ikon GmbH v. Enterasys Networks CV-02-98-B 03/05/03
UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE
Ikon GmbH and TEWS Technologies GmbH
v. Civil No. 02-98-B Opinion No. 2003 DNH 031 Enterasvs Networks, Inc.
MEMORANDUM AND ORDER
Enterasys Networks, Inc. entered into an agreement to pay
ikon GmbH to design and develop circuit boards and software.
Under the agreement, ikon's development of the products were
scheduled to begin on the date Enterasys remitted an initial
payment egualing 35% of the total cost of ikon's services.
Although Enterasys never remitted the initial payment, ikon and
its subcontractor, TEWS Technologies GmbH, began working on the
design and development of the circuit boards and software. Ikon
and TEWS have sued Enterasys for breach of contract, seeking to
recover all costs associated with the work it performed under the
agreement. Enterasys moves for summary judgment, alleging that
the initial payment was a condition precedent to ikon's performance under the agreement, and that since it never remitted
the payment a contract was never formed.
I. STANDARD OF REVIEW
Summary judgment is appropriate only "if the pleadings,
depositions, answers to interrogatories, and admissions on file,
together with the affidavits, if any, show that there is no
genuine issue as to any material fact and that the moving party
is entitled to judgment as a matter of law." Fed. R. Civ. P.
56(c). A genuine issue is one "that properly can be resolved
only by a finder of fact because [it] may reasonably be resolved
in favor of either party." Anderson v. Liberty Lobby, Inc., 477
U.S. 242, 250 (1986). A material fact is one that affects the
outcome of the suit. See id. at 248.
In ruling upon a motion for summary judgment, I must
construe the evidence in the light most favorable to the non
movant. See Navarro v. Pfizer Corp., 261 F.3d 90, 94 (1st Cir.
2001). The party moving for summary judgment, however, "bears
the initial responsibility of informing the district court of the
basis for its motion, and identifying those portions of [the
- 2 - record] which it believes demonstrate the absence of a genuine
issue of material fact." Celotex Corp. v. Catrett, 477 U.S. 317,
323 (1986). Once the moving party has properly supported its
motion, the burden shifts to the nonmoving party to "produce
evidence on which a reasonable finder of fact, under the
appropriate proof burden, could base a verdict for it; if that
party cannot produce such evidence, the motion must be granted."
Ayala-Gerena v. Bristol Myers-Sguibb Co., 95 F.3d 86, 94 (1st
Cir. 1996) (citing Celotex, 477 U.S. at 323; Anderson, 477 U.S.
at 249). Neither conclusory allegations, improbable inferences,
or unsupported speculation are sufficient to defeat summary
judgment. See Carroll v. Xerox Corp., 294 F.3d 231, 236-37 (1st
Cir. 2 002).
II. BACKGROUND
According to the agreement, ikon was "to design, have
designed, develop, or have developed" circuit board assemblies
and software. Def's Mem. in support of Mot. for Summ. J., Ex. 1
at 5 2.0 ("Agreement"). In exchange, Entrasys agreed to
compensate ikon for the project according to a payment schedule.
- 3 - Development of the circuit boards and software was scheduled to
start upon the date the first payment of 35% of the total project
costs was made by Enterasys. Agreement at Ex A, n.23(a).
According to Enterasys' director of hardware development, ikon
"would not consider Enterasys to be 'serious' about the
Agreement" until the first payment was received. Hirani Aff. at
5 3. Furthermore, ikon apparently insisted that it would not
begin the project until it received the first payment. Id. at 5
7.
About a month after entering the agreement, Enterasys
concluded that ikon would not be able to complete the project
according to the delivery schedule in the agreement.
Subseguently, Enterasys notified ikon that it would not remit the
first payment and, therefore, it considered the agreement void.
Although it did not receive the first payment, ikon had
already begun designing and developing the circuit boards and
software. Further, it had sought and received approval from
Enterasys to hire TEWS as a subcontractor. After Enterasys
notified ikon that it would not remit the initial payment and
considered the contract void, ikon and TEWS initiated this action
- 4 - seeking to recover damages for the work they had completed.
III. DISCUSSION
A. The initial payment
Enterasys argues that ikon's promise to perform under the
Agreement was conditioned upon the receipt of Enterasys' initial
payment. Enterasys concludes that since it did not remit the
payment, this condition precedent was not satisfied and an
agreement was never formed.
The interpretation of contracts is a guestion of law for the
court to decide. Strafford Tech., Inc. v. Camcar, 147 N.H. 174,
(2001). When interpreting a written contract, I must "read the
document as a whole and give its terms their reasonable meaning."
Id. This remains true for contractual terms that establish
conditions precedent. However, "[a]s a general rule, conditions
precedent are not favored, and [I] will not so construe such
conditions unless reguired by the plain language of the
agreement." In re Estate of Kelly, 130 N.H. 773, 781 (1988).
Conditions precedent "'are those facts and events, occurring
subseguently to the making of a valid contract, that must . . .
- 5 - occur before there is a right to . . . performance.'" Id. at 781
(quoting 3A A. Corbin, Corbin on Contracts 628, at 16 (I960)).
"As a rule of thumb, provisions which commence with words such as
'if,' 'on condition that,' 'subject to' and 'provided' create
conditions precedent." Holden Engineering and Surveying, Inc. v.
Pembroke Road Realty Trust, 137 N.H. 393, 396 (1993). When the
parties expressly condition their performance upon the occurrence
or non-occurrence of an event, "rather than simply including the
event as one of the general terms of the contract, the parties'
bargained-for expectation of strict compliance should be given
effect." Renovest Co. v. Hodges Dev. Corp., 135 N.H. 72, 78
(1991)
I conclude that the initial payment provision was not a
condition precedent to ikon's promise to perform under the
agreement. Ikon promised to design and develop certain items and
to deliver these items to Enterasys according to a set schedule.
The performance of this promise was not conditioned upon the
receipt of Enterasys' initial payment. See Agreement at 5 2.0.
Indeed, none of the common terms that trigger a condition
precedent are present in the contract language that established
Free access — add to your briefcase to read the full text and ask questions with AI
ikon GmbH v. Enterasys Networks CV-02-98-B 03/05/03
UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE
Ikon GmbH and TEWS Technologies GmbH
v. Civil No. 02-98-B Opinion No. 2003 DNH 031 Enterasvs Networks, Inc.
MEMORANDUM AND ORDER
Enterasys Networks, Inc. entered into an agreement to pay
ikon GmbH to design and develop circuit boards and software.
Under the agreement, ikon's development of the products were
scheduled to begin on the date Enterasys remitted an initial
payment egualing 35% of the total cost of ikon's services.
Although Enterasys never remitted the initial payment, ikon and
its subcontractor, TEWS Technologies GmbH, began working on the
design and development of the circuit boards and software. Ikon
and TEWS have sued Enterasys for breach of contract, seeking to
recover all costs associated with the work it performed under the
agreement. Enterasys moves for summary judgment, alleging that
the initial payment was a condition precedent to ikon's performance under the agreement, and that since it never remitted
the payment a contract was never formed.
I. STANDARD OF REVIEW
Summary judgment is appropriate only "if the pleadings,
depositions, answers to interrogatories, and admissions on file,
together with the affidavits, if any, show that there is no
genuine issue as to any material fact and that the moving party
is entitled to judgment as a matter of law." Fed. R. Civ. P.
56(c). A genuine issue is one "that properly can be resolved
only by a finder of fact because [it] may reasonably be resolved
in favor of either party." Anderson v. Liberty Lobby, Inc., 477
U.S. 242, 250 (1986). A material fact is one that affects the
outcome of the suit. See id. at 248.
In ruling upon a motion for summary judgment, I must
construe the evidence in the light most favorable to the non
movant. See Navarro v. Pfizer Corp., 261 F.3d 90, 94 (1st Cir.
2001). The party moving for summary judgment, however, "bears
the initial responsibility of informing the district court of the
basis for its motion, and identifying those portions of [the
- 2 - record] which it believes demonstrate the absence of a genuine
issue of material fact." Celotex Corp. v. Catrett, 477 U.S. 317,
323 (1986). Once the moving party has properly supported its
motion, the burden shifts to the nonmoving party to "produce
evidence on which a reasonable finder of fact, under the
appropriate proof burden, could base a verdict for it; if that
party cannot produce such evidence, the motion must be granted."
Ayala-Gerena v. Bristol Myers-Sguibb Co., 95 F.3d 86, 94 (1st
Cir. 1996) (citing Celotex, 477 U.S. at 323; Anderson, 477 U.S.
at 249). Neither conclusory allegations, improbable inferences,
or unsupported speculation are sufficient to defeat summary
judgment. See Carroll v. Xerox Corp., 294 F.3d 231, 236-37 (1st
Cir. 2 002).
II. BACKGROUND
According to the agreement, ikon was "to design, have
designed, develop, or have developed" circuit board assemblies
and software. Def's Mem. in support of Mot. for Summ. J., Ex. 1
at 5 2.0 ("Agreement"). In exchange, Entrasys agreed to
compensate ikon for the project according to a payment schedule.
- 3 - Development of the circuit boards and software was scheduled to
start upon the date the first payment of 35% of the total project
costs was made by Enterasys. Agreement at Ex A, n.23(a).
According to Enterasys' director of hardware development, ikon
"would not consider Enterasys to be 'serious' about the
Agreement" until the first payment was received. Hirani Aff. at
5 3. Furthermore, ikon apparently insisted that it would not
begin the project until it received the first payment. Id. at 5
7.
About a month after entering the agreement, Enterasys
concluded that ikon would not be able to complete the project
according to the delivery schedule in the agreement.
Subseguently, Enterasys notified ikon that it would not remit the
first payment and, therefore, it considered the agreement void.
Although it did not receive the first payment, ikon had
already begun designing and developing the circuit boards and
software. Further, it had sought and received approval from
Enterasys to hire TEWS as a subcontractor. After Enterasys
notified ikon that it would not remit the initial payment and
considered the contract void, ikon and TEWS initiated this action
- 4 - seeking to recover damages for the work they had completed.
III. DISCUSSION
A. The initial payment
Enterasys argues that ikon's promise to perform under the
Agreement was conditioned upon the receipt of Enterasys' initial
payment. Enterasys concludes that since it did not remit the
payment, this condition precedent was not satisfied and an
agreement was never formed.
The interpretation of contracts is a guestion of law for the
court to decide. Strafford Tech., Inc. v. Camcar, 147 N.H. 174,
(2001). When interpreting a written contract, I must "read the
document as a whole and give its terms their reasonable meaning."
Id. This remains true for contractual terms that establish
conditions precedent. However, "[a]s a general rule, conditions
precedent are not favored, and [I] will not so construe such
conditions unless reguired by the plain language of the
agreement." In re Estate of Kelly, 130 N.H. 773, 781 (1988).
Conditions precedent "'are those facts and events, occurring
subseguently to the making of a valid contract, that must . . .
- 5 - occur before there is a right to . . . performance.'" Id. at 781
(quoting 3A A. Corbin, Corbin on Contracts 628, at 16 (I960)).
"As a rule of thumb, provisions which commence with words such as
'if,' 'on condition that,' 'subject to' and 'provided' create
conditions precedent." Holden Engineering and Surveying, Inc. v.
Pembroke Road Realty Trust, 137 N.H. 393, 396 (1993). When the
parties expressly condition their performance upon the occurrence
or non-occurrence of an event, "rather than simply including the
event as one of the general terms of the contract, the parties'
bargained-for expectation of strict compliance should be given
effect." Renovest Co. v. Hodges Dev. Corp., 135 N.H. 72, 78
(1991)
I conclude that the initial payment provision was not a
condition precedent to ikon's promise to perform under the
agreement. Ikon promised to design and develop certain items and
to deliver these items to Enterasys according to a set schedule.
The performance of this promise was not conditioned upon the
receipt of Enterasys' initial payment. See Agreement at 5 2.0.
Indeed, none of the common terms that trigger a condition
precedent are present in the contract language that established
either the parties responsibilities under the Agreement or the
- 6 - schedule for the development and delivery of the circuit boards
and software. See id.; c f. Holden Engineering and Surveying,
Inc., 137 N.H. at 396.
Furthermore, the language of the agreement's delivery
schedule referred to in paragraph 2.0 of the agreement merely
establishes the date ikon was to receive Enterasys' initial
payment as the starting date of development. See Agreement at
Ex. A, n.23(a). This starting date may have been critical to the
agreed upon schedule for delivery of services, but it was not a
condition precedent to ikon's actual promise to perform. In
other words, the terms of the contract regarding the starting
date of development are more akin to general contract terms
regarding the delivery of services, rather than express terms
conditioning performance on the occurrence or non-occurrence of
an event. See Renovest, 135 N.H. at 78. In short, ikon's
promise to perform was not expressly subject to the receipt of
the initial payment. Therefore, according to the plain language
of the agreement, I cannot conclude that the initial payment
provision was a fact or event that had to occur before triggering
ikon's duty to perform under the agreement.
- 7 - B. Third Party Beneficiary Status of TEWS
Enterasys also moves for summary judgement as to TEWS' claim
that it is a third-party beneficiary to the agreement between
Enterasys and Ikon. Enterasys argues that TEWS was a
subcontractor hired by ikon, not a third party beneficiary to the
agreement between ikon and Enterasys. As such, Enterasys
concludes that TEWS has no cause of action directly against
Enterasys, and must pursue any alleged claim against ikon. Ikon
counters that ikon and TEWS entered into a "joint venture" with
Enterasys, and that Enterasys expressly granted ikon permission
to hire TEWS as a subcontractor, as called for under the
agreement. As such, TEWS was a third-party beneficiary entitled
to maintain a cause of action directly against Enterasys.
A third-party beneficiary relationship exists if (1) the
contract reguires the promisor to satisfy an obligation owed by
the promisor to a third party; or (2) the contract gives the
promisor reason to know that the promisee has entered into the
agreement, at least in part, in order to benefit a third party.
Arlington Trust Co. v. Estate of Wood, 123 N.H. 765, 767-68
(1983). In either event, the parties must contract with an intent to confer rights upon the third party. Tamposi Assocs.,
Inc. v. Star Market Co., Inc., 119 N.H. 630, 633 (1979).
The agreement in this case was solely between ikon and
Enterasys. Nothing in the agreement indicates that TEWS was
intended as a third-party beneficiary to the agreement. Thus, it
is clear that the parties did not intend to confer a benefit upon
TEWS. See Hrushka v. State of N.H., 117 N.H. 1022, 1024 (1977);
Tamposi, 119 N.H. at 633. TEWS cannot sustain a claim against
Enterasys as a third-party beneficiary.
IV. CONCLUSION
For the foregoing reasons, I deny Enterasys summary judgment
motion (Doc. No. 9) as it pertains to ikon, and grant Enterasys
motion as it pertains to TEWS.
SO ORDERED.
Paul Barbadoro Chief Judge
March 5, 2003
cc: Russell Hilliard, Esg. Charles Szypszak, Esg.
- 9 -