THE CHOWNS GROUP, LLC v. Grimberg Co., Inc.

CourtDistrict Court, E.D. Pennsylvania
DecidedJanuary 30, 2024
Docket2:22-cv-02238
StatusUnknown

This text of THE CHOWNS GROUP, LLC v. Grimberg Co., Inc. (THE CHOWNS GROUP, LLC v. Grimberg Co., Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
THE CHOWNS GROUP, LLC v. Grimberg Co., Inc., (E.D. Pa. 2024).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF PENNSYLVANIA

THE CHOWNS GROUP, LLC : CIVIL ACTION : v. : : JOHN C. GRIMBERG CO., INC., : STEVEN J. GRIMBERG, HENRY : DANFORTH, JAMES L. GRAHAM, : NO. 22-2238 and JERRY ELMORE

MEMORANDUM OPINION Savage, J. January 30, 2024 Seeking to transform a construction contract dispute into a False Claims Act action, The Chowns Group, LLC (“Chowns”), a subcontractor on a government project, brings this qui tam action against the general contractor. It accuses John C. Grimberg Co., Inc. (“Grimberg”),1 the general contractor, of submitting false claims to the government for payment for defective work that was not in compliance with the contract specifications and industry standards. It asserts that Grimberg terminated the subcontract in retaliation for complaining about the construction defects to the government. Chowns includes state law claims for wrongful termination, commercial defamation, breach of contract, fraud, and fraudulent inducement. Defendants move to dismiss all counts,2 except Count IV, commercial defamation. They argue that Chowns has failed to state a claim under the False Claims Act upon which relief can be granted under Federal Rule of Civil Procedure 12(b)(6) and has failed

1 Chowns also names as defendants Steven J. Grimberg, President and Owner of Grimberg; Henry Danforth, Grimberg’s General Counsel; James L. Graham, Senior Vice President of Grimberg; and Jerry Elmore, Grimberg’s project manager. 2 The government declined to intervene on January 23, 2023. The United States’ Notice of Election to Decline Intervention, ECF No. 9. to plead fraud with sufficient particularity under Federal Rule of Civil Procedure 9(b). Defendants also argue that Chowns has no standing to assert a retaliation cause of action under 31 U.S.C. § 3730(h) because the statute protects only individual employees, contractors, or agents. Even if it had standing, the defendants contend, Chowns did not engage in protective conduct. Grimberg moves to compel arbitration of the state law

claims as mandated by the contract. We conclude that Chowns’ allegations show that the defendants’ certifications in the bills submitted to the government that the work satisfied contract specifications were not material to the government’s decision to pay. The retaliation claim fails because Chowns lacks standing to assert an FCA retaliation claim; and even if it had standing, its complaints of construction defects did not constitute protected conduct. Consequently, Chowns has failed to state an FCA violation. The state law claims, except defamation, are subject to arbitration pursuant to the contract. Therefore, we shall dismiss the FCA claims, decline to exercise supplemental jurisdiction over the state law defamation claim,

and compel arbitration of the remaining state law claims. Background3 The United States contracted with Grimberg to build a new school building on the Marine Corps Base in Quantico, Virginia (“Quantico Project”).4 The project was overseen and funded by Naval Facilities Systems Engineering Command.5 In response to a

3 The facts are recited from the allegations in the First Amended Complaint. We accept them as true and draw all reasonable inferences from them in favor of Chowns. 4 First Am. Compl. ¶¶ 2, 27, ECF No. 25 [“Compl.”]. We refer to Grimberg’s contract with the government as the Prime Contract. 5 Id. ¶ 4. request for bids,6 Chowns submitted a bid for steel work.7 On January 12, 2018, it entered into a subcontract with Grimberg to provide labor and materials for the structural steel work.8 The subcontract called for completion of construction by January 11, 2020.9 Chowns began supplying steel to Grimberg in September 2019.10 Construction on the Quantico Project was delayed throughout 2019 due to soil

conditions and leaking underground fuel storage tanks.11 Chowns attributes additional delays to “Grimberg Co.’s poor supervision of the work of other subcontractors.”12 During this period, Chowns delivered multiple loads of steel.13 Some were turned away, forcing Chowns to pay for storage for the unloaded steel.14 Others remained on trailers for twelve months due to delays and issues with the foundation walls upon which the steel was to be erected.15 Sometime before April 2020, Chowns alerted Grimberg to construction defects, including deficiencies in the concrete, foundations, and the Insulated Concrete Form (ICF) wall system.16 Chowns informed the on-site government representative of the defects, identifying incorrect elevations and missing pockets and bearing plates.17

6 Id. ¶ 43. 7 Id. ¶ 44. 8 Id. ¶¶ 20, 24, 26. 9 Id. ¶ 36. 10 Id. ¶ 25. 11 Id. ¶¶ 31-32. 12 Id. ¶ 38, n.1. 13 Id. ¶ 33. 14 Id. ¶ 34. 15 Id. ¶ 33. 16 Id. ¶¶ 41, 50. 17 Id. ¶ 53. James Graham, Senior Vice President, contacted Chowns and threatened to bar anyone talking to the government from the job.18 Chowns discussed the construction concerns with Steven Grimberg, President and Owner of Grimberg Co., and Henry Danforth, Grimberg’s General Counsel.19 Grimberg directed Chowns to fix the elevation errors, missing bearing plates and

embeds, and mislocated pockets in the ICF walls needed to connect to or support the steel.20 Jerry Elmore, Grimberg’s project manager, instructed Chowns to use shims to fill in gaps that exceeded four inches.21 Grimberg issued a change order authorizing the purchase of a pallet of shims to use in correcting the defects.22 Grimberg also complained to the bar joist supplier, insisting that the bar joists were not fabricated properly.23 Grimberg later learned that the joists were built to specification and the problem was that the wall was not constructed at the proper elevation.24 Danforth “began a rushed campaign to get the out-of-specification work completed and thereby covered up.”25 Grimberg demanded additional crews working overtime to fix the errors.26

To make up for delays, Grimberg continued construction during the COVID-19 lockdown from mid-March through April 2020.27 It directed Chowns to fabricate and

18 Id. 19 Id. ¶ 55. 20 Id. ¶ 51. 21 Id. ¶ 54. 22 Id. 23 Id. ¶ 57. 24 Id. 25 Id. ¶ 58. 26 Id. ¶ 59. 27 Id. ¶ 38. deliver steel.28 Chowns could not force its employees to work at its Pennsylvania location or go to the Quantico Project without violating the Governor of Pennsylvania’s order requiring non-essential businesses, including construction, to cease operations.29 On April 28, 2020, Grimberg terminated the subcontract with Chowns.30 Chowns asserts that Grimberg terminated the subcontract because Chowns had complained to

Grimberg about the workmanship defects and planned to relay information to the government.31 On June 3, 2020, Chowns’ attorney sent a letter containing a “Statement of Construction Defects” to Soledad P. Credo, Contracting Officer and Supervisory Contract Specialist.32 The letter asserted that Grimberg did not perform the work in accordance with the plans and specifications, and in a good and workmanlike manner.33 It detailed defects that it warned could result in catastrophic collapse, causing injury to property and persons.34 The Navy investigated the Quantico Project and discovered that vertical rebars

had been installed inside the horizontal rebars, causing the vertical rebars to drift inward toward the middle of the ICF walls during the concrete pours of the ICF walls.35 As a result, the ICF wall system was structurally deficient.36

28 Id. 29 Id. ¶¶ 38-39. 30 Id. ¶¶ 40, 104. 31 Id. ¶ 105. 32 Id. ¶ 63. 33 Id. ¶ 64. 34 Id. 35 Id. ¶ 68. 36 Id. ¶ 69.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rex Trailer Co. v. United States
350 U.S. 148 (Supreme Court, 1956)
Safeco Insurance Co. of America v. Burr
551 U.S. 47 (Supreme Court, 2007)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Hedges v. Musco
204 F.3d 109 (Third Circuit, 2000)
Guidotti v. Legal Helpers Debt Resolution, L.L.C.
716 F.3d 764 (Third Circuit, 2013)
Kirleis v. Dickie, McCamey & Chilcote, P.C.
560 F.3d 156 (Third Circuit, 2009)
Fowler v. UPMC SHADYSIDE
578 F.3d 203 (Third Circuit, 2009)
Quiles v. Financial Exchange Co.
879 A.2d 281 (Superior Court of Pennsylvania, 2005)
Pencheng Si v. Laogai Research Foundation Foundation
71 F. Supp. 3d 73 (District of Columbia, 2014)
Borough of West Mifflin v. Lancaster
45 F.3d 780 (Third Circuit, 1995)
Hutchins v. Wilentz, Goldman & Spitzer
253 F.3d 176 (Third Circuit, 2001)
Alston v. Parker
363 F.3d 229 (Third Circuit, 2004)
United States Ex Rel. Purcell v. MWI Corp.
807 F.3d 281 (D.C. Circuit, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
THE CHOWNS GROUP, LLC v. Grimberg Co., Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-chowns-group-llc-v-grimberg-co-inc-paed-2024.