The Oregon v. Pittsburgh & L. A. Iron Co.

55 F. 666, 1893 U.S. App. LEXIS 2010
CourtCourt of Appeals for the Sixth Circuit
DecidedMay 1, 1893
DocketNos. 34 and 35
StatusPublished
Cited by20 cases

This text of 55 F. 666 (The Oregon v. Pittsburgh & L. A. Iron Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Oregon v. Pittsburgh & L. A. Iron Co., 55 F. 666, 1893 U.S. App. LEXIS 2010 (6th Cir. 1893).

Opinion

TAFT, Circuit Judge,

(after stating the facts.) It is contended by appellants that the provisions of the charters that the vessels should make as many trips as possible did not prevent them from towing other vessels on their trips, because it was the custom for a propeller like the Oregon, to tow two, three, and sometimes as many as five, vessels at a time. We do not see how such a custom could affect the construction to be placed, on this contract. It may be very true that propellers of the power and tonnage of the Oregon are in the habit of towing three, four, and five vessels, but they do not always do it. Mr. Harvey Brown, in giving evi[670]*670dence as one experienced in lake transportation, said that he had in his charge three propellers carrying iron ore between Marquette and Michigan, which towed only one vessel. Indeed, appellants’ own witnesses admitted that the number of tows was varied from one to five. It is only reasonable to suppose, therefore, that the intention of the parties to the contract in inserting the stipulation that the vessel should make as many trips as possible was to prevent delays, as well by the towing of other vessels as by other causes. We may infer, from the fact that the two contracts were executed about the same time, and for the same purpose, that the patties expected the propeller named in one to tow the schooner named in the other, although there is no such express provision in either. The Oregon towed the Palms throughout the season. The libelant had full notice of it, and did not object. This is a practical construction' of the contract by the parties that is quite conclusive. The Marsh was not carrying freight for libelant, but she and the Palms seem to have been the regular tows of the Tuttle, the propeller mentioned in the original contract, for which the Oregon was substituted, and there is no denial that the libelant knew she was being towed by the Oregon all summer. The libelant made no objection, and cannot be heard now for the first time to claim that this was a breach of the contract. There is no evidence to show, however, that libelant had any knowledge that the Oregon was towing other vessels, and we are satisfied that, in so far as this extra towage delayed the Oregon and the Palms, and made their trips less numerous, it was a violation of both contracts. It is objected on behalf of the Palms that her owners, who are not all the same as those of the Oregon, should not be responsible for the delay caused by the Oregon’s taking up other tows, because the Palms could not control the propeller’s action. There is no force in the objection. The Palms was under contract to make her trips as fast as possible. We have found from the surrounding circumstances that this meant as fast as possible with another tow and the propeller Oregon. In so far as the Palms’ making the trip without delay depended on the conduct of the steamer, her owners, in effect, agreed that the steamer should do nothing to prevent it. There is nothing unusual or impossible in one person contracting with another that a third person shall do something. But here the case is even stronger, for the managing owner of the Palms and the managing owner of the Oregon were the same person. When he allowed the Oregon to take up other tows in violation of both contracts, he made the owners of the propeller and the schooner both liable for his act, because, as managing owner for the schooner, he necessarily consented to his own conduct as managing owner of the propeller. His was a general agency for the owners of the two vessels, and he represented both sets of owners fully and completely.

The evidence shows that the delay occasioned by towing third vessels was about three quarters of a mile an hour, or 18 miles a day. This would mean a reduction of speed of one eighth. Estimating the time for a half trip, exclusive of the time for loading, as [671]*671six days, though it was often longer, this would amount to a delay of about three fourths of a day for each half trip. There were ten half trips when the Oregon towed a third vessel in addition to the Palms and the Marsh, which made a delay in all, on this account, of seven days and a half. Some effort was made to show that extra tows were only taken up when no delay could occur. The captain of the Oregon said that he only took an extra tow when he calculated ahead, and found he would arrive at Marquette Saturday night, and no unloading could begin until Monday; or when he would arrive at the Sault canal too late to go through until the next morning. It was immaterial in such cases whether he arrived at ldght or the next morning, so far as the time to be consumed in the trip was concerned. The captain could only have referred in this excuse to tows which he took for short trips. The tows counted in the ten half trips we have been considering were towed all the way between Cleveland and Marquette, one way or the other; and it was impossible, with respect to a whole trip, to make such a calculation with any exactness. This excuse is of a piece with the excuse which Gilchrist and his captains offer for the flagrant and deliberate violation of the two contracts in going to Buffalo, and taking thence full up loads' of coal on the Oregon, the Palms, and the Marsh for the ninth trip. They were ready to leave Cleveland on September 15th. Gilchrist went to the secretary of the libelant company, and informed him that he was going to send Ms vessels to Buffalo, to take cargoes of coal from there to Marquette. He was told that this was a violation of bis contract. He intimated that he would do it anyhow. He says that he explained that in the heavy winds that were likely to prevail during the trip which covered the equinoctial season his vessels would make better time if loaded than light, ‘and that on the previous trip up they had been delayed by being blown around by side winds, although the record shows that to have been one of his shortest trips. The libelant objected, and sent a written protest to' Gilchrist. The captains of Ms vessels seek to sustain this explanation as a valid excuse, and argue that, even though a technical violation of the contract, it caused no delay. The district and the circuit courts evidently gave no credence to this claim, and rightly. Harvey Brown, who at this same time sent three propellers and their consorts, not very unlike in draught and tonnage to those of libelant, from Cleveland to Marquette, testifies that they had no difficulty of this kind, and made their trips very promptly. The excuse was late-horn for the purposes of the case. The real reason for taking the coal was that freight rates for coal had risen so much that Gilchrist could make upwards of $1,500 by violating his contract. This is perfectly evident from his conduct in respect to Ms last — the twelfth- — trip, when he again applied to Outhwaite, the secretary of the libelant, to take up a load of coal. Outhwaite’s statement is as follows:

“At first I refused, but be threatened to repudiate these contracts if he was not allowed to take these up loads, saying that he knew he could make more money by breaking these contracts and carrying these up loads of coal than all [672]*672the damages we could recover against Mm by reason of the broach of the contract At that time it was almost impossible to get vessels to carry ore by reason of the great demand for such tonnage, and it was absolutely necessary that we should have the ore to fulfill our contracts with other parties, and for tMs reason I was obliged to yield to Ms demands, and consent to these vessels carrying on this one occasion an up load of coal, as demanded by him.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Western Canada Steamship Co., Ltd. v. United States
245 F.2d 921 (Ninth Circuit, 1957)
Krauss Bros. Lumber v. Dimon Steamship Corp.
290 U.S. 117 (Supreme Court, 1933)
Clarke S. S. Co. v. Munson S. S. Line
59 F.2d 423 (E.D. New York, 1932)
Cheatham v. Wheeling & L. E. Ry. Co.
37 F.2d 593 (S.D. New York, 1930)
Pendleton Bros. v. Pearce
10 F.2d 692 (Second Circuit, 1926)
The Capitaine Faure
10 F.2d 950 (Second Circuit, 1926)
Cooper & Cooper, Inc. v. Cameron
10 F.2d 950 (Second Circuit, 1926)
Rotterdamsche Lloyd v. Gosho Co.
298 F. 443 (Ninth Circuit, 1924)
H. C. Jones & Co. v. Atlantic Transport Co.
284 F. 310 (Fourth Circuit, 1922)
Grimwood v. Munson S. S. Line
273 F. 166 (Second Circuit, 1921)
Hughes v. Chesapeake & Ohio Coal & Coke Co.
269 F. 589 (Third Circuit, 1921)
The A. Denicke
138 F. 645 (Fourth Circuit, 1905)
Wessels v. The Ceres
72 F. 936 (Second Circuit, 1896)
The Oscoda
66 F. 347 (N.D. New York, 1895)

Cite This Page — Counsel Stack

Bluebook (online)
55 F. 666, 1893 U.S. App. LEXIS 2010, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-oregon-v-pittsburgh-l-a-iron-co-ca6-1893.