The Sherwin-Williams Company v. Power Engineers, Inc. et al.

District Court, N.D. Ohio·Decided July 31, 2026·No. 1:25-cv-02100·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF OHIO

The Sherwin-Williams Company, Case No. 1:25CV2100

Plaintiff,

-vs- JUDGE PAMELA A. BARKER

Power Engineers, Inc. et al.,

Defendants. MEMORANDUM OPINION & ORDER

Currently pending is Defendant Bobcat Heavy Civil, LLC’s (hereinafter “Bobcat”) Motion for Judgment on the Pleadings and Alternative Motion to Transfer Venue. (Doc. No. 3.) Plaintiff The Sherwin-Williams Company (“Sherwin-Williams”) filed a Brief in Opposition on January 29, 2026, to which Bobcat replied on March 6, 2026. (Doc. Nos. 11, 13.) For the following reasons, Bobcat’s Motion for Judgment on the Pleadings and Alternative Motion to Transfer Venue (Doc. No. 3) is GRANTED IN PART as set forth herein. I. Factual Allegations A. Sherwin-Williams enters into an Environmental Services Agreement with Defendant Power Engineers, Inc. in 2020

The Complaint sets forth the following factual allegations. (Doc. No. 1-1 at PageID#s 8-21.) Sherwin-Williams is an Ohio corporation with its principal place of business in Cleveland, Ohio. (Id. at ¶ 2, PageID# 9.) This matter involves a construction project at a Sherwin-Williams facility on West Miller Road in Garland, Texas (hereinafter “Garland Facility”). (Id. at ¶ 1, PageID# 8.) On March 25, 2020, Defendant Power Engineers, Inc. (“Power”) submitted a proposal to Sherwin-Williams to conduct “an evaluation of the stormwater drainage and spill retention infrastructure” at the Garland Facility (hereinafter “Power March 2020 Proposal”). (Id. at ¶ 9, PageID# 10.) A copy of the Power March 2020 Proposal is attached to the Complaint as Exhibit B. (Id. at PageID#s 37-46.) Power is an Idaho corporation located in Meridian, Idaho. (Id. at ¶ 3, PageID# 9.) See also Doc. No. 8 at ¶ 3, PageID# 156. In the Power March 2020 Proposal, Power proposed “to approach the project using a phased methodology, allowing [it] to develop cost estimates based on information gathered during each

stage.” (Id. at ¶ 10, PageID# 10.) Power proposed the following four (4) different phases of work: (1) Phase 1: Document review, site work, and work planning; (2) Phase 2: Site surveys, subsurface investigation, and assessment reporting; (3) Phase 3: Conceptual engineering analysis and bid document preparation; and (4) Phase 4: Construction oversight. (Id.) Based on Power’s proposal, as well as further discussions and negotiations, Sherwin-Williams and Power entered into an Environmental Services Agreement (hereinafter “Power ESA”) on August 19, 2020. (Id. at ¶ 11, PageID# 10.) A copy of the Power ESA is attached to the Complaint as Exhibit A. (Id. at PageID#s 23-35.) The “Scope of Work” outlined in the Power March 2020 Proposal was incorporated by reference into the ESA. (Id. at ¶ 11, PageID#s 10, 23.) In addition, the Power ESA contains the following provision regarding venue and jurisdiction:

The parties agree that any disputes arising under this Agreement shall be litigated in the State of Ohio, and for that purpose both parties agree to submit to the venue and jurisdiction requirements of the state or federal courts having jurisdiction over the county of Cuyahoga in the State of Ohio. The validity, interpretation and performance of this Agreement shall be governed and construed in accordance with the Laws of the State of Ohio. ***

(Id. at PageID# 33.) Between August 19, 2020 and early 2022, Power completed the first three phases outlined in the Power March 2020 Proposal. (Id. at ¶ 12, PageID# 10.) Phase 3 consisted of Power preparing a 2 Request for Proposal (“RFP”) and coordinating up to three (3) potential vendors for competitive bidding to complete the actual construction and site work. (Id. at ¶ 13, PageID#s 10-11.) At some point during this time period, Power issued an RFP on Sherwin-Williams’ behalf for the Garland Facility. (Id. at ¶ 15, PageID# 11.) Sherwin-Williams paid Power for its completion of Phases 1-3, as outlined in the ESA and Scope of Work proposal. (Id. at ¶ 14, PageID# 11.) B. Bobcat submits a proposal to Power and Power submits its own Proposal to Sherwin-Williams for Phase IV of the Garland Facility Project

Bobcat is located in Texas and all of its members reside in Texas. (Id. at ¶ 4, PageID# 9.) On March 4, 2022, Bobcat submitted a proposal to Power to complete the project at the Garland Facility (hereinafter “Bobcat March 2022 Proposal”). (Id. at ¶ 15, PageID# 11.) A copy of the Bobcat March 2022 Proposal is attached to the Complaint as Exhibit C. (Id. at PageID#s 49-56.) “In its proposal, and during negotiations between the parties, Bobcat represented to Power and Sherwin-Williams that it had prior experience constructing stormwater drainage and spill retention infrastructure.” (Id. at ¶ 17, PageID# 11.) Specifically, in its Proposal, Bobcat represented that it “is a capable partner for electric utility site development and infrastructure construction” and that it “provides construction services with [the] highest level of quality control.” (Id. at PageID#s 52, 54.) Bobcat further represented that it had “diligently analyzed the project scope of work, plans, specifications, and guidelines to ensure that we have developed a sound plan to construct the project according to lines, grades and specifications provided in the bid and construction documents safely, without harming the public, employees or the environment.” (Id. at PageID# 52.) The total bid amount in the Bobcat March 2022 Proposal was $1,106,370.50. (Id. at PageID# 49.)

Shortly thereafter, on March 16, 2022, Power submitted its own proposal detailing additional work and related fees to Sherwin-Williams outlining how it would complete Phase IV of the Power 3 ESA (hereinafter “Power March 2022 Proposal”). (Id. at ¶ 22, PageID# 12.) A copy of the Power March 2022 Proposal is attached to the Complaint as Exhibit E. (Id. at PageID#s 106-109.) Under this Proposal (which Sherwin-Williams alleges is incorporated into the Power ESA), Power agreed to complete several tasks pertaining to “Construction Oversight.” (Id. at ¶ 23, PageID# 12.) These tasks included the following: (1) Task 1: Site Design Review and City of Garland Site Permit; (2) Task 2: TPDES Construction General Permit; (3) Task 3: Contractor Management Support; (4) Task

4: Construction Oversight; and (5) Task 5: Status Meetings. (Id. at ¶ 24, PageID# 12.) See also id. at PageID#s 107-108. As part of Task 3 (“Contractor Management Support”), Power agreed to do the following: POWER will provide Management Support to Sherwin-Williams in managing the selected construction contractor. This support will include:

• Review Contractor submittals and shop drawings • Respond to Contractor Requests for Information (RFIs) • Review Contractor invoices for accuracy and work scope variances

POWER assumes that Sherwin-Williams will contract directly with and pay invoices submitted by the Contractor. POWER’s role will be to provide clear direction, communicate and liaison between the Contractor and Sherwin-Williams regarding work scope variances, and facilitate the project progress.

(Id. at PageID# 108.) As part of Task 4 (“Construction Oversight”), Power proposed to “provide an engineers’ representative and/or environmental specialist daily during construction activities for up to twenty-five (25) weeks (800 hours).” (Id.) In addition, Power proposed that “oversight of construction crews and activities will be performed; daily activities will be logged; and review of construction actions in relation to engineering designs will be performed.” (Id.) 4 Sherwin-Williams agreed to pay, and did pay, Power a separate fee for the “Contractor Management Support” and “Construction Oversight” tasks outlined in Tasks 3 and 4 of the Power March 2022 Proposal. (Id. at ¶¶ 26, 28, PageID# 13.) C. Sherwin-Williams and Bobcat enter into a Construction Agreement in October 2022

Free access — add to your briefcase to read the full text and ask questions with AI

The Sherwin-Williams Company v. Power Engineers, Inc. et al., (N.D. Ohio 2026).

The Sherwin-Williams Company v. Power Engineers, Inc. et al. (The Sherwin-Williams Company v. Power Engineers, Inc. et al.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Milliken v. Meyer
311 U.S. 457 (Supreme Court, 1941)
International Shoe Co. v. Washington
326 U.S. 310 (Supreme Court, 1945)
World-Wide Volkswagen Corp. v. Woodson
444 U.S. 286 (Supreme Court, 1980)
Burger King Corp. v. Rudzewicz
471 U.S. 462 (Supreme Court, 1985)
Goodyear Dunlop Tires Operations, S. A. v. Brown
131 S. Ct. 2846 (Supreme Court, 2011)
American Greetings Corporation v. Gerald A. Cohn
839 F.2d 1164 (Sixth Circuit, 1988)
Kerry Steel, Inc. v. Paragon Industries, Inc.
106 F.3d 147 (Sixth Circuit, 1997)
Julio E. Roman v. John Ashcroft
340 F.3d 314 (Sixth Circuit, 2004)