The Century Indemnity Company v. United States

236 F.2d 752, 99 U.S. App. D.C. 19, 1956 U.S. App. LEXIS 4676
CourtCourt of Appeals for the D.C. Circuit
DecidedAugust 9, 1956
Docket12947_1
StatusPublished
Cited by4 cases

This text of 236 F.2d 752 (The Century Indemnity Company v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Century Indemnity Company v. United States, 236 F.2d 752, 99 U.S. App. D.C. 19, 1956 U.S. App. LEXIS 4676 (D.C. Cir. 1956).

Opinion

WILBUR K. MILLER, Circuit Judge.

In the Government’s suit against Century Indemnity Company to recover $34,-867.87 allegedly due from it as surety for Spencer Wire Company on an advance payment bond, the District Court awarded judgment for the amount claimed. The surety appeals.

By a contract dated February 9, 1942, Spencer Wire Company agreed to manufacture and sell to the United States a quantity of wire rope at a total price of $581,405.00, delivery to be made during that month. The Government agreed to make an advance payment of $145,351.25, and then to pay for each shipment upon delivery at stated unit prices, until the sum of such payments plus the advance payment should equal the total contract price; thereafter the remainder of the merchandise contracted for was of course to be delivered without further payment.

The contract provided for an advance payment bond to secure the repayment to the Government of the full sum advanced by it, or such part thereof as was not liquidated in accordance with the terms of the agreement. February 9, 1942, Century Indemnity Company, as surety for Spencer Wire Company, executed the advance payment bond contemplated by the contract in the penal sum of $145,351.25, and February 12, 1942, the Government advanced approximately that amount to Spencer.

Although the entire quantity of wire rope originally contracted for was required to be delivered during February, 1942, the requirement was not met by Spencer during that month or year. On January 2, 1943, obviously in order to expedite deliveries, the United States agreed to make an additional advance payment of $100,000.00. Century Indemnity supplemented its original bond by adding $100,000.00 to the penal sum, increasing it to $245,351.25. Thereupon, the Government made another advance payment to Spencer, after which the net total advanced amounted to $244,124.49.

Some six months after the second advance payment was made, and more than 16 months after the original contractual period for full delivery had expired, Spencer had delivered slightly more than half of the total requirement. In those circumstances, and at the request of the War Production Board, but without the knowledge or consent of the surety, the Government on July 14, 1943, wrote Spencer as follows:

“You are hereby directed to cancel the outstanding balances on the above orders. We will accept whatever material is now in process. However, every effort should be made to divert this material which you now have in production to other orders.
“Please acknowledge this cancellation to, Mr. Paul F. Schucker, Room 1354, Social Security Building, and advise him as to exactly how much *754 material you now have in process and the amount affected by this cancellation, item by item.”

When this letter was written, Spencer had made and been paid for deliveries aggregating $291,206.78, and had also received advance payments of $244,124.-49. The then unexecuted portion of the contract — $290,198.22—exceeded the advance payments by the sum of $46,078.73. Consequently, if the contract had proceeded to completion, the Government could easily have recaptured its advances out of deliveries.

By letter dated July 27, 1943, Spencer acknowledged the letter of cancellation without protest, and advised that it then had 44,000 pounds of material in process which would be delivered upon completion. Two deliveries thereof were made, one on July 28, 1943, in the sum of $13,-787.03, and the other on August 18, 1943, in the sum of $10,937.33. It thus appears that the material Spencer had in process when the letter of cancellation was written amounted to only $24,724.36. Despite the fact that unliquidated advance payments to Spencer then amounted to $244,-124.49, the Government paid in cash for the two post-cancellation shipments: $13,787.03 on August 6, 1943, and $10,-937.33 on August 24. It also paid Spencer $10,143.51 on July 21, 1943, for a delivery made July 12. These three payments, made after cancellation, total $34,-867.87, which is the amount in controversy here.

On January 27, 1944, the Government made formal demand on Spencer for $250,504.29, which included the advance payments of $244,124.49, and certain items not in issue here. Spencer did not respond but went into bankruptcy. Whether the United States proved its claim does not appear; at any rate, it received nothing from the bankrupt estate. On or about February 21, 1944, the Government demanded of the surety the sum of $244,124.49 1 under the advance payment bond. Century acknowledged liability for $209,256.52 and paid that amount August 14, 1948. It denied liability, however, for the remainder of $34,867.87, the sum of the three post-cancellation payments to Spencer, on the theory that instead of making these payments the Government should have retained them to apply on the liquidation of the advance payments. This suit followed.

The parties agree that the sole issue on this appeal is whether the surety was released from liability to the extent of the three payments to Spencer made after the notice of cancellation had been given.

By the terms of the bond, the surety’s liability thereunder was “conditioned upon the failure of the principal to make payment to the Government according to the provisions of the contract” between Spencer and the United States. The contract and the bond must therefore be read together to determine the rights and liability of the surety and the duty, if any, owed to it by the Government.

Spencer agreed in the contract that, on or before the original or extended completion date, it would “pay to the Government the full sum * * * advanced or such part thereof as shall not have been liquidated as hereinabove provided.” Thus the repayment obligation of Spencer and Century is connected with and dependent upon the preceding provision of the contract which governed the liquidation of the advance payments. That provision is as follows:

“All wire delivered to the Government under the contract shall, upon acceptance thereof by the Government, be paid for at the unit prices stated in the contract until the sum of the payments so made plus the amount of the advance payment shall equal the full contract price. All remaining deliveries of wire under the contract shall, upon acceptance *755 thereof by the Government, be paid for by crediting the value of such wire, at the unit prices stated in the contract, against the contractor’s obligation to repay the sum advanced, until such sum shall be completely liquidated.”

The imperative “shall” in the last sentence of the passage just quoted from the contract required the Government, after delivery payments and advance payments together equalled the full contract price, to apply the value of subsequent deliveries to the liquidation of the advance payments. To do so was a duty owned by the Government to the surety.

The Government argues that when it made the three post-cancellation payments, the total of delivery payments and advance payments did not equal the full contract price; that therefore its duty to apply the value of subsequent deliveries to the liquidation of advance payments had not arisen.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Russell Electric Co.
250 F. Supp. 2 (S.D. New York, 1965)
McQuagge v. United States
197 F. Supp. 460 (W.D. Louisiana, 1961)
Philip Krupp v. Federal Housing Administration
285 F.2d 833 (First Circuit, 1961)
Stephen S. Kelley v. United States
236 F.2d 746 (D.C. Circuit, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
236 F.2d 752, 99 U.S. App. D.C. 19, 1956 U.S. App. LEXIS 4676, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-century-indemnity-company-v-united-states-cadc-1956.