The City of Fort Wayne v. Consolidated Electrical Distributors, Inc d/b/a All-Phase Electric Supply Co.

998 N.E.2d 733, 2013 WL 6091704, 2013 Ind. App. LEXIS 577
CourtIndiana Court of Appeals
DecidedNovember 20, 2013
Docket02A04-1306-CC-283
StatusPublished
Cited by2 cases

This text of 998 N.E.2d 733 (The City of Fort Wayne v. Consolidated Electrical Distributors, Inc d/b/a All-Phase Electric Supply Co.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The City of Fort Wayne v. Consolidated Electrical Distributors, Inc d/b/a All-Phase Electric Supply Co., 998 N.E.2d 733, 2013 WL 6091704, 2013 Ind. App. LEXIS 577 (Ind. Ct. App. 2013).

Opinion

OPINION

VAIDIK, Judge.

Case Summary

This case arises from a light-installation project on Courthouse Green, a park owned by the city of Fort Wayne ("the City"). Consolidated Electrical Distributors, Inc., otherwise known as All-Phase Electrical Supply Co. ("All-Phase"), was a subcontractor on the project and supplied thousands of dollars' worth of materials. Though the City paid the general contractor, the general contractor never paid All-Phase.

All-Phase served notice of its unpaid subcontractor's claim on the mayor of Fort Wayne and filed suit against the City, seeking payment. Both parties moved for summary judgment. At issue was All-Phase's compliance with the notice requirements of Indiana Code section 36-1-12-12, which provides a right of recovery to an unpaid subcontractor. The City argued that All-Phase was not entitled to payment because notice was not given within sixty days of the date All-Phase last provided materials and served improperly on the mayor, rather than the parks department. The trial court disagreed and granted summary judgment for All-Phase.

When read in conjunction with relevant statutory provisions, we conclude that Seetion 36-1-12-12 allowed All-Phase to serve notice of its unpaid subcontractor's claim on the mayor of Fort Wayne. We also find that All-Phase provided timely notice of its claim. Finding that summary judgment was properly granted for All-Phase, we affirm.

Facts and Procedural History

In November 2010, the Courthouse Green project was awarded to a construction company called Lights & Signals, Inc. ("LSI"). The contract for the project was worth $85,990. All-Phase was a subcontractor on the project and supplied $24,050.71 worth of materials to LSI. Though the City paid LSI ninety-five percent of the contract price, LSI never paid All-Phase. LSI ultimately stopped doing business and declared bankruptcy.

In April 2011, All-Phase sent notice of LSI's nonpayment to the mayor of Fort Wayne, Thomas C. Henry. An attorney for the City responded to the notice and advised All-Phase that the City had paid LSI the full contract price, minus a small amount in retainage. The City declined to pay All-Phase any amounts owed.

All-Phase filed suit against the City and issued requests for admissions. In its response, the City made the following admission:

REQUEST NO. 4: Admit that during the period from on or about December 14, 2010, through February 7, 2011, ALL-PHASE supplied $24,050.71 worth of materials to LSI for construction of the Project on the City's Real Estate.
RESPONSE: Admit.

*736 Appellant's App. p. 82 (emphasis added). The City also admitted that it received All-Phase's notice of claim on April 6, 2011. Id.

Both parties filed summary-judgment motions. At issue was All-Phase's compliance with the notice requirements of Indiana Code section 36-1-12-12, which provides a right of recovery to an unpaid subcontractor. All-Phase's designated evidence included the affidavit of its Credit Manager, Jay Orchard. In his affidavit, Orchard confirmed that All-Phase provided materials to LSI from December 14, 2010, through February 7, 2011. In paragraph 8 of his affidavit, he also confirmed that notice of All-Phase's claim was sent to the mayor on April 6, 2011, "which was 58 days after [All-Phase] supplied the last of the materials for the project." Id. at 60. The City moved to strike paragraph 8, but the trial court denied the City's motion.

After a hearing, the trial court granted summary judgment for All-Phase. The City now appeals.

Discussion and Decision

On appeal, the City contends that the trial court erred by granting summary judgment for All-Phase. The City argues that All-Phase improperly served notice of its claim on the mayor of Fort Wayne. The City also claims that All-Phase gave untimely notice of its claim.

Summary judgment is only appropriate when the moving party affirmatively shows that there are no genuine issues of material fact with regard to a particular issue or claim. See Ind. Trial Rule 56(C); Holiday Hospitality Franchising, Inc. v. AMCO Ins. Co., 983 N.E.2d 574, 577 (Ind.2013) (citing Town of Avon v. W. Cent. Conservancy Dist., 957 N.E.2d 598, 602 (Ind.2011)). The non-moving party then bears the burden of producing designated evidence showing the existence of a genuine issue of material fact. Holiday, 983 N.E.2d at 577.

"An appellate court reviews these cases through the same lens, and we view all designated evidence and reasonable inferences in a light most favorable to the non-moving party; any doubts are resolved against the moving party." Id. We will affirm a trial court's grant of summary judgment on any theory supported by the record. Id. (citing Woodruff v. Ind. Famity & Soc. Servs. Admin., 964 N.E.2d 784, 790 (Ind.2012)). When the facts are not disputed, reversal is only appropriate if the trial court incorrectly applied the law to those facts. Id.

I. Notice Properly Served

The City first claims that All-Phase improperly served notice of its claim on the mayor of Fort Wayne. All-Phase argues that the relevant statutory provisions allow it to serve notice on the mayor. All-Phase's argument is based on its reading of the provisions in Title 36 of the Indiana Code.

Indiana Code section 36-1-12-12 provides a right of recovery to an unpaid subcontractor. However, in order for a subcontractor to receive payment, the subcontractor "must file a claim with the board not later than sixty (60) days after that person performed the last labor, furnished the last material, or performed the last service...." Ind.Code § 36-1-12-12(b) {(emphasis added). According to the definitions section of the chapter, " 'board' means the board or officer of a political subdivision or an agency having the power to award contracts for public work." Ind. Code § 36-1-12-1.2(1) (emphasis added).

A "political subdivision" is a municipal corporation or special taxing district. Ind. *737 Code § 86-1-2-13. 1 Elsewhere in Title 36, Article 1, "municipal corporation" is defined as, among other things, a unit. Ind.Code § 36-1-2-10. "Unit," in turn, means a county, municipality, or township. Ind.Code § 36-1-2-23. Finally, a "municipality" is defined as a city or town. Ind. Code § 36-1-2-11.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
998 N.E.2d 733, 2013 WL 6091704, 2013 Ind. App. LEXIS 577, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-city-of-fort-wayne-v-consolidated-electrical-distributors-inc-dba-indctapp-2013.