United States Shipping Board Emergency Fleet Corp. v. Hedden

282 F. 766, 1922 U.S. App. LEXIS 2697
Court of Appeals for the Third Circuit·Decided August 29, 1922·No. No. 2828·Published·Cited by 4 cases

Opinion

DAVIS, Circuit Judge.

This is an appeal from a decree of the District Court allowing a claim of $1,500 against the United States Shipping Board Emergency Fleet Corporation, owner of the tug Mascot, which rammed the Emma K. Reed, hereinafter called the Reed, while lying at Hog Island. The libelant claimed damages of $6,291.37, made up as follows»

Repairs 465.HO
Demurrage, detention of 48 days, at !?100 per day................... 4,800.00
Expense for extra labor in pumping out the boat while performing
government contract............................................ 1,026.07
Total 201.3?

The commissioner to whom the case was referred allowed the first and third items as claimed, but modified the second, by reducing the days to 42 and deducting $12.51, the daily cost of fuel, from each day, so that this item was reduced to $3,674.58, and his total allowance for the original damage of $465.30 was $5,165.95. Exceptions were entered to tírese findings, which were sustained by the learned trial judge, “to the extent of reducing award of damages to $1,500, with costs, in favor of the libelant. The exact ground on which this award was made is not clear. A number of items were eliminated, and, after stating that the basis for finding damages did not dearly appear in the record, but that an award could be made under tire evidence, and that there was no need of prolonging tire long and expensive litigation, the judge o£ the District Court said:

“We end it now, so far as concerns this court, by sustaining the exceptions to the extent of reducing the award of damages to 81.500, and entering judgment for that sum, with costs, in favor of the libelant and against the respondent, by authorising a formal decree to be entered that the respondent pay this sum to the libelant, with costs. In estimating the damages at even this sum, we feel that we have fallen In with the old sentiment, which still lingers, that any catastrophe which befalls a vessel ia a deodand, a veritable gift to the gods, to any one who can get anything out of the event, and that, if payment Is made by government, the blessing should be doubled.”

It may be impossible to make, or even approximate, a mathematically exact award; but this is due to confused and inexact testimony. For an injury to a boat in a collision, all the damages suffered should be paid by the party at fault, if the value of the offending boat and the pending freight for the voyage are sufficient to do so. Section. 4283, Revised Statutes of the United States (Comp. St. § 8021); Norwich Co. v. Wright, 80 U. S. (13 Wall.) 104, 120, 20 L. Ed. 585; Benedict’s Admiralty (4th Ed.) §§ 521, 543, 544. The wrongful act and the [768] measure of the indemnity are not limited by contract, but are coextensive with the damages, including damages for detention of the vessel during the time necessary to make repairs and fit the vessel to resume her work. “ ‘Restitutio in integrum’ is the leading maxim in such cases.” Williamson et al. v. Barrett, 54 U. S. (13 How.) 101, 110, 14 L. Ed. 68; The Baltimore, 75 U. S. (8 Wall.) 377, 385, 19 L. Ed. 463; The Conqueror, 166 U. S. 110, 125, 17 Sup. Ct. 510, 41 L. Ed. 937. While the libelant did not appeal, it is seeking to justify and sustain the allowance made by the commissioner, with a modification of the detention claim. These allowances will be considered in their reverse order.

The first one is the claim of $1,026.07 for the labor of an extra crew alleged to have been necessitated by the leaking of the Reed. The old crew, it is averred, operated the pump, while the new crew handled the lumber. It should be observed that, while the accident occurred July 16, 1918, the Reed continued its regular and daily work throughout the season until that contract with the government was completed. Eibelant then made another contract, on which the Reed worked 7 or 8 days at $100 per day, and no claim whatever was made for damages for the collision, nor negotiation entered into relating to it, until May 23, 1919. In the libel, filed 3 months later, no claim was made for the labor of a new crew. This claim was first intimated at one of the hearings before the commissioner, the first of which began December 30, 1920, and an amended libel was thereafter filed on January 19, 1921, which contained the formal claim. Although the leaking is alleged to have begun at once after the accident, on July 16, 1918, the log does not contain even a hint that the boat leaked until October 9, 1918, sometime after she had been struck on the starboard side in another collision. Since leaking is mentioned once in the Reed’s log—“Started to load Oct. 9 for St. George; leaking”—it is not unreasonable to infer that there would have been some mention of leaking caused by this collision in the log, if she had been leaking so badly as to require an extra crew to keep her pumped out.

Eurther, it does not appear how many persons composed the new crew. There were seven on the boat composing the old crew, which, after the accident, according to the libelant, did not handle any lumber but operated the pump. It appears that only one man at a time worked at the pump, which was not continuously operated, and what the others did while he was pumping is not disclosed. Just when this new crew began to work is not clear. The amount of $1,026.07 is reached by multiplying 610,758 feet of lumber, all the Reed is alleged to have carried for the government on that contract after the accident, by $1.68 per 1,000 feet. Exactly how many feet were actually carried, however, after the accident, is not definitely known. Mr. Harold K. Paxson, half owner of the Reed, said:

“I have figures [which he did not produce] showing the number of feet the boat carried after that on the Hog Island contract was 600,000 feet.”

The extra cost per 1,000 feet for transportation does not seem to have been definitely determined. Mr. Paxson testified that the “average cost for handling lumber was $2, $2.17, or $2.70,” while the claim [769] in the libel, adopted by the commissioner, is based on a cost of $1.68 per 1,000. How libelant worked out the basis of $1.68, different from any one of the three average costs, is not disclosed.

The burden is on the libelant to establish that the services of an entire new crew to handle the lumber was made necessary by using the entire old crew forpumping, and this burden has not been sustained to our satisfaction. The claim is clothed with such doubt and is so indefinite that it must be disallowed.

Free access — add to your briefcase to read the full text and ask questions with AI

United States Shipping Board Emergency Fleet Corp. v. Hedden, 282 F. 766, 1922 U.S. App. LEXIS 2697 (3d Cir. 1922).

282 F. 766 (United States Shipping Board Emergency Fleet Corp. v. Hedden) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Royston Distributors, Inc. v. Moore-McCormack Lines, Inc.
252 F. Supp. 480 (E.D. Pennsylvania, 1965)
Atkins v. Alabama Drydock & Shipbuilding Company
195 F. Supp. 944 (S.D. Alabama, 1960)
W. B. Moses & Sons v. Lockwood
295 F. 936 (District of Columbia, 1924)