The R.R. Gregory Corporation

CourtArmed Services Board of Contract Appeals
DecidedFebruary 6, 2014
DocketASBCA No. 58517
StatusPublished

This text of The R.R. Gregory Corporation (The R.R. Gregory Corporation) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The R.R. Gregory Corporation, (asbca 2014).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of-- ) ) The R.R. Gregory Corporation ) ASBCA No. 58517 ) Under Contract No. DACA31-00-C-0037 )

APPEARANCE FOR THE APPELLANT: Brian Cohen, Esq. Greenburg & Spence, L.L.C. Gaithersburg, MD

APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq. Engineer Chief Trial Attorney Richard P. White, Esq. Engineer Trial Attorney U.S. Army Engineer District, Baltimore

OPINION BY ADMINISTRATIVE JUDGE JAMES ON THE GOVERNMENT'S MOTION TO DISMISS FOR LACK OF JURISDICTION

The government moves to dismiss this appeal for lack of jurisdiction asserting that appellant's claim, submitted more than six years after the government withheld liquidated damages, is barred by the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 7109-7109, statutory limitation period. Appellant opposed the motion, arguing that its claim is timely because it did not accrue until the expiration of the government's time to issue a decision withholding liquidated damages and the government's withholding of liquidated damages, without a final decision, was invalid. The government replied to appellant's opposition, and appellant submitted a sur-reply. We grant the motion and dismiss the appeal.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. The U.S. Army Corps of Engineers (government) awarded Contract No. DACA31-00-C-0037 (the contract) for $6,998,000 to The R.R. Gregory Corporation (Gregory) on 30 September 2000 for construction of a new physical fitness center at Walter Reed Army Medical Center in Washington, DC (R4, tabs 2, 3).

2. The contract incorporated by reference the FAR 52.233-1, DISPUTES (DEC 1998) clause, which stated in relevant part:

(c) "Claim," as used in this clause, means a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to this contract.. .. A voucher, invoice, or other routine request for payment that is not in dispute when submitted is not a claim under the Act.. ..

(d)( 1) ... A claim by the Government against the Contractor shall be subject to a written decision by the Contracting Officer.

and the FAR 52.211-12, LIQUIDATED DAMAGES-CONSTRUCTION (APR 1984) clause, whose~ (a) stated:

If the Contractor fails to complete the work within the time specified in the contract, or any extension, the Contractor shall pay to the Government as liquidated damages [LDs ], the sum of$1,015.00 for each day of delay.

(R4, tab 2 at 6 1, 21)

3. The contracting officer (CO) issued to Gregory a notice to proceed to perform the contract on 13 November 2000, which Gregory received on 17 November 2000, establishing an original contract completion date of 12 November 2001 (R4, tab 4; compl. & answer~ 5).

4. Thirteen of the 34 contract modifications gave Gregory a total of 549 days of time extensions. Bilateral Modification No. P00034 set the final contract completion date of 15 May 2003. (R4, tabs 5-8, 10, 12-13, 15-16, 19, 28-29, 32)

5. Administrative CO (ACO) Jeffrey J. Werner's 12 November 2002 letter to Gregory expressed disappointment with its "lack of progress towards completion" of the contract and stated "that as of 1 December 2002, the Government will withhold from your pay request liquidated damages in the contractually specified amount of $1,015.00 per day" until Gregory demonstrated substantially improved progress (R4, tab 9).

6. The government's 27 January 2003 payment estimate for the period 1 November 2002 through 31 December 2002 withheld $31,465 for 31 days ofLDs (R4, tab 14). Gregory's 18 February 2003 letter to ACO Werner acknowledged receipt of the foregoing payment estimate and disputed the withheld LDs (app. supp. R4, tab 43).

1 Rule 4 page cites are to their Bates numbers.

2 7. The government's 21 May 2003 payment estimate No. 14 for the period 1 January 2003 through 30 April2003 withheld an additional $121,800 in LDs for 120 days, and set forth $153,265 (31 + 120 days x $1,015) total LDs withheld under the contract (R4, tab 17). Gregory's 13 June 2003 letter to ACO Werner acknowledged receipt of that payment estimate, and requested that the LDs be withdrawn due to unadjusted stop work orders and change proposals during the period those LDs were assessed (R4, tab 18).

8. The government's 13 November 2003 payment estimate No. 16 withheld from payment to Gregory $284,200 in LDs for 280 days for the period 25 December 2002 through 30 September 2003 (R4, tab 20). The government's 11 February 2004 payment estimate No. 18 changed the LD withholding to $203,000 for 200 days (R4, tab 23).

9. ACO Werner's 17 February 2004letter to Gregory acknowledged that work under the contract was substantially complete effective 3 October 2003 (R4, tab 24).

10. Gregory's 26 February 2004letter to Mr. Werner stated that the time extension and the time left to be negotiated were unresolved areas (R4, tab 25).

11. Effective 28 July 2004 bilateral Modification No. P00034 extended the contract completion date to 15 May 2003 (R4, tab 32). The government's 4 August 2004 pay estimate No. 19 stated that LDs of$143,115 for 141 days were withheld for the period 16 May through 2 October 2003 (R4, tab 33).

12. By his 28 August 2006 email to Gregory, government engineer Alan Andrysiak stated: "As of this date, the contract shows that work was completed 141 days late. Therefore, I have held out LD's at $1015/day, for a total withholding of$143,115.00, pending any adjustment to the contract completion date that is made during contract close-out." (R4, tab 34)

13. From 2006 to 2010 the parties intermittently discussed time extensions for unadjusted change orders (app. supp. R4, tabs 48-56; app. opp'n, exs. 3-4, 11-14).

14. On 30 September 2011 Gregory requested extensions for change orders Nos. 17051 for 60 days; 17054 for 379 days; 17107 for 2 days; and 17116 for 30 days. Army engineer Drew White (apparently not a CO) denied that request finding that the "latest possible claim accrual dates" for those changes were 8 November 2002, 30 September 2001, 5 November 2003, and 13 November 2003, respectively, and hence the request was submitted more than six years after such dates. (App. opp'n, ex. 16; R4, tab 1 at 2)

3 15. Gregory's 24 August 20 12 letter to the CO submitted a certified claim for the $143,115 in LDs the government had withheld, but for which it had issued no final CO's decision, and requested a CO's decision thereon (R4, tab 1 at 1-3).

16. On 24 January 2013, Gregory appealed to the Board on the basis of a deemed denial of its 24 August 20 12 claim because the CO had neither issued a final decision or indicated when one would be forthcoming.

Relevant Statutes and Regulations

The CDA, 41 U.S.C. § 7103, provides in pertinent part:

§ 7103. Decision by contracting officer

(a) Claims Generally.- (1) Submission of contractor's claims to contracting officer.-Each claim by a contractor against the Federal Government relating to a contract shall be submitted to the contracting officer for a decision. (2) Contractor's claims in writing.-Each claim by a contractor against the Federal Government relating to a contract shall be in writing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
Placeway Construction Corporation v. The United States
920 F.2d 903 (Federal Circuit, 1990)
Systems Development Corp. v. McHugh
658 F.3d 1341 (Federal Circuit, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
The R.R. Gregory Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-rr-gregory-corporation-asbca-2014.