The Internat. Brotherhood of Boilermakers etc. v. NASSCO etc.

CourtCalifornia Court of Appeal
DecidedNovember 30, 2017
DocketD070620
StatusPublished

This text of The Internat. Brotherhood of Boilermakers etc. v. NASSCO etc. (The Internat. Brotherhood of Boilermakers etc. v. NASSCO etc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Internat. Brotherhood of Boilermakers etc. v. NASSCO etc., (Cal. Ct. App. 2017).

Opinion

Filed 11/30/17

CERTIFIED FOR PUBLICATION

COURT OF APPEAL, FOURTH APPELLATE DISTRICT

DIVISION ONE

STATE OF CALIFORNIA

THE INTERNATIONAL BROTHERHOOD D070620 OF BOILERMAKERS, IRON SHIP BUILDERS, BLACKSMITHS, FORGERS AND HELPERS, LOCAL 1998 et al., (Super. Ct. No. Plaintiffs and Respondents, 37-2014-00041656-CU-OE-CTL)

v.

NASSCO HOLDINGS INC. et al.,

Defendants and Appellants.

APPEAL from a judgment of the Superior Court of San Diego County, John S.

Meyer, Judge. Affirmed.

Morrison & Foerster, James R. Sigel, Miriam A. Vogel; Morgan Lewis & Bockius

and Jason Scott Mills for Defendants and Appellants.

U.S. Chamber Litigation Center, Janet Galeria; California Manufacturers &

Technology Association, Dorothy E. Rothrock; Munger, Tolles & Olson, Fred A.

Rowley, Jr., and Aaron D. Pennekamp for Chamber of Commerce of the United States of

America, National Association of Manufacturers, California Manufacturers & Technology Association, and Shipbuilders Council of America as Amici Curiae on behalf

of Defendants and Appellants.

Klapach & Klapach, Joseph S. Klapach; Kelley Semmel and Amy Semmel for

Plaintiffs and Respondents.

Under a California law known as the California WARN Act, employers must

provide 60 days' notice to affected employees before ordering a "mass layoff." (Lab.

Code, § 1400 et seq.)1 A labor union and several employees sued an employer, alleging

the employer violated this law by failing to provide notice before ordering about 90

employees not to return to work for four to five weeks. The employer countered that the

California WARN Act was inapplicable because its action was a temporary furlough and

not a "mass layoff." All parties recognized there was no liability under the parallel

federal WARN Act because the federal law applies to a temporary layoff only if the

layoff "exceed[s] 6 months." (29 U.S.C. § 2101(a)(6)(B).)

The parties filed cross summary judgment/adjudication motions raising primarily

the duty issue: did the employer have a statutory duty to notify the affected employees

even though the layoff was temporary, rather than permanent? The superior court

concluded the California WARN Act did apply to the employer's temporary layoff, and

therefore the employer owed a statutory notification duty to the affected workers. The

court thus granted summary adjudication in plaintiffs' favor on this issue. The court then

1 All unspecified statutory references are to the Labor Code. WARN stands for Worker Adjustment and Retraining Notification Act. (MacIsaac v. Waste Management Collection & Recycling, Inc. (2005) 134 Cal.App.4th 1076, 1078 (MacIsaac).) 2 held a one-day bench trial on damages issues. After trial, the court entered judgment in

plaintiffs' favor, awarding the workers $211,405 in backpay and lost pension benefits.

The court denied plaintiffs' request for statutory penalties, finding the employer acted in

good faith because the legal issues were "unsettled."

On appeal, the employer contends the court erred in interpreting the California

WARN Act as applying to temporary layoffs. We affirm. Based on our analysis of the

statutory language, statutory scheme, legislative history, federal WARN law, and policies

underlying the California WARN Act, we determine the employer had a duty to provide

statutory notice under the particular circumstances of this case, even if the layoffs were

not permanent and were for less than six months.

FACTUAL AND PROCEDURAL BACKGROUND2

NASSCO Holdings Incorporated and National Steel and Shipbuilding Company

(collectively NASSCO) employs thousands of workers in its ship building and repairing

business. NASSCO employees are represented by The International Brotherhood of

Boilermakers, Iron Ship Builders, Blacksmiths, Forgers, and Helpers, Local 1998 (the

Union). NASSCO's staffing requirements change frequently, and its collective

bargaining agreement contains rules applicable to terminations and short-term unpaid

work stoppages. The agreement refers to a short-term work stoppage as a "layoff."

2 Because the appeal concerns solely the court's summary adjudication and summary judgment rulings, we consider only the evidence before the court when it made these rulings. To the extent the parties discuss evidence presented at the later trial, this evidence is not properly before us. 3 By early 2014, NASSCO determined it would need to temporarily reduce its labor

force because there would be a lull in its shipyard production work. On March 3, 2014,

NASSCO notified about 14 employees on the day they reported to work that they were

not to return to work for at least three weeks. The written notice characterized the

reduction as a layoff. NASSCO later notified these employees the layoff would be

extended by several weeks. On March 17, 2014, NASSCO notified about 76 additional

employees they were laid off for at least three weeks. They were not given prior notice

of the layoff.

Between March 3, 2014 and March 17, 2014, a total of about 90 NASSCO

employees were laid off, without work or pay (except for the reporting time pay on the

day they were told not to return to work) for three to five weeks. Some of the laid-off

employees returned to work on April 7, 2014, with the remainder returning on April 14,

2014. When the workers returned to work, they returned to their same job classifications.

On March 17, 2014, the Union president wrote to NASSCO, claiming NASSCO's

action in laying off more than 50 workers within a 30-day period triggered statutory

notice protections. Later that day, NASSCO responded that it had not implemented a

"layoff," and instead it was a "furlough[]" or a "manpower reduction," and that under the

federal WARN Act, notice is not required "when the layoffs are for less than a 6 month

period." NASSCO said it was aware of the impact the "furloughs may have on its

employees. Therefore, . . . NASSCO has continued to extend certain benefits to these

furloughed employees," including that it has "1) continued to pay BOTH the employer

4 contribution AND the employee portion of the health care premiums; and 2) allowed

employees to continue to accrue seniority."

Despite the representation regarding the health care premiums, the workers were

initially charged for and paid their own health care obligations. However, they were later

reimbursed for these payments. During their time off, the employees were not paid any

wages (except for a few workers who elected to use their accrued vacation wages), nor

did they earn vacation pay or accrue service credit for purposes of pension benefits.

In December 2014, the Union and three individual employees (Alberto Florian,

Gustavo Perez, and Jose Rodarte) sued NASSCO alleging it violated the California

WARN Act and seeking back pay and millions of dollars in statutory penalties.

Plaintiffs moved for summary judgment/adjudication claiming the undisputed

facts showed NASSCO (1) had a statutory duty under the California WARN Act to give

60 days' notice before the March 2014 layoffs; (2) breached that duty; and (3) failed to

conduct a reasonable investigation into whether its actions would violate the California

WARN Act. In its cross-motion, NASSCO argued the undisputed facts showed (1) it had

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Collins v. Gee West Seattle LLC
631 F.3d 1001 (Ninth Circuit, 2011)
Brinker Restaurant Corp. v. Superior Court
273 P.3d 513 (California Supreme Court, 2012)
Continental Casualty Co. v. Phoenix Construction Co.
296 P.2d 801 (California Supreme Court, 1956)
North Bay Regional Center v. Maldonado
241 P.3d 840 (California Supreme Court, 2010)
Dieckmann v. Superior Court of Los Angeles County
175 Cal. App. 3d 345 (California Court of Appeal, 1985)
Duty v. Abex Corp.
214 Cal. App. 3d 742 (California Court of Appeal, 1989)
JR Norton Co. v. GENERAL TEAMSTERS, WAREHOUSEMEN
208 Cal. App. 3d 430 (California Court of Appeal, 1989)
MacIsaac v. Waste Management Collection & Recycling, Inc.
36 Cal. Rptr. 3d 650 (California Court of Appeal, 2005)
Professional Engineers in California Government v. Schwarzenegger
239 P.3d 1186 (California Supreme Court, 2010)
San Bernardino Valley Audubon Society v. City of Moreno Valley
44 Cal. App. 4th 593 (California Court of Appeal, 1996)
Pineda v. Williams-Sonoma Stores, Inc.
246 P.3d 612 (California Supreme Court, 2011)
Day v. City of Fontana
19 P.3d 1196 (California Supreme Court, 2001)
State v. Altus Finance, S.A.
116 P.3d 1175 (California Supreme Court, 2005)
Microsoft Corp. v. Franchise Tax Board
139 P.3d 1169 (California Supreme Court, 2006)
Lee v. Hanley
354 P.3d 334 (California Supreme Court, 2015)
Fluor Corporation v. Super. Ct.
354 P.3d 302 (California Supreme Court, 2015)
Brown v. Superior Court of Sacramento County
371 P.3d 223 (California Supreme Court, 2016)
Stuart Day v. Celadon Trucking Services, Inc
827 F.3d 817 (Eighth Circuit, 2016)
City of San Jose v. Superior Court of Santa Clara Cnty.
389 P.3d 848 (California Supreme Court, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
The Internat. Brotherhood of Boilermakers etc. v. NASSCO etc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-internat-brotherhood-of-boilermakers-etc-v-nassco-etc-calctapp-2017.