEWS as a subcontractor. After Enterasys

notified ikon that it would not remit the initial payment and

considered the contract void, ikon and TEWS initiated this action

- 4 - seeking to recover damages for the work they had completed.

III. DISCUSSION

A. The initial payment

Enterasys argues that ikon's promise to perform under the

Agreement was conditioned upon the receipt of Enterasys' initial

payment. Enterasys concludes that since it did not remit the

payment, this condition precedent was not satisfied and an

agreement was never formed.

The interpretation of contracts is a guestion of law for the

court to decide. Strafford Tech., Inc. v. Camcar, 147 N.H. 174,

(2001). When interpreting a written contract, I must "read the

document as a whole and give its terms their reasonable meaning."

Id. This remains true for contractual terms that establish

conditions precedent. However, "[a]s a general rule, conditions

precedent are not favored, and [I] will not so construe such

conditions unless reguired by the plain language of the

agreement." In re Estate of Kelly, 130 N.H. 773, 781 (1988).

Conditions precedent "'are those facts and events, occurring

subseguently to the making of a valid contract, that must . . .

- 5 - occur before there is a right to . . . performance.'" Id. at 781

(quoting 3A A. Corbin, Corbin on Contracts 628, at 16 (I960)).

"As a rule of thumb, provisions which commence with words such as

'if,' 'on condition that,' 'subject to' and 'provided' create

conditions precedent." Holden Engineering and Surveying, Inc. v.

Pembroke Road Realty Trust, 137 N.H. 393, 396 (1993). When the

parties expressly condition their performance upon the occurrence

or non-occurrence of an event, "rather than simply including the

event as one of the general terms of the contract, the parties'

bargained-for expectation of strict compliance should be given

effect." Renovest Co. v. Hodges Dev. Corp., 135 N.H. 72, 78

(1991)

I conclude that the initial payment provision was not a

condition precedent to ikon's promise to perform under the

agreement. Ikon promised to design and develop certain items and

to deliver these items to Enterasys according to a set schedule.

The performance of this promise was not conditioned upon the

receipt of Enterasys' initial payment. See Agreement at 5 2.0.

Indeed, none of the common terms that trigger a condition

precedent are present in the contract language that established

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Navarro Pomares v. Pfizer Corporation
261 F.3d 90 (First Circuit, 2001)
Carroll v. Xerox Corp.
294 F.3d 231 (First Circuit, 2002)
Arlington Trust Co. v. Estate of Wood
465 A.2d 917 (Supreme Court of New Hampshire, 1983)
Hrushka v. State of New Hampshire Department of Public Works & Highways
381 A.2d 326 (Supreme Court of New Hampshire, 1977)
Tamposi Associates, Inc. v. Star Market Co.
406 A.2d 132 (Supreme Court of New Hampshire, 1979)
In re Estate of Kelly
547 A.2d 284 (Supreme Court of New Hampshire, 1988)
Renovest Co. v. Hodges Development Corp.
600 A.2d 448 (Supreme Court of New Hampshire, 1991)
Holden Engineering & Surveying, Inc. v. Pembroke Road Realty Trust
628 A.2d 260 (Supreme Court of New Hampshire, 1993)
Strafford Technology, Inc. v. Camcar Division of Textron, Inc.
784 A.2d 1198 (Supreme Court of New Hampshire, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
2003 DNH 031, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ikon-gmbh-v-enterasys-networks-nhd-2003.